Cornell University Library TF 220.G22 Earthwork in railway wi 615 617 3 1924 004 , il ES ! a) Gornell University Library Ithaca, New York BOUGHT WITH THE INCOME OF THE SAGE ENDOWMENT FUND THE GIFT OF HENRY W. SAGE 1891 engr | THE GLASGOW TEXT BOOKS OF CIVIL ENGINEERING. Epitep By G. MONCUR, BSc. M.I.C.E. Professor of Civil Engineering in the Royal Technical College, Glasgow. EARTHWORK IN RAILWAY ENGINEERING THE GLASGOW TEXT BOOKS. Epitep sy G. MONCUR. EARTHWORK IN RAILWAY ENGINEERING BY JOHN W. F. GARDNER, M.Inst.C.E. NEW YORK D. VAN NOSTRAND COMPANY EIGHT WARREN STREET 1922 PRINTED IN GREAT BRITAIN PREFACE THE purpose of this book is to describe in a practical manner the underlying principles which control earthwork undertakings, so far as they relate to general railway work. It has not been possible in the limited space available to deal fully with certain matters and preference has been given to the points more directly affected by the actual constructional work. In view of the uncertainty of the character of the material to be met with, no hard and fast scheme of operations can be adhered to, and the methods of procedure hereinafter referred to should be taken more as a guide to what course or design to follow. The author would emphasize the importance of thorough con- sideration being given to drainage works, and matters relating thereto have been given special attention. The particulars in regard to constructional work are for the most part the result of experience gained by the author when acting as Resident Engineer under Mr. Donald A. Matheson, formerly Engineer-in-Chief, now General Manager of the Cale- donian Railway, and he takes the opportunity of placing on record his appreciation of the valuable assistance received from him. J. W. F. G. CONTENTS CHAPTER PAGE I. Prepiminary INVEsTIGATIONS anD Estimates or Cost 1 II. INVEsTIGATION aS TO STRATA . ‘ z ‘ 9 III. CuLverts anp DRAINAGE . ‘ ‘ . 18 IV. Execution or Eartawork : . 36 V. PLANT USED IN EXECUTING EaRTHWORK . i wm ACE VI. Sires in EARTHWORK AND THE MEANS TAKEN TO PREVENT THEM . : ie ‘ ‘i ‘ x 99 VII. Maintenance oF EARTHWORK . Z 7 ‘ - 127 VIII. Conpitions AFFECTING THE Cost oF HarRTHWORK . 184 IX. SpEciFicaTION . : : 4 : . . . 142 INDEX : s ‘i * ; ‘ ‘ ‘ . 149 LIST OF ILLUSTRATIONS FIG, PAGE 1.—Cutting for single line . 2 F ‘ : : : : Z 2 2.—Cutting for double line : . : 7 3 3.—Difference between cutting for aagle et downs lies 3 4.—Chisel boring 5 z : 12 5.— Crown ” of diamond drill . 3 . : 15 6.—Water openings in embankments s % ; 2 . 21 7.—Fire-clay pipe drains under railway és 2 ‘ 22 8.—Timber box drain under railway . : 7 : » -22. 9.—Built stone drains under railway. ‘ . é 2 : - 23 10.—Arch culverts under railway 3 : 2 ‘ . . 23 11.—Culverts with steel beams and concrete covering : é 3 . 24 12.—Pipe conduit under railway embankment on side-lying ground . » 25 13.—Stepped arch culvert on side-lying ground : 3 ‘ 5 - 26 14.—Design of ends of culverts. : : . 28 15.—Two water-courses conveyed in one iatuens wees railway § . 2 16.—Water channel diverted along contour of sloping ground 3 . 3 17.—Road and stream diversion carried under railway at one place - 82 18.—Syphon pipe under railway : j 33 19.—Pipe carried over railway on trestle ‘ 2 ‘ r . 84 20.—Pipe carried over railway on road bridge . ‘ 35 21.—Water-eourse carried over railway in open conduit . : . 35 22.—Stream and road carried over railway on one bridge . é . 35 23.—Contract—general plan . : : : . 38 24.—Contract—longitudinal section : 38 25.—Contract—cross sections 41 26.—Fixing slope stakes : . 3 ; . : . 42 27.—Area of cross section : é ° ; : 43 28.—Working longitudinal section p s 2 45 29.—Soft cutting overlying rock . a . . - 50 30.—Excavating cutting 10 to 20 ft. deep 2 3 . 52 31.—Width required by steam digger . x si 2 . . 53 32.—Leaving wings on gullet 2 é ‘ 2 i 5 . 53 33.—Cutting into slope 3 : : » 54 34.—Arrangement in cubine —thtes iitiee of ratbeaiy 3 ‘ . 55 35.—Arrangement in cutting—two lines of railway ‘ 56 36.—Arrangement at embankment end . : j . 57 37.—Method of expediting emptying wagons . 4 ‘ é . 658 xi xil LIST OF ILLUSTRATIONS FIG, 38.—Excavating rock 39.—Example of railway autting ( 1) 40.—Example of railway cutting (2) 41.—Example of railway cutting (3) 42.—Cross section of railway through bog land 43.—Section of railway approaching bog 44.—Widening of railway—single to double line 45.—Widening of railway—two lines to four lines 46.—Excavating rock by “ plug and feather ” 47.—Ruston steam crane navvy 48.—Ruston steam crane navvy 49.—Wilson steam crane navvy 50.—Wilson steam crane navvy (with bent jib) 51.—Ruston steam shovel 52.—Lubecker land dredger . 53.—Ingersoll-Rand rock drill 54.—Hand hammer drill 55.—Iron tip wagon : 56.—End and side tip wagons ‘ 57.—Drain for intercepting field drains id setone water 58.—Slope drains in cutting 59.—Large slope drains with toe wall at foot di dle 60.—Drystone dwarf wall at foot of slope 61.—Flat slope in loose rock cutting 62.—Face wall in rock cutting 63.—Retaining wall in soft rock cutting 64.—Slip of small dimensions in cutting 65.—Slip of large dimensions in cutting . 66.—Slip in cutting requiring special treatment 67.—Section in cutting with large volume of subsoil water 68.—Slip in embankment on side-lying ground 69.—Intercepting subsoil water under embankment 70.—Cross sections of British permanent way . 71.—Part cross section of Pennsylvania railroad, America 72.—Form of cost statement for earthwork undertakings . 73.—Detailed statement of cost and output of railway cutting . 74.—Diagram of cost and output of railway cutting ei PAGE 64 66 66 68 69 70 70 78 81 83 84 85 86 88 90 92 94 95 101 105 107 108 109 110 lil 112 112 114 115 121 123 128 132 135 136 137 EARTHWORK IN RAILWAY ENGINEERING CHAPTER I PRELIMINARY INVESTIGATIONS AND ESTIMATES OF COST THE location of a railway is for the most part governed by geo- graphical considerations, but the promoters of the undertaking will look more to the proposal from a financial point of view, and in their deliberations they will be guided by the Engineer as to the practicability and probable cost of the work. Various proposals will no doubt have to be examined before the scheme which is to be carried out is decided upon, and, in view of the importance attached to the Engineer’s report, it is essential that he be thoroughly informed in all matters which may influence the decision of his clients. While none of the proposals which are considered may be altogether impracticable, yet the carrying out of the project may only be done at a loss. It is impossible to foresee all the difficulties that may be met with during the progress of a particular work, but these may be very considerably reduced by more particular examination of the details of the project by the Engineer when the scheme is being developed. It has been truly said that ‘“‘ It is much easier to make an expen- sive railway than a cheap one under the same circumstances, and the object of every Engineer ought to be as far as possible to adapt the work he has to design to the results to be obtained.” In a through main line of railway, heavy works such as tunnels and large bridges will in all probability require to be executed in order that the curves may be as easy as possible, and steep gradients E.R.E.—B 2 EARTHWORK IN RAILWAY ENGINEERING avoided, and large expenditure may be justifiable, whereas, in the case of branch or secondary lines, the Engineer may have to be content with steeper gradients and sharper curves if he is to keep the cost within moderate limits. Consideration of each different project must, however, be governed by the particular circum- stances of the case. What may be an economically constructed railway in one place, may be a wasteful expenditure in another. Questions relating to location which are affected by trafic working do not fall to be considered here, and the preliminary investigations which are referred to deal with matters affecting the actual execution of the work. The estimated cost of the works which the Engineer prepares should represent to a nearness what the ultimate expenditure will be. The first cost of a railway may be reduced by making a detour, but, on the other hand, the annual outlay in maintenance or work- ing of the railway may be increased in consequence of the additional length to such an extent that no real saving will be effected. The expediency of making a diversion may arise from a desire to avoid interference with valuable property, or to save the expense of the construction of a large bridge, tunnel, river diversion, or other important work, or it may be that the materials likely to be met with in the cuttings or under the site of the embankments are of a treacherous character, or the cost of the earthwork may be excessive. These, and other circumstances, may have so added to the initial estimated cost of the shorter route as to make a diversion imperative, and it should be further noted that the more heavy the description of the work the greater generally is the after cost of maintenance. When considering whether the works should be constructed for Fie. 1.—Cutting for single line. a single or double line of railway or of a greater width, it should be kept in view that the cost of the earthwork is not proportionate to the number of lines of railway. PRELIMINARY INVESTIGATIONS AND ESTIMATES 3 Referring to Figs. 1 and 2 the areas of sections for a cutting 20 ft. deep and with the usual side slopes for soft material are for single and double lines 980 square feet and 1200 square feet respec- tively, the increase of the double over the single line section being Fic. 2.—Cutting for double line. about 22} per cent. This increase is represented in Fig. 3 by a vertical strip 11 ft. wide, and roughly indicates the increased cost of the earthwork with cuttings and embankments of an average depth of 20 ft. for a double line of railway over a single line of rail- way. The excavations for the greater width would cost a little Fic. 3.—Difference between cutting for single and double lines. less per unit of volume on account of the service roads and other temporary works and plant required during construction not being proportionately increased, and also on account of there being greater facilities for carrying on the operations, but for all practical purposes the same unit rate may be used in preparing the preliminary estimates of cost. If there is a likelihood. of the railway being widened at some future time it may be advantageous to acquire land for the wider line to begin with, although the construction of the wider line may be deferred to a future date. In the construction of the partial scheme the quantity of materials in the cuttings may be in excess of the quantity required to form the embankments, and the surplus excavated material should be deposited in the embankments for the ultimate 4 EARTHWORK IN RAILWAY ENGINEERING widening, or for station yards which may be contemplated in the future, if these are conveniently situated to the cuttings. In fixing the width of formation regard must be had to the future maintenance of the railway. The additional cost of constructing cuttings and embankments a foot or two wider so as to obtain better drainage in cuttings and greater solidity in embankments is small compared with the extra periodical expenditure in main- tenance incurred by the construction width being restricted. By increasing the width of a double line cutting 20 ft. deep and in ordinary soft material from 28 ft. to 30 ft., the quantity of ex- cavations is increased by only 34 per cent. The advantage of having sufficient width of formation is referred to in Chapter VII, page 130. Consideration must also be given to the curves and gradients of a railway. With a diverted or longer route, better gradients may be obtained than with the direct route, but with the latter there will probably be a better alignment. These matters will require to be considered from a traffic working point of view before the route is finally decided upon. In settled countries there is not the same opportunity for railways being made on constructionally economic lines on account of the proximity of valuable land and property, but in undeveloped countries where land is either given free or is comparatively cheap considerable attention is now being paid to the question of economics in construction which will undoubtedly effect large savings in carrying out the undertaking and also give a better return for the capital expended. In laying out the line of a railway or road, endeavour should be made to reduce the quantity of earthwork to a minimum, and the formation level should, consistently with other considerations, be fixed so that the quantity of suitable material excavated from the cuttings will just be sufficient to form the embankments. It must be kept in view that all unsuitable materials should be run to spoil and allowance also requires to be made for the quantity of excavations which may be used for constructional purposes. It is a considerable advantage to have the “lead” (haul) to embank- ment on a down grade and as short as possible. The cost of the work, as will hereafter be shown, is largely dependent upon the relative positions of cuttings and embankments. PRELIMINARY INVESTIGATIONS AND ESTIMATES 5 Under certain conditions it may be advantageous to run some of the materials which are quite suitable for embanking purposes to spoil embankment rather than run them for a considerable distance on an up grade. To make up the deficit of embanking materials thts caused, side cuttings or borrow pits may be necessary, and while this would incur the additional cost of excavation it may be a cheaper method to adopt. Where furnace ashes can be obtained in large quantities and at little cost no better material could be obtained for making an embankment and the work of depositing them can be carried on very speedily. An embankment constructed of ashes will also entail a minimum of expense in subsequent maintenance. The site of a spoil bank should be convenient to the excava- tions and have an easy access with a minimum of expenditure for wayleave, use of ground, subsequent restoration and for depositing the material. A mistake may be made by using moss land or other similar site where the ground can be cheaply obtained, as there may be considerable expense incurred in making up and constantly repairing service roads while the material is being deposited. The simplest construction for a railway might appear to be where the work is executed on side-lying ground, partly in cutting and partly in embankment, and with just sufficient material in the cutting to form the embankment. If the material excavated is of an earthy description and can be removed without any slipping on the upper side taking place the conditions would be favourable, but if, on the other hand, there is a tendency for the ground to slip by reason of the support which formerly existed having been removed, the work may be very costly to execute. This matter is fully considered in subsequent reference to slips. In skirting hillsides it is frequently found that the natural slope of the soft material overlying rock is inclined at the angle of repose of the material, and it is thus desirable under these conditions to have as little cutting as possible. The material necessary for embanking purposes could then be obtained either from adjoining cuttings where the surface was at such an angle as to prevent slips or it could be got from borrow pits. In the latter contingency the extra cost of side cutting would be incurred, but this course may ultimately prove to be the more economical form of construction. A usual practice in countries where there are severe snowstorms is 6 EARTHWORK IN RAILWAY ENGINEERING to dispense with cuttings almost entirely and thus avoid obstruction to traffic by snow blocks, the banks being made up by material taken from borrow pits. Apart from the question of snow blocks a railway on embankment is less costly to maintain. The side ditches in a cutting require to be kept clear of materials washed off the slopes or which may have collected, and which if not removed will tend to keep the formation of the railway in a wet sodden condition, to the detriment of the permanent way. In countries where timber is plentiful, ravines necessitating what would be long high embankments may be temporarily spanned by trestle-work so ag to speedily complete the line of communication, and at a later date the embanking materials would be deposited. Again, by following closely the line of a water-course the presence of moss, clay, or other soft material may be the cause of serious trouble, either in a cutting or in an embankment, and therefore the possibility of more material being excavated or more material being required for embankment than originally anticipated should not be overlooked when locating the proposed works. In rough hilly country, where there may be a large exposed surface of loose friable rock and boulders, the streams will, after frost and during torrential rain, carry in their course a considerable quantity of stones down the hillside which will be deposited on the plain below. If the railway were constructed on the flat land at the foot of the hill, any water openings would then be liable to be choked up, and the railway should, therefore, be constructed on the hillside where the velocity of the water is still great enough to carry the stones through the water openings. Further, the water-courses which are confined to narrow channels on the hillside will open out and spread over a wide area on the flat ground, which in flood-time will thus be under water, and if the railway were constructed on the low ground considerable damage might result before the water passed through the flood openings in the railway embankment. Reference to allowing flood water to pass entirely over low railway embankments is made in Chapter ITI, page 21. The cost of the undertaking will largely depend on the character of the materials met with during construction, and it is necessary that the fullest information be ascertained in regard to the strata. PRELIMINARY INVESTIGATIONS AND ESTIMATES 7 For the purpose of the preliminary estimates, this information will have to be obtained from general observations of the surrounding country, and from geological maps of the district, if these are procurable. In the absence of actual bores or trial pits on the site of the works, the depth of soft material overlying rock and the characteristics of that material would be more or less indefinite, but after such arrangements have been made as will allow of a complete series of bores being taken or trial pits sunk, the fullest particulars should be obtained. The cost of obtaining information in regard to the strata is so small in comparison with the results obtained that in work of any magnitude the question of expense should be a secondary con- sideration. The extent of land necessary for both cuttings and embankments is dependent upon the character of the materials in the cuttings and under the sites of the embankments. If the works are being constructed through or in the vicinity of valuable property retaining walls may be required to support the sides of a cutting, or reduce the area of land covered by embankment, and the cost of these contingent works has also to be estimated. The Engineer must keep in view the possibility of the materials requiring flatter slopes than would at first sight appear necessary and the probability of retaining walls having to be provided to retain the slopes within the land acquired or the necessity of more land being required than was originally contemplated. If more land has to be bought after the works are commenced a larger rate will most likely have to be paid for it. If these matters are lightly passed over the original estimates will in all likelihood be largely exceeded when the works are completed. In the initial stages of an undertaking it is generally necessary that secrecy be observed, and, in view of this fact, and also on account of the short time usually allotted for the preparation of preliminary enquiries, the estimates of cost may be of a somewhat incomplete description. An exact section of the ground may not be available, but sufficient information can generally be obtained from “ spot” levels of the more prominent points, and by making full use of the levels and contour lines which are laid down on Ordnance Survey maps. For the purpose of calculating the quan- tities of earthwork and for ascertaining the boundaries of the land. 8 EARTHWORK IN RAILWAY ENGINEERING required typical cross sections should be prepared, and in open country these might be at intervals of from three to five chains apart. In view of the approximate description of the preliminary esti- mates an ample allowance—say 10 to 15 per cent of the whole— should be added to the cost for possible contingencies, so that the total sum will prove adequate for the execution of the proposed work. It is better that this estimate should be over rather than under the actual cost of the undertaking, so that the promoters of the scheme will not be misled, but unfortunately it too frequently occurs that preliminary estimates are considerably understated. Where estimates of costs are subjected to the criticism of rival Engineers or Parliamentary Committees, and when the various details on which the figures are based are subjected to the closest scrutiny, it is most desirable that the assumptions both as regards quantities and rates should be well founded. After Parliamentary sanction has been obtained or agreements have been made with the proprietors of the land on which the pro- posed works are situated, complete longitudinal and cross sections of the ground should be taken and a thorough investigation made of the strata so that the exact line of the railway may be determined and a fully revised estimate of cost prepared. The quantities of the materials of this new estimate will form the basis for the subse- quent Contract Schedule and these should be as full and complete as possible. Special consideration should be given to the unit prices for each item of work. The probability of an increase of the cost of labour or materials during the period of construction and the possibility of interruption by reason of wet weather and conse- quent loss should also be kept in view. The magnitude of the work will also influence the unit cost. In works of small dimensions on which it would be unprofitable to place large and expensive plant the cost would be proportionately more than where mechanical excavators, etc., can be advan- tageously used. The more complete the information is that affects the quantities or prices the nearer will be the amount of the Contract Tender to the actual cost of the work, in which case the result will be more satisfactory to both contracting parties. CHAPTER II INVESTIGATION AS TO STRATA In earthwork undertakings the principal matter that affects the quantities and prices in the Detailed Estimate on which the Con- tract Tender is based, is the character of the strata under the site of the works, It is thus of the first importance that definite and reliable informa- tion be obtained in regard to the characteristics of the materials in the strata. The presence of water and the effect of it on the various classes of materials met with have an important bearing on the success of the undertaking, and particulars relative thereto should receive special attention. For the purpose of ascertaining the character of the strata it is usual to put down bores along the line of the railway or over the site of the works. Some Engineers consider that trial pits should be sunk, so as to get more complete information than is obtainable from bores. By the particulars so obtained the slopes for the cuttings are decided on and the quantities for the Contract Schedule calculated. The slopes in a cutting of ordinary material may vary from 1 horizontal to 1 vertical, to 2 horizontal to 1 vertical, while in a rock cutting from a plumb face to $ horizontal to 1 vertical, depend- ing on the character of the tinier the quantity of water met with, the effect of water or atmospheric conditions on the material when exposed, and the slope or “dip” of the strata. A description of the materials on the sites of the embankments is also essential for the purpose of ascertaining the bearing capacity, and fixing the quantity of material required for the embankments. If in carrying out the work there should be any great divergence in the actual quantities of materials in the cuttings from what was stated in the Contract Schedule the method of procedure may have to be modified. 9 10 EARTHWORK IN RAILWAY ENGINEERING As example, a cutting may contain considerably more rock than was at first anticipated, and on account of this it may be necessary to construct overland routes for the purpose of passing the material from other cuttings to embankments, and thus allow the oper- ations in the soft cutting to be proceeded with at the same time as in the rock cutting, or other special means may require to be adopted so that the work may be executed within a reasonable time. The fact of having an increased quantity of rock to excavate increases both the cost of the work and the time of completion and if definite information in regard to the strata had been forthcoming previous to the work having been commenced the Engineer might have considered a diversion of the route of the railway, or the promoters might have decided to abandon the project. When executing the widening of an existing railway it may seem sufficient to form an opinion as to the character of the materials in cuttings from the appearance of the existing cuttings. In the case of solid rock cutting no mistake may arise, but in the case of the ordinary soft material or materials of a “ faikey’’* character where the action of the weather may have very materially altered the adhesion of the particles or the surfaces to one another, it is not safe to rely too much on what is seen of the existing cuttings. In a case which recently came under the author’s notice the slope of the original cutting had a batter of 14 horizontal to 1 vertical, and to all appearance the cutting was of a clayey descrip- tion. On executing the work, however, the material met with con- sisted of close-bound gravel held together by hard clay, and was of such a character that it was quite impossible to remove it by pick and shovel. On account of the situation it was not possible to use a steam digger, and it was necessary to break up the material by blasting throughout the whole period of the operations. After the material had been exposed to wet weather the clay lost all its cohesion and the slopes had to be dressed to the batter for an ordinary soft cutting. At several places in the slopes minor slips took place on account of the “weathering” of the material. In another instance of railway widening a number of large pieces of rock protruded from the slope of the existing cutting, which gave every indication of rock being met with, but on the work * Similar in character to laminated shale. INVESTIGATION AS TO STRATA ll being carried out it was found that no solid rock existed and that a large number of loose stones were embedded in the slopes of the old cutting, so that the appearance of the original cutting was deceptive in respect of the actual condition of matters. In general practice boring is carried out by means of a chisel, samples of the material passed through being brought to the surface for inspection at intervals as the sinking operations proceed. Where more accurate information is required diamond drilling is adopted, in which case a solid core of the material passed through is obtained. By sinking pits the most reliable data as to the actual state of matters will be obtained, but the time taken in sinking pits of any great depth will, in most cases, be against this mode of procedure. Chisel boring is a very simple operation, and when the work is in the hands of a thoroughly skilled and trustworthy borer very satisfactory results are obtained. In chisel boring, owing to the importance of the information required, the work should be carried out by a reputable firm of borers under the direct supervision of the Engineer, who should keep himself fully conversant with the progress of the operations, and have repeated checks made of the depths of the strata entirely independent of the journal with which the borer afterwards furnishes him. He should also verify the depth of each bore immediately after it has been put down to the required depth. The borer should lay out for inspection samples of all the various strata passed through. By adopting such means the information so obtained will be as accurate as is possible by this method. It is unnecessary to describe in detail the whole procedure of chisel boring, and only a brief reference to the tools and the manner of use will be made. The bore hole is formed by repeated blows from a chisel (c) which is raised and lowered by manual labour (see Fig. 4). The tool is turned round in the hole a quarter of a circle after each stroke is made so that no two blows fall in succession on the same spot, and the material, after being thoroughly bruised, is brought to the surface by means of a “sludge” pump (f). ; In passing through ordinary soil, sand, clay without stones, or similar material the sharp edge of the tube of the pump is sufficient to pierce the strata, but where gravel, boulders, or 12 EARTHWORK IN RAILWAY ENGINEERING rock are met with the chisel is required. Where the material is exceptionally hard the cross-shaped piece, or “ riffle”’ tool (e), is used. The cutting tool is connected with the cross-head on the working platform by means of l-in. square section rods, which i Flood openings Longitudinal Section of Railway Cross Section of Railway shewing Pitching of Embankment Fia. 6.—Water openings in embankments. by forming the line on each side of the depression with an easy grade down to a level portion, which level portion might extend to from 100 to 400 ft. in length, as shown in the diagram. For the purpose of protecting the railway and the slopes on each side and between the sleepers, the surface would be covered with stone pitching which would extend for the whole length of the level portion and up the gradients to a level clear of flood level. DESIGN OF CULVERTS OR WATER-COURSES It is of the utmost importance that the construction of culverts and water-courses, where they pass under embankments, should be of a most substantial description in view of the expense and inconvenience incurred in opening up embankments for the purpose of executing remedial work. Existing conduits on the site of the embankment should be strengthened or reconstructed. When pipes are used for the pur- pose of carrying the stream, they should preferably be of iron or steel, and if they are not laid on solid ground they should be sup- ported on masonry piers or piles. On account of malleable iron or steel pipes being lighter than those of cast iron they can be made in longer lengths and consequently fewer joints are necessary. They are also less liable to injury than cast-iron pipes. In soft ground or where there is a tendency to subsidence by 22 EARTHWORK IN RAILWAY ENGINEERING reason of mineral workings malleable iron or steel pipes are prefer- able. The smaller weight per unit of length is also a consideration in cases where it is necessary to drag the pipes over fields or convey them long distances over secondary roads. Malleable iron or steel pipes, however, are more subject to corrosion than cast-iron pipes, and care should be taken to ensure that they are properly pro- tected by preservative coatings or by having them encased in concrete. Where fire-clay pipes are taken under a railway they should be 15'Dis' EC Pipes Concrete (a) (6) (c) Fia. 7.—Fire-clay pipe drains under railway. ‘Dia’ ECPip 10) Concrete encased in concrete (see Fig. 7). When concreting materials can be economically obtained a fire-clay pipe conduit is in many cases adopted in preference to cast iron, more especially in the smaller diameter of pipes. In conveying water from one side of a railway embankment to another when crossing bog-land, timber box drains are generally ax Bolts 12x3 (2x3 4 Cross Section Longitudinal Section. Fic. 8.—Timber box drain under railway. for——_— 9° 0 — used (see Fig. 8). While these may be considered to be more of a temporary character, if they are constructed of creosoted pitch-pine timber they will last for a number of years, and in the particular situation where they would be used they are easily accessible when they require to be repaired or renewed. For conduits of a less size than 2 ft. 6 in. square, and where pipes cannot be conveniently used, built stone drains are constructed CULVERTS AND DRAINAGE 23 (see Fig. 9). These consist of a floor of concrete with masonry walls built with cement and covered over with a slab or paving stone. The cover stones should be well bedded on the top of the side walls Stone Slab: he Paving Stone [Ss T Stone a! *o toa ge co ss N; 6k Fok 2: —L | el 9 hee 26 ood: = | Concrete iS | Conarete Ss (a) (4) al = # ‘oa i@ Tn ‘ sy} on Bk 16 —e 2-0 ake (6 te 2°0 bake 16 9 Ee Se (c) Fia. 9.—Built stone drains under railway. and close jointed with cement mortar in order to prevent banking material finding its way into the culvert. When the volume of water in a stream is greater than a 2 ft. 6in. ro" See ee ae Concrete od oon j ie 3°6 5:0 C—O pm Concrete ar (a) (6) Fiq. 10.—Arch culverts under railway. drain can carry masonry built culverts are adopted (see Fig. 10). These generally have an arched roof and are either wholly of con- crete or are constructed partly of concrete and partly with stone or brickwork. The particular materials used will be governed by 24 EARTHWORK IN RAILWAY ENGINEERING the facilities for obtaining them. Ferro concrete construction is now largely adopted, having either a rectangular or arched section. To ensure satisfactory results, however, it is absolutely essential that the materials used should be of the best description and also that every care be taken in the making of the concrete, Riveted malleable iron or steel tubes are sometimes substituted for built culverts. These can be obtained up to 6 or 8 ft. in diameter, and, being accessible for inspection and for painting or coating with preservative solution, they may, if proper attention is paid to the maintenance, be said to be equally as efficient as a masonry culvert. If one line of tubing is not sufficient to carry the stream two or more could be laid alongside one another. k2°6 8 TE Saeston: Longitudinal Section. Fia. 11.—Culverts with steel beams and concrete covering. When the headway above the bed of the stream where it passes under a railway or road is limited, the roof of the culvert could be formed with steel beams and concrete filling between them, or slabs of concrete with steel reinforcement could be used (see Fig. 11). These can either be built in lengths on the solid ground alongside and afterwards lifted into position, or the reinforced concrete can be formed in situ by placing timber between the side walls. The former method has the advantage that less timber is necessary, but, on the other hand, additional lifting power is required to place the slabs in position if they are made on the adjoining ground. When a culvert requires to be constructed in very side-lying ground and where there would be considerable flow the invert should be left rough, and, in this connection, whinstone pitching is largely used. In open channels, in addition to whinstone pitching being used for the purpose of checking the flow, some of the pitching stones can be set on edge at intervals and made to project above the surface to the extent of about 6 in., the object being to further reduce the velocity of the current. CULVERTS AND DRAINAGE 25 A series of steps at the end of a culvert would fulfil the same purpose, or a well or pool about 4 ft. in depth could be formed intercepting Drain 8 I [ 5 3 eh 3 3 ——— 2 S 8 E [ = So = a é ee o ry — {Ets Fia, 12.—Pipe conduit under railway embankment on side-lying ground. Coy et SFI a Sats ee rs a 3 =n és = = Ea es into which the water would discharge before getting into the regular course of the stream (see Fig. 12). When a line of pipes is laid on side-lying ground the pipes should 26 EARTHWORK IN RAILWAY ENGINEERING be supported by small masonry piers which, in the case of cast-iron pipes, would be placed on the lower side of the faucets, or the joints can be encased in concrete, as shown in Fig. 12, while if malleable iron or steel pipes are used the pipes would be held in position by having metal straps riveted to the tubes at intervals, the ends of the straps being embedded in concrete blocks. Any movement in the pipes would be attended with very serious results to the embankment overhead. In the case of a culvert built on sloping ground the foundations should be laid on level benches while the water-run would either follow the grade of the side-lying ground or could be stepped, and if the ground has a very steep slope the arch would also be built Railway Embankment we oe A Culvert vee Fra. 13.—Stepped arch culvert on side-lying ground. in level sections (see Fig. 13). The level crown, while allowing of level beds being formed in the masonry, would also act as a support to, and prevent slipping of the embankment. Where culverts are constructed on soft ground they should be carried on piles and built in lengths of from 20 to 30 ft., each length being entirely disconnected from the adjoining one except for a cement joint, the idea being that in the event of unequal subsidence taking place by reason of the weight of the embankment on the top, the culvert will not be subjected to the same risk of damage. In the event of subsidence taking place the joints between the various lengths can be made good. Even in good ground—except solid rock—it is well to build the culvert in sections when under high embankments, as there will be subsidence, however slight, due to the weight of the embankment on the strata under the culvert. CULVERTS AND DRAINAGE 27 This suggests that culverts under high embankments should be built with a vertical camber, as is sometimes done to allow for the varying subsidence which may be expected from the greater weight under the centre of the embankment. If the culvert is constructed on the level and subsidence takes place the hollow in the centre will become silted up and the effective water area will thereby be reduced. Tn fixing the line of a culvert under an embankment it is better that it should be constructed by cutting into the sloping ground on one side of the natural run of the stream and thus have a smaller side surface area exposed to the pressure of the made-up embankment, as at Section B, Fig. 15. There would also be less risk of damage to the culvert by reason of any slipping of the material of which the embankment is composed. The length of culverts under high embankments should be such as will allow of the slopes of the embanking material taking the natural angle of repose. The invert of the water channel between the walls at both ends should be pitched with stone, and at the inlet end the pitching should be laid on a bed of concrete made continuous with the concrete foundation of the inlet walls. A concrete apron should also be formed at the inlet end for the pur- pose of preventing the invert of the culvert being undermined by flooding, as shown in Fig. 12. Culverts and waterways should be protected by having a grating placed at the upper end to prevent debris or floating branches of trees choking the culvert and obstructing the flow. These gratings or gates should be placed far enough back from the entrance to the culvert as not to reduce the available area of the waterway or in any way obstruct the free flow of water into the culvert. Special attention should be given to the design of the ends of the culvert in order to obtain a maximum efficiency (see Fig. 14). The best results are obtained when the inlet has a bell mouth shape and where the approach channel is at the same level as the invert of the culvert. All obstruction by forming corners in the masonry should be avoided. The most objectionable form of inlet would be to have the walls at right angles to the line of the culvert as at (A), Fig. 14, in which case the water entering the culvert forms an eddy, which is a serious obstruction to the free flow. The walls at the outlet end should be carried straight out in the line of the culvert or 28 EARTHWORK IN RAILWAY ENGINEERING Intet End. Elevation. Outlet End.Elevation. ee ee roe mee | o Inlet End. Plan. Outlet End Plan. Yor ‘ pn (A) Level Line A LhApron Inlet End. Section AA. Fira. 14.—Design of ends of culverts. a ae ” CULVERTS AND DRAINAGE 29 bell-mouthed the same as the inlet end so as to take the water clear of the culvert. Culverts should, wherever possible, be straight and have a uniform grade throughout. Under certain circumstances it may be possible to convey water from two or more water-courses into one culvert and thereby reduce the number and length of culverts under the railway or road (see Fig. 15). Where it is necessary to take the waterway in Din, EMO OOH a0 Lisa a 4 Ss Sroung c& ae so S SS Concrete Section B Fic. 15.—Two water-courses conveyed in one culvert under railway. an open channel alongside a railway embankment the bottom and sloping walls of the channel should be pitched with hand-set stones and grouted with cement to prevent damage to the railway embank- ment. In constructing culverts under embankments it is a common practice to place them in the line of the water-course at the bottom of the valley to be crossed and consequently at the highest and widest part of the embankment. In this situation the culvert may be of considerable length, and the first cost of it, 30 EARTHWORK IN RAILWAY ENGINEERING as well as the subsequent maintenance will form an important item. Where the ground is comparatively flat there may be no alternative, but where it is side-lying and where the stream has a rapid fall it may be possible to divert the water- course on the upper side of the embankment and carry it in open cut or built culvert with very little cover along the contour of the sloping ground and with just sufficient fall to properly carry away the water and thereby cross the railway at a much narrower point (see Fig. 16). By doing so the length of the portion under the rail- way or road may be very considerably reduced and the part of the conduit in open channel or built culvert would be easily accessible for the purpose of repairs or for the cleaning out of debris which might be washed down. It would, of course, be better that the whole length of the approach conduit should be in open channel, but this may not be possible. If it can be arranged to have the crossing of the railway or road at the junction of the embankment with the adjoining cutting, the length of the covered channel would be reduced to the width of the formation of the railway or road. The pressure on the arch or upper surface of the culvert would also be reduced to a minimum as the load would only be that due to the weight of the material of which the railway or road surface is constructed, with in addition the live load due to the traffic passing over it. If the stream or water-course is diverted in a manner similar to what has been indicated, the level of the discharge end of the waterway will be considerably higher than the original course of the stream, and it will thus be necessary to construct a series of steps in the part of the channel on the low side of the railway to break the flow of the water, as shown on the diagram, over which steps the water would discharge. If the excavations should be in rock, the discharge would be over a rocky surface and no building would be necessary in forming the water channel. When diverting a stream from its original course it is necessary to guard against the forming of abrupt corners in the altered channel, which would cause an obstruction to the flow of water, and an endeavour should also be made to have the altered channel constructed so that the flow at the point where it connects with the original course will be as nearly as possible what it was previous to the stream being interfered with, as otherwise damage by flood- eae = © Sst] SS >< | ad 7 ——— —— aS$N09 JI7EM —“— a 0 YOIzeUll Se] —_— = Lge eT EN > SS | ai 3 ESA it Z SSM = -—— pat i | | a ee | =e, OSE | EEE S77 \\\ ! 3 Os 8H, \\\ \\ } ade Lp me : : ~~ a2] oe \ \ © paqseaip 8g C7 UESIS o ACM ERA < ~ ere es pee wos SON Bs ba ees $ yy < 7 2 = z / 3S Sees SS) ae ° 3 Li si || QOS. . gy est let] Ee, SN) / o 8 8 so2 Lee SS oer wn 9 ‘s 5 x Ys \’ i co = Fy j 3 BALD, [i caf Wy pun 124/09 /D ays TULA) | SN : =o = i 5 Ry ¢ = = oS A< Pas == Hes ss | eee: a Ht Sf f= 8 puede In S BEUNOD JAIEM J FE S== DRK—lY Ov quawaouvaliwoy ESS ka 18. n en SectianC.C Fia. 16.—Water channel diverted along contour of sloping ground. 32 EARTHWORK IN RAILWAY ENGINEERING ing may result to the lands either higher up or lower down the stream than the site of the culvert. In order to prevent the lodgment of water on the upper side of the embankment between the level of the diverted water channel and the original level of the stream where it passes under the bank, the ground should be made up to the level of the diverted water channel if this can conveniently be done, as shown in Fig. 16, the oe Ps Y/ St 7 Versio. mM cversion\ ad diversion 08d di Stream diversion / Seetion A.A Section B.B Fic. 17.—Road and stream diversion carried under railway at one place. embanking material used for the purpose being well consolidated s0 as to prevent surface water damaging the embankment. If the filling up of this area is too extensive an operation it will be necessary to lay a pipe or construct a small culvert under the railway embankment to drain this ground. Every care must be taken in diverting the water-courses to see that there is no drainage left along the original course under the railway embankment, as serious damage may result through the material becoming sodden and slips taking place. CULVERTS AND DRAINAGE 33 Under certain circumstances it may be possible to take a road and stream under the railway at one place by a bridge as shown in Fig, 17. Where the water-course is at a higher level than the formation level of the railway and has to be carried across the railway, it will either require to be taken under the railway in a syphon pipe or over it by means of a pipe or box conduit. A syphon would be adopted where there was not sufficient headway for railway traffic to allow of the conduit being taken overhead (see Fig. 18). The pipes forming the syphon would be of iron or steel and the joints made watertight, and the piping would require to be capable of withstanding the pressure of the head of water caused by the difference in level of the top and bottom of the cutting, in addition to any other pressure to which it may be subjected. Lower Upper End, E0d ao oe ji geese! 3 2 1] Tt ete Scour Fipe Fic. 18.—Syphon pipe under railway. When the pipe or conduit is carried over the railway it would be supported on a trestle bridge, or on a road bridge. If supported on a trestle, as at Fig. 19, there is a danger of drivers or firemen of trains meeting with accident when engaged taking coal from the top of the engine tender, owing to their not observing the pipe as clearly as they would the girder of a bridge. By reason of this, and also on account of the extra cost involved in constructing the piers and framework of a trestle it may be preferable to divert the water-course so as to cross the railway on an overbridge if there should be one near at hand. In Fig. 20 the pipe is shown carried over the railway on a road bridge, being supported on the outside of the main girders. If the water-course is larger than can be conveyed in a pipe it can be taken across the railway in an open conduit (see Fig. 21). The author has knowledge of a case where a stream and farm road were carried over the railway on one bridge (see Fig. 22). Instead of conveying the water across the railway by any of the methods described it might be taken down the slope of the cutting E.R.E.—D EARTHWORK IN RAILWAY ENGINEERING 34 “OG YO!QDaG O *o]4801} uo AeMTTeI JoAO palireo odig— 6] “OL w 2 UR}g Weg i b> fees po (a h ‘ : ' bold | ee t i _——r y a i a: gy 7 bye i || od Hacer: ? aim IE foorn IL i tor ir > ae ; | S| a mi ee ‘BIJSOuy JO uoIqzeAd}yA Ue >» a : = a + Tk 170 Ss Lp eee Tr —— =a = ’ fT = CULVERTS AND DRAINAGE 35 either in an open stepped conduit or in a pipe and led alongside the formation of the railway into a watercourse at the end of the cutting. This would, of course, necessitate the making of the formation of the railway wide enough to take the conduit in addition to what is required for the actual construction of the railway, and the additional cost involved might be prohibitive. Fic. 20.—Pipe carried over railway on road bridge. Where a railway is constructed through a town, water, drainage, and gas pipes will have to be dealt with, and provision made for them when designing the bridges carrying streets over the railway or other work. The question of what drainage works are necessary for the pro- tection of cuttings and embankments of railways is dealt with in Chapter VI. 4 Surface of Farm road Water Channel Water Channel Limmer Asphalte A J Water Channe/ Loncrete SI i lonmenMaphalte Rolled steel joist Section of Bridge. ‘Rolled steel ols C onceete ige steel joists Fic. 21,—Water-course Section A. carried over railway Fig. 22.—Stream and road carried over in open conduit. railway on one bridge, CHAPTER IV EXECUTION OF EARTHWORK For the execution of the work there will be a Specification, Schedule of Quantities, and Contract Drawings. SPECIFICATION The requirements of the Contract Specification are referred to in Chapter IX, and it will only be remarked here that so far as the descriptive clauses are concerned they should be as full as possible, both as regards the manner in which the work is to be executed and the quality of the materials used in construction. SCHEDULE The general practice in preparing a Contract Schedule is to detail as fully as possible the various items and quantities of work to be executed in carrying out the work. Under the heading of “ Earthwork ” the quantities of materials, whether in road or railway cuttings and embankments, with their situation in relation to the mileage marked on the general plan and section hereinafter referred to, should be separately stated. Where there is rock in any of the cuttings there should be a separate item. The quantities of materials in each item of work in bridges, stream diversions, and culverts should also be scheduled in detail. Sewers and drains which will be distributed generally all over the work should be grouped together under one quantity for each item. Under the heading of “‘ Sundries” there should be included general work such as office accommodation, the setting out of works, scaffolding, watching, lighting, etc. 36 EXECUTION OF EARTHWORK 37 The Schedule when read with the Specification should leave no doubt in the mind of the Contractor as to the character and extent of the work to be executed. In so detailing the Schedule the Engineer furnishes the Con- tractor with all the information at his disposal, and the Detailed Estimate when priced, on which the Contract Tender will be based, will give, so far as can be seen when the work is let, what the actual cost of the undertaking will be. CONTRACT DRAWINGS The drawings with which a Contractor is furnished to enable him to execute the work usually consist of a general plan, a longi- tudinal section, a sheet or sheets of cross sections, and detailed cross sections giving width of road-bed or formation, depth of ballast or road forming, the size of side ditches or water channels, drains, etc. He will also be furnished with typical drawings of culverts and drains for the general drainage of the adjoining lands, and drawings of special culverts or aqueducts for conveying water-courses over or under the railway. The plans should be as complete as possible. GENERAL PLAN (see Fig. 23) The general plan is generally prepared to the scale of the Ordnance Survey of 25344 ins. to a mile (gs), or a somewhat similar scale if an Ordnance Survey does not exist, but where there are few divi- sions of land a small scale plan can with advantage be used. The plan should show the boundaries of adjoining properties, the centre line of railway, the boundary fences on each side, the radii of the curves, and the mileage measured along the centre line relative to a fixed point. The situation of the principal road and river diversions and how they are to be taken over or under the railway, culverts, and important water-courses crossing the railway, should also be indicated on the plan, and a reference should be made at each bridge or other work to the number of any detailed draw- ings of the same. Dimensions should be marked on the plan fixing the exact position of the straight portions of the railway relative to existing buildings or fences. No mileage distances EARTHWORK IN RAILWAY ENGINEERING 38 ‘UOTJOOS [VUIPNyISUOT—povIJUON— "FZ OL ? € 2 ! Sali § Z : WNIEG FIUEUPTO aA0ge F337 OG UT 0 9't' | se aWi0y 56-85, | aay 7 Gian 0-6 — “96M qaas abpisg aes abpisg Guimes wieIg YING 9 qwaayny , Gg Sulmesg aas ‘ued jeroues—jov1yu0QN—'eg ‘DIT “Goh wa / as fem2y sano aborig EXECUTION OF EARTHWORK 39 should be given to the commencement or termination of the curves as the radii will determine their exact position on the straight portions of the line at each end. The positions of the boundary fences which are ascertained from the cross sections should also be indicated by dimensions from the centre line ; and so that the fences will be erected in uniform lines it may be necessary to modify somewhat the widths obtained from the cross sections. LONGITUDINAL SECTION (see Fig. 24) “The longitudinal section will show a profile of the natural surface of the ground along the centre line and also the formation level of the railway. It should be plotted to the longitudinal scale of the 25-344 ins. to a mile Ordnance Survey, or to a somewhat similar scale, and to a vertical scale of 1 in. equal to 20 ft. It will be a convenience if the horizontal scale is the same as that of the scale of the general plan. The various gradients will be marked and also the height of formation relative to Ordnance datum at each change of gradient. For convenience of calculations in the field the gradients should if possible, be stated at a regular figure per chain (66 ft.), per 100 ft. or per 20 metres according to the particular measure of distance in use. As in the case of the general plan, the mileage of the line should be marked on the section as well as the position of principal bridges or culverts and a reference to more detailed drawings. While the datum line of the section may for convenience be above or below ordnance datum, all levels marked on the section should be the height in relation to ordnance datum. When fixing the level of formation endeavour should be made to get the quantities of the materials in the cuttings and embankments to balance so far as is consistent with the character of the materials, keeping in view that certain quantities of the material may be suitable for building, road-making, or other uses on the Contract, and also that the excavated material will not occupy the same volume in the embankment as in the cutting, and that an allowance will require to be made for bulking. As regards the allowance made for “bulking” of the excavations, it is usual to assume when preparing the Contract Schedule that the material 40 EARTHWORK IN RAILWAY ENGINEERING in a thoroughly solid embankment will occupy from 3 to 5 per cent more volume than it formerly did in the cuttimg. The “bulking” of rock taken by itself may be as much as 40 per cent, but as the quantity of rock in railway embankment is generally a small proportion of the whole, the figure of 3 to 5 per cent above stated may be taken as a fair average for all classes of material. Regard should also be had to the desirability of having the material from the cuttings run down the grade to embankment and with as short a “lead” (haul) to embankment as possible, and it should also be kept in view that the intervention of a rock cutting which will take longer to excavate than a soft cutting, or of a tunnel or viaduct will probably delay the excavations. For the more effective drainage of the permanent way it is also desirable that the line where through cuttings should have a slight fall to one or both ends of the cutting. Ata change of gradient a vertical curve should be introduced so as not to have a sudden change when passing from one gradient to another. The maximum or ruling gradient will be influenced by traffic requirements, but it is necessary that the line where through stations, or where sidings join and where it may be necessary to have carriages or wagons standing on the Main Line, shall not be on a steeper gradient than 1 in 260. Where the horizontal measurements are in chains (66 ft.) it is usual to make this gradient 1 ft. in 264 ft. (4 chains). CROSS SECTIONS (see Fig. 25) The cross sections should be plotted to a natural scale of 1 in. equal to 20 ft., so as to correspond with the vertical measurements of the longitudinal section. For the purpose of ascertaining the quantities of material in the cuttings or embankments required for the contract schedule of quantities, and also for determining the position of the boundary fences, cross sections should be taken at every 66 ft., 100 ft. or 20 metres, according to the particular measure of distance in use. Cross sections should also be taken at intermediate points where the ground is irregular in order that the quantity of earthwork may be more correctly ascertained. For the Contract sheet of sections it is sufficient to give sections at every 3 or 5 chains apart, the object being to give the Contractor a general idea of the character of the work. The cross sections EXECUTION OF EARTHWORK 41 will show the surface of the ground, the slopes of the cuttings or embankments which have been determined upon after considera- tion of the character of the strata obtained from the bores or trial pits previously put down, and the boundary fences will be placed from 7 to 10 ft. back from the top or bottom of the slope according to whether the line is in cutting or embankment. Another method is frequently adopted in this country—and usually in America—which would avoid the necessity of taking cross sections at every peg (except at points where the ground is Fia, 25.—Contract—cross sections. (a) In cutting. (b) In embankment. very irregular) and still give the same information, viz. side widths, edges of slopes, areas of cross sections, and cubic quantities of earthwork. Having completed taking the levels along the centre line and obtained the reduced level of each peg and of the formation level, the heights of embankments and depths of cuttings are known. The Engineer then proceeds to set out and drive the slope stakes opposite each peg, directly on the ground by means of a level, staff, and tape line. To illustrate the method (see Fig. 26) an embankment 10 ft. deep will be assumed, 30 ft. wide at formation, and having slopes of 1} to 1. The level is set up conveniently on the higher side of the centre line, the staff is held on the centre peg A and reads, say, 12-50. The staffman then proceeds to some point B, which should 42 EARTHWORK IN RAILWAY ENGINEERING be fully 30 ft. [15+(10 x 13)] from A since ground slopes downward. The horizontal distance A to B is measured and found to be 36 ft., and the staff reading at B is, say, 14-50. Assuming for the moment that B is at the bottom of the slope, the corresponding distance A to B can be calculated. Since A C=10 ft., therefore C D=2:5 ft. and B H=(14-5—2-5)=12 ft., ie. the height from formation to assumed bottom of slope. The distance from A to B should therefore be (12 ft. x 14)+ 15 ft. =33 ft., but as it was actually measured 36 ft., this at once indicates that the staffman must move back nearly 3 ft. towards A. This is done and a second reading of staff at F is taken and same computation made. An expert stafiman can frequently obtain the point with sufficient accuracy at the second shot. The bottom of the other slope is similarly obtained, and the Fic. 26.—Fixing slope stakes. whole operation for one centre peg can be completed in com- paratively few minutes. The same plant for the instrument will usually be sufficient for several pegs on either side of it. The areas can be readily obtained (see Fig. 27). The hatched area OS T is a constant for each cross section, AC is given, the horizontal distances A F’ and A M’ are measured and OC can be computed. The area FSOTM is therefore equal to ae x40 AM’xAO AO AO =—g (AP +AM)=>- xF'M’, and by deducting from this the hatched portion the area of the cutting is obtained. Since these areas are computed from actual field measurements it eliminates any error in plotting or scaling cross sections. A special form of field book ruled in columns is generally used for entering up both field work and computed areas and cubical contents of each cutting or embankment. There are columns for chainage, peg level, and formation level, also a column giving the height of formation, above or below EXECUTION OF EARTHWORK 43 centre peg and slope pegs, and the distances of the latter from the centre peg are also noted. When a new line of railway is being constructed it may be advan- tageous to acquire sufficient land to allow for future widening, say, from a single to a double line, or if the line is at first constructed for a double line of railway it may be considered desirable to acquire sufficient land to allow of two additional lines of railway being subsequently provided for future developments. By doing so the land will no doubt be more economically acquired and save the inconvenience of having to obtain further Parliamentary powers or making additional agreements with landowners. Inci- dentally, it may be remarked that the extra width of land so obtained may be conveniently utilized for a service railway or over- F Fria. 27,—Area of cross section. land route for use during construction of the railway, which other- wise would probably have had to be constructed on land temporarily acquired outside of the boundary fences of the railway. The contract drawings for culverts and drains will be more or less of a general character, as the particular circumstances in each case can best be determined when the works are in progress. In works involving the construction of earthwork and masonry it is desirable that operations should commence in the early spring- time. It is thus important that the contract specification, schedule, and drawings should be completed some months pre- viously so that the Contractor may have ample time to prepare his tender and also that the Engineer and his clients may be able to give due consideration to the Contract Tenders, and, further, that the Contractor may have full opportunity to mature his schemes for carrying out the work and bringing forward plant and materials. By this means the work would be begun under the most favourable auspices and full advantage would be obtained of the best season of the year. 44 EARTHWORK IN RAILWAY ENGINEERING SETTING OUT OF LAND AND WORKS The first operation in the actual construction is the setting out of the land and works. Under the Contract Specification the Contractor is held responsible for the accuracy in position of the works, but in view of the possible legal questions which may subse- quently arise as to the boundaries of the promoter’s property, it is better that the centre line and the boundary fences be marked off jointly between the promoter’s Resident Engineer and the Contractor's Engineer without in any way prejudicing the pro- moter’s position in the matter or relieving the Contractor of his responsibilities. The centre line of railway should be marked off by having pegs about 14in, square by 15ins. long driven into the ground at distances of 66 ft. apart, or other convenient length. Where the line is across a tock surface chisel markings should be made or iron spikes driven. The distances along the centre line would be made continuous throughout the whole length and the mileage would be indicated on flat pieces of wood or stakes 3 ins. wide by ? of an inch thick, placed immediately behind each peg. The straight portions of the line would be laid down accurately to the dimensions marked on the contract plan and the curves put in to the radii marked on the plan. The pegs on the straight portion would be ranged out by means of a theodolite between the fixed points laid down from the general plan, and the pegs on the curves by deflection angles from the tangent points, transition curves being introduced where required. The intersection points of the curves will in all prob- ability be outwith the boundary fences, and it is therefore most important that the tangent point at each end of the curves should be very carefully marked. This is usually done by having a larger peg for the tangent points and placing a smaller one on either side transversely to the centre line. The tangent points should be transferred to other pegs or fixed points in the line of one of the boundary fences, the distance to the same being entered in a setting- out book specially used for the purpose. All measurements taken in connection with the fixing of the centre line or transference of the marks should be made with a steel band tape, and for setting out purposes a 5-in. theodolite is very suitable both for accuracy and for convenience in use. For EXECUTION OF EARTHWORK Ofen Omg aes PyNTAp ous Ce cea sea » LOOT LOGE HLOLT peceapey Sear Dab e990 wr Gay BBG BRIE ees 28 LIL IU tek 00-050 1ist 7 _ ORO ERG EFESE G60 19-86 79592 cusseneiaa she dg ccs easel 02 00-90 11892 | a en OS ae 1 1 : ' ' | IG-2 CEL PES | , ! 29 PE /PAT IBY CO T*L9 eb «ERE | cern ee lpg (ete eeee | ' “| 849 oer BSE | OR) ee PON ~~ 19 ePL ES CE | we at See DCS ~~ Lg 2H BONE q TOTO CELT 1 92bL SESE : BG) 9 Eb EF EE : PR gg EEL EF BET eae {pea 19H EE i OS HB 19 BR ES TAT | ppaaececeveeeee-fp-pLoPD Oy PTT TOM TF 20 TB GL PUB MD § ~"P" 9RS) 0 G2” HILT Bie "epi EBERT P8EE eyes fo [sew Ieee” z08 ' Siig feeswaceoesoe pote cy cael eee ae 4 lS 196 OO bl EE-HET ' ee 500 ~~ eboet B21ET fT [ “giz Lg HE 16 HE | Re) cptikror ree 165 00560 38050 ~) nS ieee ee Berea IT CES BGT | ap ee ee ra Se 1211 L9-5¢ BIT S| hd Serra Sh 07 06-902 C09 q ! ff et SABRE BRS sae? Se Id] Sisto We oe es Pacayte 96 i 19 9 27 2 S| 1 2k aN ee ee Nicely le oan arenes aie np east | i ' 1 i ' ' ' i os 4 2°62 4 ee 3s = = y SS = 34 i 2§ S$ §§ & = g 8s a. Fra. 28.—Working longitudinal section. 45 46 EARTHWORK IN RAILWAY ENGINEERING approximate determination of intermediate points on a curve the method of chords and offset measurements may be used, but the exact position of any point either on a curve or straight should only be determined by means of the theodolite. The levels of the centre line pegs should thereafter be taken, and a working longitudinal section prepared (see Fig. 28) on which will be marked the level of each peg, the calculated formation level of the railway, and the depth of cutting or height of embankment below or above the level peg. It is usual to indicate the peg and formation levels in black figures, the depths of cuttings in red, and the heights of embankments in blue figures on the working section. When the railway covers a large tract of country a small scale map, preferably 6 ins. to a mile ordnance, with the cutting and banking materials indicated along the centre line in red and blue colours respectively, is very useful for general purposes in locating the site of the works. When the centre line has been finally laid down on the ground, the boundary fences should be pegged out from measurements previously marked on the general plan. The enclosing of the promoter’s property by the erection of walls and fences should be entirely completed before any of the other constructive works are proceeded with, and with a view to protecting the centre line pegs it is desirable that the boundary fences should be erected as soon as possible after the position of them has been marked off. Previous to constructional operations being proceeded with at any section, each of the centre line pegs for the length to be inter- fered with should be carefully transferred to fixed points on the boundary fence, so that their original position on the centre line can be obtained at any time as the work progresses. The levels of the pegs should also be transferred. These transfer pegs should for convenience be placed all to the one side of the centre line, and the particulars of situation and level should be noted in the setting-out book. Considerable inconvenience and expense to the Contractor is incurred when it is necessary to remove only a few inches of material from the slope of a cutting after it has once been dressed off to a regular batter, and it is thus most important that the information furnished by the Contractor’s Engineer should be strictly accurate. EXECUTION OF EARTHWORK 47 CONSIDERATION OF GENERAL SCHEME OF OPERATIONS Before proceeding with the actual operations on a contract of any considerable magnitude the Contractor should carefully con- sider the manner and order in which he proposes to execute the whole work and the various portions of it. He will have looked into this matter in a general way when pricing his Schedule, and when the time limit within which he promised to execute the work was under consideration ; but in view of the short time generally allowed to prepare his Tender the modus operandi will require to be revised, and the whole question again gone into. In contracts of other than the smallest dimension, it is unusual to enumerate in detail the minor works to be executed, such as provision of drainage of adjoining lands, the carrying of small water- courses over or under the railway, the diversion of gas and water pipes or electric cables, the construction of roads and bridges necessary for the accommodation of the lands intercepted, ete. While the greater number of these works are necessary for the proper execution of the undertaking, certain of them will require to be determined by agreement with the proprietors of the land passed through, or with public bodies, involving legal formalities. The time so taken up, together with that occupied in the preparation of special drawings, would very seriously delay the commencement of a contract if it were necessary that these should be finally decided upon beforehand. The Contractor must, there- fore, keep in view the probability of such works being necessary and his operations should be regulated accordingly. In terms of his Contract Specification the Contractor may require to take the whole risk of the materials in the excavations or under the sites of the embankments proving different from what he anticipated. While the journal of bores which the Engineer has had prepared previous to the Contract Schedule being made up, and to which the Contractor has access, may correctly represent the character of the materials in the strata at the points where the bores were put down, in view of the importance of the matter, the Con- tractor may think it desirable to obtain further information by putting down additional bores, or sinking trial pits. If he decides to do so he would put the work in hand immediately after getting 48 EARTHWORK IN RAILWAY ENGINEERING the contract, so that it could be going on simultaneously with the other preparations he is making for having the work commenced. The result of this check may not materially affect either the total value of the work or the time within which the work can be executed. It may, however, alter the order in which it was originally proposed to execute the work and also the disposition of the neces- sary plant, and it may be found that the expense of putting down these additional bores was fully justified. With the information previously obtained when making his Tender, supplemented by the additional particulars he himself obtains, the Contractor will lay out his works in a manner best suited to fulfil the considerations which influenced him in pricing his schedule in respect of the depositing of excavations in the nearest embankment and other points already referred to. He will first direct his attention to those cuttings which take the longest time to excavate, or from which he expects to obtain building material for use on the work. So that the work may be carried on both expeditiously and economically it may be necessary to proceed with cuttings at more than one point simultaneously. SERVICE RAILWAYS Tn addition to the ordinary lines of service railway required for the removal of the excavations from the cuttings to the embank- ments it may be, as already stated, necessary to lay overland routes to take the excavations from the euttings to the embank- ments past rock cuttings or the site of viaducts or tunnels under construction. If there is not sufficient space within the boundary fences for the overland route, additional land will have to be temporarily acquired either by the powers of the special Act of Parliament under which the works are being constructed, or by agreement with the land proprietors. Apart from the possible necessity for a service railway or overland route for the removal of excavations, a line of communication is essential for the con- veyance of constructional materials required for bridges, culverts, etc., along the line, and for general convenience. This temporary railway should be laid with a light section of rail, generally flat bottomed, and weighing from 40 to 50 lb. per yard, and would be fixed to light sleepers. The rails should EXECUTION OF EARTHWORK 49 be placed to the gauge of the railway with which the new line will connect so that building and other materials can be brought for- ward from the existing lines of railway to where they are required without the necessity of transhipping them. Generally the sleepers of the service railway will be laid on the surface of the ground, with only the inequalities in the surface removed. Where crossing soft or marshy land some additional support may be necessary. The gradient should not, as a rule, exceed 1 in 30, and even with this steep gradient it will probably be necessary at certain places to construct shallow cuttings or embankments. Where any cutting or embankment requires to be done it should, if possible, be on the line of the permanent railway, thereby saving expense. When ravines or steep ground intervene it will either be necessary to support the line on a temporary trestle with convenient ap- proaches at either end, form a detour to obtain an easier crossing, or entirely break the line of communication. The service railway will, as a rule, be constructed for a single line, but loop lines or passing places will be required at intervals, of sufficient lengths to allow of trains used in conveying the excava- tions from the cuttings to the embankments or to spoil passing one another. These passing places should be situated at such points as will cause the least delay to the earthwork operations, and in fixing their position consideration should be given to the con- venience for watering locomotives. DRAINAGE WORKS All works connected with the drainage of the land adjoining both the cuttings and embankments, and under the sites of the embank- ments, should wherever possible be executed before proceeding with the other works, so as to reduce the damage to the earthwork from insufficient drainage. Certain of the drainage outfalls may ulti- mately be carried alongside the formation of the finished cutting, or taken in conduits over the top of cuttings, and it will thus be necessary to carry them in temporary channels until such time as the permanent work can be executed. The drainage works required are referred to under the heading of “Culverts and Drainage” in Chapter II, and also m Chapter VI. E.R.E.—E 50 EARTHWORK IN RAILWAY ENGINEERING CULVERTS, BRIDGE WALLS, AND RETAINING WALLS Where culverts are required under embankments, these should be constructed well in advance of the tipping of the materials, so that sufficient time may elapse to allow of the masonry becom- ing thoroughly hardened, and also that no delay may result in forming the earthwork embankments. The same remarks apply to the construction of abutment walls of bridges under the railway and retaining walls required along the foot of embankments. Where line cuttings are supported by retaining walls, the walls should be built in trench from the level of the top of the wall. The excavations above the level of the top of these walls should be first removed, and, after the walls have been built, the excavations in front should be taken out. SLOPES OF CUTTINGS AND EMBANKMENTS The slopes to which the cuttings and embankments should be formed will depend on the character of the material. As a general rule, cuttings in ordinary soft earth will stand at a slope of 1} horizontal to 1 vertical. The slope usually adopted for a solid rock cutting is } horizontal to 1 vertical, and where soft material overlies rock there should be a bench 3 ft. in width between the bottom of the slope of the soft material and the top of the rock (see Fig. 29). These slopes of soft and rock may have to be modified as a result of the particulars obtained from bores, the amount of water likely to be met with, or other information in regard to the strata. In the case of embankments of ordinary soft earth the slope of the upper 25 ft. should be 1} to 1, between 25 ft. and 40 ft. 13 to 1, and below 40 ft. 2 to 1. This matter is considered in Chapter VI, page 100. The exact position of the top of the slopes of cuttings and the bottom of the slopes of embankments should be accurately marked Fig. 29.—S8oft cutting overlying rock. EXECUTION OF EARTHWORK 51 out from the cross sections, and where there are any inequalities in the surface, additional ground levels should be taken and the exact width from the centre line calculated. When the cuttings and embankments are being formed the slopes should be brought to proper line by means of wooden “ batter” rules or “ profiles,” which may be about 6 or 8 ft. long. In depositing the earthwork in embankments, timber cross-heads should be erected at every 2 or 3 chains, and in fixing the height of them an allowance should be made for the subsidence of the embanked material. This allowance for ordinary material should be about 1 in. to every foot in height, and in making up the embankments the width should be proportionately wider. SOIL STRIPPING OF SURFACE After having marked off the lines of the top of the slope of the cuttings to be excavated, and the lines of the bottom of the embank- ments—known as “lock splitting” of the surface—and after the centre line and level pegs have been properly transferred, the soil and turf over the area to be operated upon should be laid aside for the subsequent soiling and turfing of the permanent slopes. It is a common practice to deposit this material immediately outside of the top of cuttings and the bottom of embankments, and between them and the surface catch water ditches where, in the case of embankments, it will act as a barrier, forming a temporary toe, against which the embanking material will abut when being de- posited. PROCEDURE IN LINE CUTTINGS The simplest form of a railway cutting is where the material to be excavated consists of dry sand or gravel and where the depth does not exceed 10 ft. In such a case the material would be taken out to the full section in one operation. If the cutting exceeds 10 ft. and is less than 18 or 20 ft., a gullet would first be driven at formation level (see Fig. 30). While the gullet is beg excavated in advance, the wings BB on each side, above the level of the top of the wagons, would be removed to the full section behind where the excavations are proceeding in the gullet, and loaded up simultaneously with the material from the face of the 52 EARTHWORK IN RAILWAY ENGINEERING gullet. After the top level has been removed the wings CC of the lower portion would be taken off. In trimming off the slopes batter rules would be used and the surfaces trimmed from the top down. It is usual to cut tracks square to the railway and trimmed to the proper batter, these being at intervals of about 66 ft., and the surface of the slopes is dressed uniformly between these tracks. Where the cuttings are of a less depth than 15 ft. the excavations would be removed by hand labour. If the cutting is over 20 ft. deep and has of necessity to be removed by hand the work would be executed in more than one level. As regards the means adopted for disposal of the excavations, if the “lead” to embankment or to spoil is less than about 80 yards ordinary barrows or light hand-carts would be used; from i Gulleé —s ieee ie Fig. 30.—Excavating cutting 10 to 20 ft. deep. 60 to 100 yards “ dobbin” carts drawn by a horse; and when over that distance and less than about half a mile, wagons of a capacity of 14 cubic yards, running on light rails placed at 3-ft. gauge and drawn by a horse, would be used. When this distance is exceeded 44-yard wagons, and worked by a locomotive with from 8-in. to 12-in. diameter cylinder, would be adopted. In the latter case, the gauge of the rails would be the standard railway gauge in use. The number of wagons taken in a “rake”? would depend on the gradient of the service railway, and whether the place of deposit is at a higher or lower level than the cutting, but generally, with 14-yard wagons and horse power a rake would consist of three wagons, and with 44-yard wagons and locomotive power it would consist of from seven to ten wagons. The load should, wherever possible, be taken downhill. In countries where sharp curves and steep gradients are the rule, embankments are generally shallow, and any cuttings that exist are of no great depth. In such cases it may be cheaper to obtain EXECUTION OF EARTHWORK 53 embanking material from borrow pits situated alongside the line of railway, especially where land is of little or no value. When the cuttings exceed 15 or 18 ft. deep and consist of “ soft” material or loose rock, a steam digger may with advantage be used. If the quantity of material in the cutting is more than from 30,000 to 50,000 cubie yards it will generally be more economical to use a digger. With a clean dry sand or soily material there may not PO Gitta an a) : Say Fic. 31.—Width required by steam digyer, be much saving in cost, but with hard clay, boulder clay, hard- bound gravel, shale or loose rock, which are but slowly removed by pick and shovel, a considerable saving may be effected, and, with all classes of material, the quantity excavated in a given time may be two or three times greater when a steam digger is used than when the material is removed by hand. It is a common practice when the material to be excavated is very hard to loosen it by blasting in advance of the cutting face. Fia. 32.—Leaving wings on gullet. The charges would be placed about 20 ft. in advance of the face of the cutting and about the same distance apart and would be sunk to about 12 or 15 ft. below the surface. Care should be taken to see that the charges are at least 3 ft. from the formation slope of the finished cutting, so that the slope may not be damaged. In boulder clay, loose rock, or similar material, the explosive used would be black powder, instead of dynamite or nitro-glycerine, as would be the case if the material to be removed were solid rock, the object being merely to lift the rock off its natural bed or break up the boulder clay so that it may be the more easily removed by the steam digger. 54 EARTHWORK IN RAILWAY ENGINEERING The cutting of a single line of railway with a width of 17 or 19 ft. at formation level is too narrow to allow of a steam digger being used, and it will be necessary to keep the level at which the steam digger is operated about 3 or 4 ft. above formation, as shown in Fig. 31. When the width is unrestricted, as in the excavations for a depot or series of sidings, a larger and heavier machine than would work in an ordinary railway cutting may with advantage be used. It is thus that in large canal undertakings considerable quantities of excavations can be removed in a much shorter time and conse- quently at a less cost than can be done in ordinary railway work. In the removal of the excavations of a railway cutting long gullets should not be driven in advance of the main excavations Fie. 33.—Cutting into slope. (see Fig. 32), as otherwise the weight of the projecting pieces may draw or strain the material outwith the intended slope of the cutting. The sides of the cutting should be battered back as the work proceeds, the slopes being always entirely completed within at least 100 ft. of the working face. A very objectionable practice is to cut away the toe of the slope when the excavations are being removed by a steam digger (see Fig. 33), and thereafter to throw down the upper portion of the wings to replace the part cut away. As a consequence a slip may result through water finding its way into the back of the material that has been thrown down. If the toe of a slope is so cut away it should be made good by stone filling as referred to in Chapter VI, page 112. DISPOSAL OF EXCAVATED MATERIAL In order to obtain the best results from a cutting it is necessary that the means of disposal be most complete, while at the same time a great deal depends on the management of the operations to ensure that the work is skilfully executed. The usual mode of pro- EXECUTION OF EARTHWORK 55 cedure in excavating a soft cutting and tipping an embankment where a steam digger is employed is as follows. Service rails to the standard gauge in use would be laid from the cutting face to the tip ends at the embankment. A light locomotive engine would work at the tip end, while a horse or light locomotive would be employed at the cutting face, and a heavier locomotive than that used at the tip end would run between the cutting and the embankment. If the “lead” to embankment is over two miles, more than one locomotive would be necessary for running the earthwork trains, and passing places would also be required at convenient intervals, probably every two miles. Section Fia. 34.—Arrangement in cutting—three lines of railway. The general arrangement at the cutting face where there is sufficient width is shown in Fig. 34. A short distance back from the face a passing place or loop line is provided for leaving empty wagons and taking away full wagons. At the cutting face the service railway branches into three lines, the steam digger being placed at the end of the centre road. The train of empty wagons, in which there would be eight or ten wagons, would be placed in the centre road behind the digger. An empty wagon would be run by a horse through the “jump” or sharp turn-out and placed at the end of each of the two side roads, so as to be in line with the front of the digger. When each wagon has been filled it is propelled or drawn out into the portion of the side 56 EARTHWORK IN RAILWAY ENGINEERING road behind the “jump” and replaced by another empty wagon. When the whole rake has been filled the next train of empties will be due to arrive and these will be left in the loop while the loco- motive engine, which has brought them forward, pulls out the full wagons, and having pushed the train of empties into the centre road behind the digger, the engine takes the full train away to embankment. With the two side roads there is no delay with the digging opera- tions, as, when a full wagon is being replaced by an empty wagon on one road the digger is filling a wagon on the other road. To be able to get three roads it is necessary that the formation width be not less than 28 or 30 ft., so that in a single line cutting Hill if ybehind Digger Si ir Fig, 35.—Arrangement in cutting—two lines of railway. operations require to be carried out at a level of about 4 ft. above formation level to get that width. If the work is conducted at formation level in a single line cutting, which would be about 17 or 19 ft. wide, it is necessary to have the digger placed in advance of the wagon to be filled (see Fig. 35). Tn this case there would be only two roads. Empty wagons would be placed in the loop, and after each is brought forward and filled it is placed in the straight road from which the whole rake is lifted and taken to embankment. A steam digger can work well in a cutting from 18 to 22 ft. deep. In deep cuttings the work would be carried on at different levels of 20 to 25 ft. between each. When the depth of a cutting is slightly more than the bucket can reach the material is pushed into the cutting by crowbars or is brought down by the operating of the bucket. The arrangement at the embankment end is shown at Fig. 36. Full wagons from the cutting are run into the line A. The wagons which have just been emptied are standing on the line B, and after EXECUTION OF EARTHWORK 57 the engine which has brought forward the full wagons has been uncoupled, it runs the empties back to the cutting. The light engine for tipping is standing in the line B. The first of the full wagons is set in motion by a pinch-bar and run down the line C. The most favourable conditions for depositing material in embankment are obtained when the lines of railway are falling towards the tip end. In high embankments the gradient can be steepened and the upper or narrow portion subsequently made up. On the diagram the gradient down to the tip end is shown to be easy so far as the point X, but beyond that point it is much steeper, but not more than, say, 1 in 30. When the full wagon is within 3 or 4 yards of the tip, the front, which is hinged on the lower edge, is opened by having the fastening From A sae Pi re ae Cutting Empty | Full yak adel oly bibl, SUDO TOUTE Ey J ul Ee + 0 »h = B! Plan, vee oniigemnnninias PO x a) ; Seotion alent say lingg Fie. 36.—Arrangement at embankment end. at the side thrown up by a man striking it with a shovel. The end of the service road is elevated by having a few sleepers raised above the level of the end rail, and when the front wheels of the wagon strike against this buffer the body of it is thrown up and the muck tipped out. Meantime the tipping engine has got in behind the empty wagon and immediately thereafter the second full wagon is run through the crossing into the line D and emptied alongside of the first. The engine with the empty wagon from the line C is taken out and run into the line D, and the second empty wagon, having been attached, both empties are taken out and placed behind the full wagon at point A. The whole “rake” having been emptied in this way they are placed in the line B to allow of another rake being run into the line A, following on which the empty wagons are run back to the cutting. When on account of the shallowness of the embankment or when completing the top portion of a high embankment the material 58 EARTHWORK IN RAILWAY ENGINEERING has to be deposited on a rising gradient, it will be necessary for the shunting engine to propel the full wagons right up to the tip end. The position and number of the passing places already referred to will be fixed by the time which is occupied in filling the wagons at the cutting or emptying them at the embankment. RISKS OF DELAY When the excavated material is dry no difficulty is experienced in tipping it, but if water is present in the cutting which cannot be kept separate from the excavations, progress is retarded. If the excavated material is gravel the water will probably have Fia. 37.—Method of expediting emptying wagons. drained itself off before the embankment is reached; but if it should consist of clay or muddy sand, the material will most likely have been converted into a thick paste, closely adhering to the sides and bottom of the wagon by the time that the muck train has reached the tip end. This adhesion of the material to the wagons may be reduced by spreading a layer of clean gravel or engine ashes in the bottom of the wagons. For the purpose of expediting the work at the tip end, when bad material is met with the following method has been successfully adopted (see Fig. 37). One end of a chain was fixed between the sleepers on the inclined road and after having been carried under- neath several sleepers the other end was attached to the wagon which was being tipped before it had reached the incline. The tip engine, having given the wagon an extra hard push, the wagon was sent down the incline, and on being held up by the tightening EXECUTION OF EARTHWORK 59 of the chain it was brought to a sudden stop at the tip end and the muck thrown out. When the material is bad there may be considerable loss of time in removing it from the wagons, and also by reason of derailments, or wagons going over the end of the embankment, in which case the wagons cannot be emptied quick enough to keep the steam navvy constantly employed; but, when conditions are favourable for disposing of the material, the reverse is generally the case, and the supply of excavated material may have to be augmented by having a squad of men working by hand labour fillmg wagons at some other part of the cutting. In removal of excavations there is always a portion of the slope which cannot be reached by the steam digger, and it is usual to fill so many wagons of each rake in trimming off the slope in the portion of the cutting behind where the digger is working. In wet weather there is also a great risk of delay by reason of engines and wagons being derailed on the service railway. If the material should be of a clayey description, which with water is converted into a slurry composition, a quantity of it will drop on the way to embankment, and it is thus very important that the line of communication should receive proper attention so as to avoid derailments. The further the embankment or place of deposit is from the cutting the greater is the necessity for keeping the service railway in good condition. PROCEDURE ADOPTED IN FORMING EMBANKMENTS If the embankment is over 20 ft. in height it should be brought up in layers, these being, in the case of high embankments, from 15 to 20 ft. thick. When the width at the tip end is less than 30 ft. two wagon roads would be used in the manner already described ; but when the width is greater than 30 ft. additional roads are necessary, an extra road being laid for every additional 15 ft. in width. When there are three or more lines at the tip end, one of the centre lines would be used for holding the empty wagons after the material had been tipped in the side roads. The centre roads would be carried forward simultaneously with, but a little in the rear of those at the side. In forming an embankment the two 60 EARTHWORK IN RAILWAY ENGINEERING outside roads should be at the extreme width of the completed embankment, as, if it should be necessary to slue them for the purpose of subsequently adding to the width, there is a tendency for the additional material to slip on that which had previously been deposited, the whole object being to get a thoroughly consolidated homogeneous mass. When forming embankments the centre should be kept slightly above the level of the outer edges, so that water falling on the surface will easily drain off, but care should be taken to ensure that this is not carried to excess as otherwise the material subse- quently deposited will have a tendency to slip. In widening line embankments or in forming an embankment on very side-lying ground it is usual to cut tracks or benches in line of the railway on the sloping ground so as to form grips for the embanked material. These should not be placed closer than 15 ft., and they should have a slight fall longitudinally so as to prevent the lodgment of water. A deep trench cut along the toe of the new slope and immedi- ately inside of the soil which has been thrown up into a mound to be subsequently used for soiling the slope, will also assist in preventing any movement of the newly deposited material. Where the side-lying ground is pasture land a system of digging or of ploughing the surface to a depth of 9 in. is preferable to forming benches. This matter is further considered in Chapter VI, page 119. The question of using side tip wagons instead of end tip wagons has frequently been discussed; but the consensus of opinion is that end tip wagons should in general be used for forming railway embankments where they are of a less height than 30 ft., but where the embankments exceed 30 ft. and are of considerable length the use of side tip wagons would expedite operations and might allow of the material from several steam diggers being deposited simultaneously. When depositing excavations in embankment by means of side tip wagons the whole train of wagons, or as many of them as can be conveniently accommodated, will be run along the service railway to the site of the embankment and emptied simultaneously. By doing so the work will be considerably accelerated, provided wagons can come forward in sufficient numbers from the cuttings. EXECUTION OF EARTHWORK 61 In a wide embankment formed by side tipping, the work of depositing the material is commenced at the edges of the embank- ment, and after the service rails are raised to a height of 15 to 20 ft., which would form the level of the first lift, the material will be then deposited on the inner side of the embankment and the service road will be gradually slued towards the centre. ALLOWANCE FOR SUBSIDENCE IN FORMING EMBANKMENTS The allowance for subsidence in forming an embankment will depend on the character of the material and the weather conditions existing when the work is being executed, and also to which it will be subsequently subjected. This question is referred to in Chapter VIII, page 140; but it is here remarked that by working traffic over the bank as much as possible while it is being constructed, it is made very compact. Contractors’ service railways running on the bank very materially assist in consolidating it; but while the temporary railways are in use it is necessary that the surface be kept as free as possible from hollows so as to prevent water collecting which may sink into the bank, and thereby cause damage. The longer time that can be spared before the permanent railway is laid the better it will be for the embank- ment. Before the permanent ballast is put down the surface should be brought to proper line and level. If the top is low it should be raised to the proper height with selected material—preferably good hard clay—which will form a firm seat for the ballast, and if the surface is high it would require to be reduced. It is well, however, to keep the bank a little high to allow for ultimate subsidence. Considerable difficulty is experienced in countries where heavy rain-storms occur through banks subsiding after the traffic has been brought on to them. If the banks are made from borrow pits they should be formed as early as possible so as to give them an opportunity of settling during the rainy season. In the event of the railway being brought into use before the first heavy settle- ments have taken place, the railway should only be temporarily ballasted with sand or material from a hard cutting, and subse- quently re-surfaced and fully ballasted after settlement occurs. 62 EARTHWORK IN RAILWAY ENGINEERING CUTTING IN ROCK The method adopted for the removal of rock from the excava- tions will largely depend on the character of the rock, and whether it is proposed to use it for building or other purposes on the contract, or merely to run it to spoil embankment. In the event of the removal of the rock being the primary con- sideration the material would be taken out regardless of its value, the object being to remove the maximum quantity at the minimum cost. Blasting, if allowed, would then be carried on continuously, and if there is a greater uniform depth than from 12 to 14 ft. opera- tions would be carried out at more than one level (see Fig. 38). Fig. 338.—Excavating rock. It will generally be found more convenient to take off one lift con- tinuously for some distance before proceeding with the removal of the rock immediately underneath, but the mode of procedure will largely depend on the means for disposal of the excavated material. The blast holes would be of a depth of about 6 ft. and placed at about 16 ft. apart, but no hole should be closer than 3 ft. to the finished batter of the cutting, so as to ensure immunity from damage to the rock outwith the finished slope. Three men would be engaged at each bore hole, if the drilling is done by hand, while other ten or twelve men would be engaged loading up the excavated material. The material after being loaded into skips would be lifted and emptied into wagons either by steam cranes placed on the top EXECUTION OF EARTHWORK 63 of the cutting or by travelling cranes working on the line of railway at formation. As a preventive against stones flying out of the cutting the blast hole should be covered over and weighted down. A good cover consists of pieces of trees 6 in. in diameter and 6 it. long tied together by chains. If blasting is prohibited by reason of the proximity of property, public highways or adjoining railways, the materials would be taken out by pinch-bars. This matter is further referred to in Chapter V, page 78. If the removal of the rock from the cutting is not the key to the completion of the work, it would be taken out in large masses in a manner somewhat similar to that usually adopted in quarrying operations. In the case of freestone, limestone, or other stratified deposit the rock would be shifted by splitting it with wedges or by what is known as the “ plug and feather” method, and by raising it off its natural bed by means of crowbars. Small charges of gunpowder would be used to shake large posts of rock without shattering it. Where granite is met with in large quantities blasting will be regularly carried on, and the larger masses which are brought down will be subsequently split up into smaller pieces in a similar manner to the softer stratified rock. For the removal of the rock so quarried the blocks of stone which are to be used for building or other purposes will be run out into a depot set apart for the purpose, while the smaller material or debris would be put into tip wagons and run to spoil embankment, or it may be used to advantage for pitching slopes exposed to water, making up roads, or broken up for concrete, or crushed for use as sand, or other purposes. When rock is met with in station depéts, where there may be platform fronts to be formed in the rock, a track would be cut either by shearing the rock by hand labour or by means of a channelling machine. This would be done previous to the removal of the centre portion, and there would thus be no risk of damage to the sides of the finished cutting. EXAMPLES OF RAILWAY CUTTINGS The following examples from actual practice illustrate the manner usually adopted in the removal of excavations from rail- way cuttings. 64 EARTHWORK IN RAILWAY ENGINEERING Hach of the examples is for a single line of railway where the operations are carried on in a confined width and consequently require more consideration than where there is greater freedom for work. (1) Fig. 39 is a profile of a railway cutting for a single line of railway, the greatest depth of which was 46 ft. and the quantity of material to be excavated was 80,000 cubic yards. The material consisted of sand and gravel for a depth of 6 ft. under the surface, underlying which there was clay until within 10 ft. of formation, while the bottom 10 ft. consisted of “ faikey” fireclay. The line embankment which was situated at the upper end of the grade required about 60,000 cubic yards of material, and the balance of 20,000 cubic yards had to be deposited in a spoil bank at the To line Embankment —> Spoil Bank ss 7 es FL “qdag | Osss FOL LT LL os os SL a te _ S fe FL oo | oss 6.6 0-1 O-L Gel 8% 8L SATJOTMODOT | J9sdIq Wies4g Av) IopMmog FL qsnsny | ‘sp£ "qng | ‘gouag | ‘soueg | ‘souaq | ‘a0ueg | ‘suleyO | “e087 ‘osemvy *BUIYBAVOX *s[e119} BAL “‘s£Uq ‘syiemey Ft! Jo go go jo ‘oye “AAYVUENH | “tyaog, | ‘saxorg| ‘axvig| ‘xaoayy| ‘peey | ‘uydeq pouyzan pone Jayoureg ‘ON ‘TIL Tr! ‘Tt UVAA ANO AO GOIMAd V WHAO LSOO TVOLOV CONDITIONS AFFECTING THE COST 137 The statement will also show the actual cost of concrete, masonry, and brickwork in building culverts, etc., and as in the case of cuttings any excess expenditure should be investigated. The importance of having these costs prepared will be more fully appreciated when reference is made to Fig. 73, which gives 10,000C yds 7,000 . = o 2 ~ Qa Ae 5,000 “= a Ve a = > G & és 000 4, a 3 aid 2 3,000 os = S 2,000 1,000 pence 0 C Yds Hard dotted line represents cost per cubic yard. Hard full line represents output in cubic yards, each fortnight. Fic. 74.—Diagram of cost and output of railway cutting. particulars obtained from the cost statements of output and rela- tive cost of a cutting including disposal in an embankment, extend- ing continuously over a period of twelve months. The material in the cutting consisted of sand, or sand and gravel, and was deposited in embankment at an average distance of about a mile from the cutting. Fig. 74 gives the same information diagramatically, and clearly 138 EARTHWORK IN RAILWAY ENGINEERING shows how, with a large output, the cost per cubic yard is very much less than what it is when the output is low. The two best months’ work was in March and April, the average output during that period being 615 cubic yards per day at an average cost of 7-3d. per cubic yard. The average output over the whole year was 350 cubic yards per day at an average cost of 10-2d. per cubic yard. These costs include depositing in embankment. The work referred to was executed previous to the outbreak of the European War in 1914, when navvies’ wages averaged about 5d. per hour, and consequently do not represent the cost of the work at the present time. A saving of 4d. per cubic yard in the cost of excavations spread over 1,000,000 cubic yards represents over £2000, and this will repay the Contractor the additional expenditure incurred in having the costs made. In work of this description constant vigilance is necessary to ensure the most rigid economy. The Engineer, for his own information and for that of the pro- moters, should be fully informed as to the progress and cost of the works as the operations proceed, and this can best be seen in a diagram. Information of this description shown on a diagram indicates at a glance whether the operations are being satisfactorily executed, both as regards cost and progress. As regards the cost of labour, the fluctuations of the labour market may largely affect the cost of the work, a small increase or decrease of the rate of wages being sufficient to very materially influence the total value. If wages are low when the work is being tendered for, the Contractor, keeping in view a probable rise during execution of the works, may found his estimate on the basis of a higher rate, but by so doing he may reduce his chance of obtaining the contract. This difference will, of course, be more apparent in work on which the greater part is executed by hand labour rather than on that where steam diggers or other heavy plant are used and where the quantity of material handled is considerably greater per man employed during a given time. In connection with the character of the materials to be excavated, while the classification of “soft” and “ rock’? may be sufficient on which to prepare a Contract Tender, these two designations very inadequately describe the various kinds of material that may be CONDITIONS AFFECTING THE COST 139 met with, and in many cases misrepresent the characteristics of them so far as their removal from a cutting or placing in an embank- ment is concerned. A dry sand cutting is the simplest and least expensive to excavate, but, if there should be water in the sand, the removal of it may be equally as costly and much more troublesome to deal with than solid rock. A tough boulder clay is the most difficult of “ soft” materials to excavate, but certain clays or clay with sand are very troublesome if water is present in sufficient quantity to convert it into “ slurry.”’ The cost of the work is thus largely dependent on the quantity of water met with and the effect of water on the materials to be excavated. If clean, sharp sand, gravel, or solid rock is met with in the cuttings, it will have a commercial value in so far that sand and gravel can be used for concrete, freestone, or granite for building purposes, and freestone or whinstone for road making and pitching slopes of streams and water-courses. In the case of excavations in solid rock, if it is such that it can be put to any of the uses referred to it will generally be advantageous. The time under which the work is to be executed may, however, necessitate its removal by the usual methods of blasting instead of by quarrying as would otherwise be done. A good rock cutting is a decided asset, and the cost of excavation should be credited with its value, provided it can be used. If there should be a large quantity of rock to excavate, the removal of it may be the key to the completion of the work, and it may consequently be necessary to expedite operations by carrying them on at several points by sinking trenches and driving headings at considerably greater outlay than would be incurred if the work can be pro- ceeded with from open ends. It may be a convenience to lay an overland service route clear of the cutting to link up the lines of communication between the works on one side with the works on the other side, and thereby give greater freedom in excavating the rock cutting. In both soft and rock cutting, where it is not possible to have free drainage from the working face, the unit price will be increased by the expense of the pumping necessary to keep the excavations free from water. Considerable importance attaches to the facilities for removal 140. EARTHWORK IN RAILWAY ENGINEERING of the excavations from a cutting. It is in this connection that the work of a canal, dock, or other open excavation is so materially different from the confined space generally anticipated in a stretch of railway, road, or similar work. As has already been pointed out, it is necessary, in order to obtain sufficient width to excavate a cutting for a single line of railway by means of a steam digger, to carry on the operations at a level of about 4 ft. above the level of formation. The bottom portion has thus to be taken out by hand at a greater unit cost. In a double line of railway work can be carried on at formation level with better facilities for bringing forward and removing the muck wagons, and, if there is greater width, as in the case of a canal, the accommodation for wagons will be still better, with consequent less delay or stoppage of the operations. When, as is sometimes done in canal excavations, the material is deposited on land immediately adjoining the cutting, any delay will be due to a break-down of the digger or excavator, and any cessation of operations will be reduced to a minimum, and the unit cost will also be a minimum. As already stated, the cost of the work is largely dependent on the relative positions of the cuttings and embankments and the length of the “lead” from the cutting to the embankment or other place of deposit. It is, of course, a convenience if the material can be run down grade to embankment. In the event of it being necessary to run material to spoil embank- ment the cost will be increased by the rental of the land on which the spoil embankment is situated and also the restoration of the surface. The conditions of the weather and the season of the year during which the work is being carried out sometimes very seriously affect the cost. It has already been suggested that practical operations should be commenced during the early springtime, so that full advantage may be had of the more favourable weather and long day of the summer season. In work extending over a period of years every effort should be made to get as much done as possible in good weather, and during unfavourable weather conditions operations should if possible be curtailed or temporarily suspended. When work is carried on in wet weather not only is the cost of the excavations increased, but the material when put into embank- ment, being in a sodden condition, may cause serious slipping at CONDITIONS AFFECTING THE COST 141 a subsequent date, necessitating considerable expense in repairs. While the men usually employed are only paid during the time they are actually engaged, there are “oncost” charges for managers, engineers, foremen, etc., as well as the interest and depreciation in value of the plant in use, to be met whether the work is being carried on or not, but it is better to stop operations for a time if the circumstances will permit. Under certain conditions the actual cost per cubic yard of a cutting taken out by a steam digger may not be less than that excavated by hand, but the larger output and the ensuring of the work being executed in favourable weather may justify the use of the digger. The effect of weather conditions on the cost of the work and the advantage to be gained by making the most of the good weather both as regards the reduced cost and the larger output has already been referred to. Considerable expense is sometimes incurred in maintaining service lines of railway when crossing soft ground, by having to make up subsidences with ashes or otherwise. The time ‘within which the work is to be executed may require that operations be unduly pushed, but before tendering a Con- tractor should satisfy himself that the time allowed under his Contract is sufficient to enable him to execute the work in a manner corresponding with the amount which he has stated in his Tender. The time allowance may be altogether inadequate—no matter what the mode of procedure may be, and not infrequently Engineers make the mistake of not giving this point sufficient consideration. As a common example, the greater part of the excavation of a rail- way may be confined to one cutting, and the more economical method might be to take it out by means of one or two steam diggers, working from the lower end of the cutting; but, in order to complete the work within the Contract Time, it may be necessary to proceed with the excavations from both ends simultaneously, and the probability is that at some points it may be necessary to excavate against the gradient, necessitating pumping and addi- tional steam power at greater cost. If the same quantity of material were distributed over two or three cuttings where each could be working independently of the other, the cost would be much less and the work executed in a shorter time. CHAPTER IX SPECIFICATION THE execution of all engineering works of importance is carried out under Contract. The Contract Specification consists of “‘ General Clauses’ for the protection of the rights of both parties to the Contract. These are, for the most part, of a legal character, and there are in addition “‘ Works Clauses,” which are descriptive of the class of work and the manner in which the Engineer wishes it carried out. The Specification is framed by the Engineer and forms one of the Contract documents signed by the Contractor, and is binding on him for the due fulfilment of the Contract. In the preparation of the Specification the Engineer should be careful to ensure that what he wants is clearly brought out, and that he is neither asking for more than he expects to get, nor less than is essential for what he will afterwards insist on having. The language should be perfectly clear and of the simplest description, having only one interpretation, so that there may be no subsequent ambiguity as to the meaning attached thereto. The Engineer must himself understand his Specification as otherwise he cannot complain if the Contractor fails to understand it. In no constructional work is a Specification more necessary than in a Contract involving the execution of earthwork, and there is probably no other class of work where the Specification is more frequently departed from. There has probably been more con- troversy over questions of earthwork than any other operations which fall to be dealt with by an Engineer. The essential points for the ‘‘ Works Clauses ”’ of an earthwork Specification have already been revealed in describing the various constructive operations, and in the present chapter it is proposed only to refer briefly to a few of the points of difference which frequently arise in carrying out Contract work. 142 SPECIFICATION 143 Prices are cut so keen in making up a Schedule that it is not to be wondered at that a Contractor should claim to be paid for the slightest departure from the terms of the Contract, and at times play on the sympathies of the Engineer to get something more than a rigid interpretation of the Specification allowed. A frequent cause of difference has reference to the classification of excavations. This matter has already been referred to under the heading, ‘“‘ Investigations as to Strata,” at page 17, and “ Cost of Earthwork,” at page 139. Tt is usual to have earthwork material classified in a Contract Schedule with the two descriptions, “soft” and “rock.” A common form of Specification reads, “ All material other than solid rock will be paid for as ordinary ‘ excavation,’”’ and, “ Nothing will be paid for as rock except solid sandstone, solid limestone, or solid whinstone.” It might at first sight seem better to have a middle classification of ‘‘ soft rock” in cases where large quantities of material have to be removed, this term to include such material as fireclay or other shaley clay, hard boulder clay or close-bound gravel, which are only capable of removal by means of a pick and which not infrequently requires to be loosened by blasting. Materials of this description are more difficult to remove than sand, loose gravel, clay, or earthy material, and it is the classification of materials of this description that raises the point of difference. Some Engineers ask Contractors to give an overhead rate to cover all classes of material which he may meet with, and, while this may get over the difficulty of classification, it is better that the Engineer in calculating his quantities should have a distinction between “soft”? and ‘‘ rock,” and the writer is of opinion that no advantage is gained by having an intermediate class. Part of the soft material may be very difficult to excavate, or it may contain a large volume of water, which makes it much more costly to remove than if the cutting was dry ; but the Con- tractor should carefully consider these matters with the informa- tion obtained as to strata supplemented by minute investigations on the ground and any additional particulars he may obtain as to the probable quantity of water likely to be met with when carrying out the work. He must also consider what means will require to be taken to intercept the water and direct it clear of the opera- tions, and price his Contract Schedule accordingly. 144. EARTHWORK IN RAILWAY ENGINEERING This raises the question of the accuracy of the preliminary investigations which has already been fully dealt with in Chap- ter IT. The quantities of material separated into “ soft” and “rock,” stated in the Contract Schedule, are prepared from this preliminary information, and if those quantities have been imper- fectly estimated, or if any of the material to be excavated has been wrongly described, the cost of the work may be largely exceeded and the Contract time for completion may be inadequate. As already stated, it is customary for the Engineer to have trial bores put down on the line of the railway or site of the works, and the Contractor will have the benefit of the information so obtained. The journal of these bores should not, however, form part of the Contract Documents, and the Contractor will require to take the risk of the materials in the excavations turning out different from what he may have expected. This matter is also referred to in Chapter IV, page 47. In connection with bridges, culverts, etc., it is important that these be detailed as fully as possible in the Contract Schedule. All culverts require to be constructed previous to the railway embank- ment under which they are carried being formed and the greater number of bridges, both over and under the railway, will also require to be constructed before the railway is formed up to them. Conse- quently, the materials for these works may require to be taken over fields and inferior roads at greater cost than would be the case if the points on the line where these special works are being constructed were more easily accessible. The Contractor may have a “flat” rate for masonry, concrete, etc., no matter where the works are to be situated on the contract, but it is better that he should have the opportunity of pricing the items for each work separately, and he cannot afterwards have any grounds for claim on account of the inaccessibility. Any departure from the original schedule will, in all probability, add to the cost of the work, and that in a greater proportion than the increased quantities represent. Questions relating to damage by water not having been properly intercepted alongside of cuttings and embankments, and to the operations not having been executed in such a manner as to pre- vent the occurrence of slips, frequently arise. It is usual to ask a Contractor to state a sum for dealing with slips, which sum is SPECIFICATION 145 over and above payment for the construction of such intercepting catch-water and slope drains as the Engineer considers are essential for the construction of the works. The sum stated by the Con- tractor in his Schedule may be altogether inadequate to cover the cost of slips that will occur under the best of management, but the Contractor is liable in any expense thereby incurred. In carrying on his operations the Contractor will require to execute such temporary drainage and other contingent works as are neces- sary in his own interests, but if the operations are under proper superintendence, the risk of damage by reason of water will be very largely reduced. The necessity for executing the drainage work of the adjoining lands previous to the cuttings and embankments being commenced, and the importance of timeously dealing with water which appears in a cutting, have already been referred to in Chapter V1. It is usual to stipulate in the Specification a date before which the works are to be completed, and, in fixing the Contract Time, the Engineer should put himself in the position of the Contractor and consider how the work is to be done within the time which he proposes to stipulate. The value of the work is not necessarily the measure of the time for completion, neither is the total volume of material to be excavated. There may be 250,000 eubic yards of excavation to remove, and if this quantity is in several cuttings and can be proceeded with simultaneously at various points the work will be more speedily executed than if the whole of the material is to be removed from one working face. The removal of the excavations from a cutting may depend on the construction of a tunnel, viaduct, bridge, or other work, and this should be kept in view in fixing the Contract time. As has already been stated, the time of the year in which the work is executed will also largely affect the time taken to execute. Endeavour should be made, as far as possible, to avoid time account work, and any extra work should, wherever possible, be paid for at Schedule rates, or at rates proportionate to the Schedule rates for similar work. There is always a temptation on the part of the Contractor to unduly extend work when he knows that he will be paid for it by “ time and lime.” The importance of employing experienced men who are skilled in this particular class of work has already been referred to, and, E.R.E.—L 146 HKARTHWORK IN RAILWAY ENGINEERING im many cases, a Contractor loses by not having the best of men to supervise his operations, and this is very frequently the cause of difference between the Engineer and the Contractor. If he should not have the works properly managed, the most successful methods will not be adopted, or by adopting particular methods he may be compelled to execute certain parts of the work in winter or during adverse weather conditions, and consequently the works are uneconomically carried out and at excessive cost. The Contractor requires to have sufficient capital or have the necessary financial support to ensure that the works will not suffer for want of the most suitable plant. It is usual to specify that “the Company (or Corporation) do not bind themselves to accept the lowest or any Tender.” In advising his clients the Engineer should be satisfied that the Contractor whose Tender he recommends should be accepted is not only financially sound but that he is thoroughly capable of handling the Contract. For an earthwork contract, probably more than in any other engineering undertaking, the successful Contractor should be a specialist in this class of work. He may have sufficient capital or financial sup- port, but if he is not accustomed to the work he is not a success and the result reacts both on the Contractor and on the promoters for whom the work is being executed. If, on the other hand, he knows his work but lacks the capital, he is hampered through not being able to employ the most suitable plant. The contract will probably include steelwork for bridges, and the Engineer will require to be satisfied that it can be properly executed and timeously supplied. If the steelwork is not erected at the time when it is wanted, the Contractor may be put to the expense of providing temporary trestle bridges or constructing other temporary works at considerable expense. Before recommending a particular Tender, the Engineer should be satisfied that the Contractor can execute the work for the amount of his Tender. If it is quite apparent that the Contractor is going to lose by the contract, it is better that the promoters should not give him the work to execute, as the work will most probably cost the promoters more in the end than they would other- wise have paid if the Schedule had been correctly priced. The Contract will include for maintaining the whole works for a period after completion, generally twelve months, and the Contract SPECIFICATION 147 Schedule should have an item for maintenance for that period. The Contractor may not enter a price opposite this item, or the sum which he states may be inadequate, in which case it is assumed that the other items in his Schedule either in whole or in part allow for the cost of maintenance. In the case of the greater number of engineering works, the cost of maintenance may be small, but in the case of the earthwork of a railway the cost of proper main- tenance may be a fairly large sum. This maintenance includes the repairing of slips and soiling of slopes which may have been damaged by weather, the cleaning of ditches, and the bringing to proper level any embankments which may have subsided, and the leaving of the work in an entirely finished condition. The cost of main- tenance is largely influenced by the manner in which the several works have been executed. This matter has already been referred to in Ohapter VII. The points above referred to are sufficient to indicate the diffi- culties attached to the Engineer’s duties where he wishes to be absolutely fair to the Contractor, while at the same time jealously guarding the interests of his clients who have to pay for the work. INDEX A ANGLE of repose of various materials, 100 Arch culverts under railway, 23 B Buiastine for steam digger in hard cutting, 53, 117 rock in cuttings, 93 Bog or moss land, 67-69 Bonuses to navvy “ gangers,” 135 Bores, additional, taken by contractors, 47, 144 Boring, chisel, 11-14 diamond, 14-16 importance of, 10 necessity for, 17 rate of progress, 17 wash-out ‘“‘ drills,” 17 Boundary fences, determined from cross sections, 40 determined by levelling at site, 41 Box drains of timber, 22 British permanent way, 128 Built stone drains, 23 Cc CALCULATION of areas of cross section, 42 Capital required by contractor, 146 Character of materials and cost, 6, 138, 139 Characteristics of various materials, 99, 100 Chisel boring, 11-14 Classification of materials, 138, 139, 143 Clay slopes, action of rain storms on, 107 Consideration of railway project, 2 Contract, cross sections, 40 drawings, 37 general plan, 37 longitudinal section, 39 schedule, 36, 144 specification, 36 time of completion, 145 Contract, commencement of, 43, 140 Contractor’s risks, 47 Conveyance of excavations, 93-98 Coolie or black labour, 72, 73 Cost of earthwork, facilities for work- ing, 139, 140 character of materials, 6, 138, 139 price of labour, 138 relative position of cuttings and embankments, 45 time allowed for execution, 141,145 weather conditions, 141 Cost of plant, 135 Cost of single and double line of rail- way, 2-4 Cost statement form, 135 Cost system, 135 Cost of work over extended period, 136 diagram of, 137 Culverts, built stone drains, 23 capacity, 19, 20 constructed in advance of embank- ments, 50 design of, 21-23 design of ends, 27, 28 fire-clay pipe drains, 22 formula for discharge from catch- ment areas, 19 maintenance, 133 on side-lying ground, 24-26 on soft ground, 26 riveted, malleable iron or steel tubes, 24 steel beams and concrete covering, 24, timber box drains, 22 Cuttings, objection to cutting away toe of slope, 54 objection to long gullets, 54 procedure in construction, 51 removal of cuttings by hand, 52 removal of cuttings by steam digger, 53 D DEPRESSION in embankment for flood water, 21 ’ 149 150 Deviation, local, with a view to less costly culverts or water-courses, 18 Diamond boring, 14-16 Discharge from catchment areas, formula, 19 Drainage, interception of, necessity for, 145 Bog or moss land, 67-69 British permanent way, 128 executed before other works, 18, 49 Pennsylvania Railroad permanent way, 132 permanent way, 129 site of embankments, 121 slope drains in cuttings, 105, 106 thorough, a means to prevent slips, 111 works per.odically inspected, 127 Drains, slope drains in cuttings, 105, 106 large slope drains in cuttings, 108 Dwarf walls in soft cuttings, 108, 109 E EaRTHWORE constructed by coolie of black labour, 72, 73 exceptionally heavy, 75, 76 maintenance, 127 risks of delay in execution, 58 Economics in construction, 4 Bfficiency of control of operations, 134 Embankments, construction of high, 118 Embankments, less liable to snow blocks than cuttings, 6 procedure in forming embank- ments, 56, 59 in soft ground, 121 in unstable side-lying ground, 121 Engineer’s report, 1 Estimates, preliminary, 2, 8 Excavated material, disposal of, 54 F Faocmitizs for removal and cost of earthwork, 139, 140 Fire-clay pipe drains, 22 Flood water, openings through embank- ments, 20 Depressions in railway embank- ment, 21 Formula for discharge from catchment areas, 19 G GRAVEL, close bound, 10 Gullets, objection to long gullets, 54 INDEX H HaAND-HAMMER machine rock drill, 91, 92 Hydraulic method of forming embank- ments, 74 I IncERSOLL-RanpD machine rock drill, 89-91 L Lazovr, price of labour and cost of work, 138 Land, extent of land required, 7 setting out, 44 “Lead” down gradient when possible, 140 Location of railway, 2 Loose rock cuttings, slips, 109, 110 Lubecker land dredger, 87 M Marntenancr, advantage of greater width in cuttings, 4 culverts, 133 earthwork, 127 permanent way, 127-129 slopes, 132 work, contract, 146, 147 0 Open channels or pipes along forma- tion, 131 P Pzrwnnsytvania Railroad, drainage, 132 Permanent Way, maintenance, 127- 129 drainage, 129 section of British, 128 section of Pennsylvania Railroad, 132 Pipe drains along foot of slopes of cuttings, 130, 131 Plan, contract, 37 Plant, necessity for sufficient plant, 146 hand labour, 77, 78 Lubecker land dredger, 87 rock drilling by hand-tools, 89 hand-hammer machine drill, 91, 92 Ingersoll-Rand machine drill, 89-91 Ruston steam crane navvy, 79-83 Ruston steam shovel, 85, 86 Wilson steam crane navvy, 84, 85. _ “ Plug and feather,” 78 INDEX Preliminary estimate, 2, 8 . investigations, 144 section, 7 Procedure in constructing cuttings, 51, 55, 56 embankments, 56, 59 excavating rock cutting, 62 Q QuantirTizs, importance of accuracy, 10 R Rattway, cost of single and double line, 2, 3, 4 cuttings, examples, 63-67 local deviation and economy in culverts, 18 maintenance, 4 service, 48, 139 setting out, 44 widening, 70-72 Rock cuttings, face wall in soft cuttings, 1 excavation, 62 retaining wall in soft cuttings, lll signal to indicate fall of rock, 133 use of materials, 139 Rock drilling by hand, 89 by hand-hammer machine, 91, 92 by Ingersoll-Rand machine, 89-91 Rock excavation, blasting, 93 “plug and feather’ method, 78 Ruston steam crane navvy, 79-83 shovel, 85, 86 Ss SCHEDULE, contract, 36 Scheme of operations, 47 Scraper machines, drag and wheel, 73, 96-98 Section, contract, 39 preliminary, 7 working longitudinal, 46 Service railway, 48, 139 Setting out railway, 44 Setting out land and works, 44 Side channels or pipe drains along foot of slopes of cuttings, 130 Side-lying ground, railway formed on, 5 cutting trenches on, 119 embankments on unstable, 121 slips in embankments on, 122 water-logged, 123, 124 Sleeper fence for snow drifts, 133 151 Slips in cuttings, 101 in cuttings requiring special treat- ment, 113-115 in ae of large dimensions, 112, 13 in cuttings in loose rock, 109, 110 in cuttings of small dimensions, 111, 112 in embankments, 116 in embankments due to water- logged material, 125 in embankments due to character of materials, 124, 125 in embankments, due to character of strata under site, 120 in embankments on side-lying ‘ ground, 122 through drainage, 111 Slope drains in cuttings, 105, 106 large, 108 ' Slope of various materials, 9 Slopes of cuttings and embankments, 50, 118 Snow drifts, 133 sheds, 133 Soft material containing water, 143 Soiling and sowing slopes, 107, 108, 119, 132 Soil-stripping surface, 51, 119 Specification, cause of differences, classification of excavations, 143 contract, 36 contract should be explicit, 142 Spoil bank, site of, 5 Springs under site of embankments, 122 Steam crane navvy, Ruston, 79-83 Wilson, 84, 85 Steam digger, large output, 141 width of cutting required, 54 Steam shovel, Ruston, 85, 86 Stone drains under railway, 22 Strata, character affects cost, 6 character affects extent of land required, 7 investigation as to, 9 necessity for fullest information, 9, 10 Subsidence in embankments, allowance for, 61 Syphon pipe under railway, 33 T TrmBer box drains, 22 Time account work, 145 Time of completion, 141 Tip wagons, iron, 94 wood, 95, 96 152 ne in side-lying ground, Trestles, timber, 74 carrying water-course, 33, 34 Trial pits, 9, 16 Turfing foot of slopes of cuttings, 119, WwW Wacons, iron and wood, 94-96 side-tip versus end-tip, 60 Walls, drystone dwarf, 108, 109 face, 110 retaining, 111 Wash-out ‘‘ drill,” 17 Water, damage by, in cuttings, 102, 103 action on clay slopes, 107 damage through improper inter- ception, 144 interception of, in strata, 104 INDEX Water, large volumes of, in cutting, 115, 116 openings through embankments, 20 under site of embankments, 123, 124 Water-courses, combined in one culvert, 29 and road accommodated on one bridge, 33 carried by a syphon, 33 carried down slope of cutting, 34 carried in open conduit, 33 carried on a road bridge, 33 carried on trestles, 33, 34 diversion along contour, 30 road and stream through same opening, 33 Weather and cost of earthwork, 141 Widening of existing railways, 70-72 Wilson steam crane navvy, 84, 85 Printed in Great Britain at + The Mayflower Press, Plymouth. William Brendon & Son, Ltd. D.VAN NOSTRAND COMPANY are prepared to supply, either from their complete stock or at short notice, Any Technical or Scientific Book In addition to publishing a very large and varied number of SCIENTIFIC AND ENGINEERING Books, D. Van Nostrand Company have on hand the largest assortment in the United States of such books issued by American and foreign publishers. All inquiries are cheerfully and care- fully answered and complete catalogs sent free on request. 8 WarREN STREET - - - New York ————— a ee