Ć - • . - I OFI ORNL P 2536 'i . 11 . ? : . . . je *?. 1 5 6 EFEFEEEE S 11:25 114 11.6 1.6 . ' MICROCOPY RESOLUTION TEST CHART NATIONAL BUREAU OF STANDARDS -1963 ORNA up-2534 NOV < 9 1966 2.25.1.00. 5 50 CON4-660934.4 MASTER Philippine Special Frind Project An Illustration of a Feasibility Study by J. A. Lane For presentation at the IAEA International Survey Course on Economic and Technical Aspects of Nuclear Power Vienna, Austria, September 5-16, 1966 RELEASED FOR ANNOUNCEMENT IN NUCLEAR SCIENCE ABSTRACTS LEGAL NOTICE This report was prepared as an account of Government sponsored work. Neither the United States, nor the Commission, nor any person acting on behalf of the Commission: A. Makes any warranty or representation, expressed or implied, with respect to the accu- racy, completeness, or usefulness of the information convained in this report, or that the use of any information, apparatus, method, or process disclosed in this report may not Infringe privately owned rights; or B. Assumes any liabilities with respect to the use of, or for damages resulting from the use of any information, apparatus, method, or process disclosed in this report. As used in the above, "person acting on behalf of the Commission” includes a .y em- ployee or contractor of the Commission, or employee of such contractor, to the extejt that such employee or contractor of the Commission, or employee of such contractor prepares, disseminates, or provides acce88 to, any information pursuant to his employment or contract with the Commission, or his employment with such contractor. Introduction Figure 1 shows a map of the Philippine Islands. As seen here, these consist of two major islands Luzon and Mindanao and a group of smaller islands in between which are collectively called the Visayas. The characteristics and electrical power needs of these three geo- graphical areas are as follows: 1. Mindanao has an area of more than 98,000 square kilometers and a population of about 7 million people; however, the annual con- sumption of electricity by these people is relatively small (65 kwhr capita). This demand for electricity is largely met by the 50 MW Maria Cristina hydroelectric plant on the Agus River plus 18 Mw of diesel electric plants. Fortunately for Mindanao, even though power needs are increasing rapidly, the hydroelectric potential of the Agus River at 800 MW is sufficient to meet these needs at low costs for the next 20 years. 2. In the Visayas, on the other hand, the hydro electric potential ver, the annual consumption of electricity at 17 kwhr/ capita is even lower than in Mindanao even though the population is higher (10 million). Because of the numerous islands concerned and the difficulty of connecting these with any sort of a transmission grid, it is apparent that future electricity requirements will be met by con- structing small diesel-electric units on each of the major islands in the group other than by interconnected hydro or thermal steam plants. 3. Unlike Mindanao and the Visayas, however, the demand for electricity in Luzon is already quite large and is growing rapidly. At the present time, Luzon with an area of more than 100,000 square kilometers and a population of more than 15 million people uses 3,600 million kilowatt hours of electricity per year. About 85% of this is sold in Manila which has a per capita consumption of about 2000 kwhr year. This compares favorably with use of electricity in most of the developed countries in the world. The growth in the rate of consumption of electricity in Luzon, moreover, has been increasing at a rate of about 13 Background Information Leading to the Pre-Investment Study of Power in Iuzon Because of the rapidly growing demand for electricity in Luzon and the ever increasing dependency on imported fue is, interest in finding more economical ways of producing power has always been high. In this context, nuclear power has long been considered as a possible alternative to conventional plants and as far back as 1956, a study was made of a small nuclear plant for the Manila area. Because of the small size of this plant, however, it could not compete with oil-fired plants. In 1960, the Philippine Government invited a mission from the International Atomic Energy Agency to investigate the feasibility of a nuclear power for the Luzon Grid. The report of this mission, entitled . 2 . C Caira Balandi o 'debugon selonde Saraku 120-5 dol 2 A SAN FERNANDO 3 หcui่ 13 5'ONGSYES ILUZON t witt Ficom:O USTANOS TEATY LAUTSTOF THE PHILIPPINES O111:0 ISTANOS SunTLA QUEZON CITY CATANDUANES 1.EG UNDORO CALAMIAN GRC // REDU HUERTO PINCESA (IONO: SIMON AO SURGA S... CAGAYAN MOKO' CULF ** ZAMBORGIO 70..X Davaul N : TASIIAN GULK kanDAMAS ular Mignol ALLAGO Serengoli tilando Fig. 1. . 3. . "Frospects of Nuclear Power in the Philippines" indicated that the prospects were attractive enough to give the matter serious consideration. As a follow up of this recommendation, in December 1962, the Philippine Government submitted a request to the United Nations Special Fund for assistance in undertaking a pre-investment study of power in Luzon. This request was approved in June 1963 and the study formally got underway in February 1964. The IAEA was named executing agency for the project and he Philippine Atomic Energy Commission was delegated the responsibil..ty for coordinating the work by local agencies. A sum of $70 ,000 was budgeted for the project about two-thirds of which was provided by the Special Fund and the remainder by counterp The plan of operation that was adopted involved an initial Phase A effort to investigate the future market for power in Luzon during the next decade and establish whether available resources of hydroelectric power, coal, geothermal, or oil and gas are sufficient to meet the demand. The decision of whether or not to consider nuclear power under Phase B of the study was held open until the results of Phase A were krown. These indicated that most of the future power needs in Luzon would have to be supplied by imported fuels, therefore, nuclear power was included in the Phase B study. This was aimed at establishing the optimum power expansion program up to 1975. As a supplement to the main power study, the project also included the training of Philippine scientists and engineers in nuclear technology, & survey of possible sites for nuclear plants, and the preparation of draft legislation covering the acquisition and regulation of future nuclear installations. Phase A Studies Market Survey - The survey of future power requirements was carried out by a U.S. consulting engineering firm (Gilbert Associates, Inc.) with the help of local utility companies. This involved a field survey of almost 100% of the towns in Luzon and an actual physical count of the number of potential residential, commercial and public customers in the towns which will be accessible to the Luzon Grid during the next decade. By applying appropriate factors based on experience for the annual kwhr use by each type of customers, the total annual sales were forecasted. Industrial uses of electricity were projected on the basis of the anti- cipated growths of 23 different groups of industries. Projected street lighting requirements and miscellaneous uses were then added to estimate the total future energy and capacity requirements of the Grid. The re- sults indicated that the generation of electricity on the Grid will in- crease from 3.6 billion kilowatt hours in 1965 to more than 12 billion kilowatt hours in 1975. The installed name-plate capacity required to meet this demand will increase correspondingly from 670 MW (670,000 kilowatts) in 1965 to about 2670 Mw in 1975. Existing Power Supply System - The two principal electric utility systems are the Manila Electric Company (Meralco) and the National Power Corporation (NP ) which jointly supply more than 99% of the electricity consumed on Luzon. These two companies play complementary roles in the 4. disposition of power. Meralco, an investor owned utility supplies electricity to consumers in and about the Manila Metropolitan area and transmits power to a few nearby utilities for resale. Meralco sales in 1965 ancunted to 884, of the total for Luzon. Four-fifths of this energy 18 generated in Meralco owned oil-fired steam plants. The re- mainder 18 purchased from NPC's hydro generated power. Besides supply- ing to Mexalco, NPC also sells electricity to more than 100 small utilities serving the rural areas of Luzon. Because of this intertie between Meralco and NPC, the Luzon Grid can be considered an integrated system with Meralco supplying about 70% and NPC 30% of the energy. The second part of Phase A involved studies of local energy re- sources in Luzon, namely, hydro, coal, geothermal, and oil or gas. following summarizes the results of these studies: The Hydro Resources - An analysis of hydro electric resources in Luzon was carried out by a hydropower expert from Sweden. This involved an estimate of the overall hydropotential on the island and a review of poss. ble hydro development projects which could come into operation within the next decade. After discovering that information necessary for a proper analysis of the overall hydro potention on the island was unavailable, a rough estimate of this was computed from rainfall and topography records. This indicated a total hydro potential of 20 billion kwh/year might be expected to be economically feasible. This amount of energy corresponds to an installed electrical capacity of about 4000 to 5000 MW. Unfortunately, many difficulties stand in the way of developing this hydro power in the forseeable future. First, there is a long lead time to obtain adequate stream flow and geological data; second, almost all potential hydro sites are inaccessible and would require the es- tablishment of roads and other facilities; third, the most important river basins are far from the load centers and long transmission lines would be needed; and fourth, all of the future hydro projects considered so far involve large capital investments and cannot be justified for power production only. Thus, it was concluded that during the next decade, hydro development in Luzon will be confined to the projects &lready underway. Coal - Exploratory drilling operations were carried out in the two most promising coal areas near Luzon, and in each case about 3 million tons of recoverable coal sufficient to support two 25 MWE plants were identified. Even if such small plants were economic, their contribution would be small relative to future needs. Geothermal - Many areas exist in Luzon which show evidence of geo- thermal activity. Drilling operations and geological exploration of the most promising of these areas at Tiwi (near Legaspi) indicates the existence of underground high pressure.steam, which might be used for power production. The exploratory program, however, has not been carried far enough to establish the potential capacity of this site or of other sites in Luzon. In view of the further exploration required, it is - 5. unlikely that geothermal power will contribute significantly to Luzon's power needs during the period in question, 011 and Gea - The search for oil and gas in the Philippines has been underway for many years and about $30 million were spent in the 1950's on drilling operations. So far no commercial reserves have been uncovered, and exploration activities have practically ceased. This means that the possibility of discovering a large source of oil or gas in the near future is remote and continued reliance must be placed on imported oil. The present outlay of foreign exchange for imported crude oil (which is refined loca?ly) is about $60 million. Findings of Phase A To summarize the results of Phase A studies, these indicated that local energy sources, namely hydro, can meet only a su the future power needs in Luzon. The remaining portion will have to be provided by thermal team plants. The projected distribution of the power supplied to the Luzon Grid is given in Table 1. Table 1 Power Requirements of Luzon Grid 1965 System Input, millions of Kwhr Total Installed Capacity, Mwe(1) Hydro Capacity, MWE Thermal Steam Capacity, MWE 3,660 670 230 440 1970 6,730 1,580 450 1,130 1975 .22,060 2,670 550 2,120 (1) Name plate rating only (maximum capability 10% higher). Commitments and advance planning by the power companies in Luzon made by 1965 provide for adding 690 MWE of new oil-fired capacity by 1970; however, the 1000 MWE of thermal steam capacity to be added to the Grid during 1970-1975 has not yet been ordered. The two important conolusions that can be reached from these figures are first that about 1000 MWe of nuclear or conventional thermal steam capacity will be added to the Luzon Grid between 1970 and 1975, and second that during this period, the Grid will become large enough to warrant the construction of plants in the 200-300 MW size range. Phase B Studies The findings of Phase A paved the way for Phase B of the project which was initiated in February 1965. The main purpose of this phase of the work was to determine the most economic method of meeting the future power requirements in Luzon during the next decade. - 6 - Capital Costs of Nuclear and Conventional Plants A contract was awarded to Burns and Roe of New York to prepare costs ot' nuclear and conventional plants of 200 MW, 300 MW and 400 MW sizes. A 100 MW oil-fired plant was also considered in order to compare estimated costs with actual costs of constructing 100 MW oil-fired plants in the Philippines. Burns and Roe estimated these costs by contacting vendors throughout the world who in turn submitted estimates of the costs of all major plant equipment delivered in the Philippines. costs of constructing the plants were then added, using appropriate factors to correct for dif- ferences in labor costs between the Philippines and the United States. The resulting direct costs were then adjusted to allow for engineering services, contingencies, and interest during construction. Estinates of costs of other items associated with the plant, such as the substation and switchgear, housing for enployees, spare parts, transportation and customers costs, were also obtained and added to the cost of the plant itself. Three types of puclear plants of proven technology, namely, boiling water, pressurized water, and heavy water, were considered along with a conventional oil-fired plant similar to Meralco's 200 MW Tegen Station. All costs were based on a site in Bataan which was selected. as a result of the site surveys that were undertaken. Both indoor and outdoor type plants were considered. Capital costs for representative indoor type plants are given in Table 2. Table 2 (in millions of dollars) Conventional Nuclear (oil-fired) (Light Water) MW = 200 300 200 200 300 400 Main plant 23.8 33.9 42.2 33.7 44.0 52.8 patatea temell) Associated items 2.4 3.0 3.2 3.8 4.7 5.4 Total 26.2 36.9 45.4 37.5 48.7 58.2 Import Taxes and in- terest during construc- tion on same 3.8 5.4 5.18 5.5 7.4 8.8 Total 30.0 42.3 52.2 43.0 56.1 67.0 "Substation and switchgear, housing, transportation, customers costs. All individual costs are expressed in U.S. dol.lars; however, the Burns aná Roe estimate actually separated foreign exchange costs from the local costs. Excluding taxes, it was found that local costs amounted of the total costs for all of the cases considered. - 07- In extrapolating power plant cost data from manufacturing countries to the developing countries, it is generally found that she net costs in a developing country are higher. The estimates prepared by the consulting firm indicate that this is not the case in the Philippiucs. Both conven- tional and nuclear plants are expected to cost no more in the industrial sectors of Luzon than in most parts of the United States. In fact, con- ventional plants may cost even less, in spite of higher interest during construction, the extra charges for ocean freight, and import taxes which are 10% and 20%, respectively, of the cost of imported items. This is explained by several favorable factors, including the locally available low cost but skilled and trained labor force which is highly productive. Added to this is the experience developed by the two major utilities in building and managing a number of power projects. The cost estimates for conventional plants, prepared by Burns and Roe, Closely check with the actual figures for Tegen I and estimates for Tegen II and other plants. In fact, on the whole, Burns and Roe's esti- mates are rather conservative as they allow for a large amount of con- tingencies. Nuclear Fuel Costs Nuclear fuel cycle costs were calculated from reactor manufacturer's fuel elment design data, core loadings, and fuel management programmes using economic ground rules applicable to nuclear plants put into opera- tion after 1970. These 80-called projected costs", tales into considera- tion anticipated reductions in fabrication costs, reprocessing and other costs as a result of anticipated expansion of the U.S. nuclear power in- dustry and other industries throughout the world during the period 1970 to 2000. Fuel cycle costs based on these projected economic factors were derived by following all costs associated with each batch of fuel from the time the plant starts up in the early 1970's to the end of its 30 year life and putting these on & present worth basis using appropriate discount factors. An IBM computer code was developed which optimized the reprocessing cycle over the life of the plant and provided the input data for a second code which performed the present worth calculations. Fuel Oil Prices The average price of fuel oil delivered to Meralco in 1965 was $16.95/mt or 41.7 million Btu's. This includes 4.34 million Btu's for customs duty, special import and specific taxes, without which the price is 37.4¢/million Btu's. The special import tax of 1.7% is ex- pected to be abolished in 1966, reducing the price to 41¢/million Btu's with duty and special tax. The current fuel oil supply contract between Meralco and the local oil refineries covering the period January 1966 to March 1969 fixes the price at $16.95 per ton, assuming no price escalations and changes in Governmental taxes and duties occur. Comparative Power Costs in Nuclear and Oil-Fired Plants Power costs in nuclear and oil-fired plants, based on the economic data developed by Burns and Roe, were compared on the basis of both public and private utility ownership of the plants in question. In the former case, plant capital costs were based on 8% interest during construction. The annual fixed charges were calculated on the basis of 10% composite cost of money plus 1.7% for sinking fund depreciation, property taxes and conventional. plant insurance. An additional 0.3% was applied to nuclear plants to cover nuclear insurance. This lead to a total fixed charge rate of l1.74 and 12% for conventional and nuclear plants for publicly-owned utility plants. For investor-owned utilities, capital costs were based on 10% interest during construction. The annual fixed charges were calculated on the basis of 13% composite cost of money plus 2.6% for depreciation, taxes and insurance. The same factor of 0.3% was used to cover nuclear insurance. The fixed charge rates in this case amounted to 15.64 and 15.9%, respectively, for conventional and nuclear plants. An 80% plant factor was used in all cases. The results of the calculations are summarized in Table 3. It is seen that, with present oil prices and projected nuclear fuel cycle costs, nuclear plants are competitive for base load operation for all sizes considered. Table 3 Comparative Power Costs in Nuclear and Oil-Fired Plants in Luzon Power Costs, mills/Kwh Nuclear Oil-Fired Public Ownership Basis 300 400 200 300 200 200 Fuel (1) Fixed Charges 3.22 2.79 2.49 2.19 2.06 1.90 Operating & Maintenance 0.34 0.27 0.23 0.26 0.21 0.19 1.60 1:59 1.59 3.55 3.40 3.36 Total 5.16 4.65 4.31 6.00 5.67 5.45 Investor Ownership Basis Fixed Charges 4.99 4.32 3.87 3.40 3.20 2.96 Operating & Maintenance 0.34 0.27 0.23 0.26 0.21 0.39 Fuel(2) 1.70 1.69 1.69 3.90 3.73 3.69 Total 7.03 6.28 5.79 7.56 7.14 6.84 (+) "Projected" nuclear fuel costs, oil at 37.4 cents/106 Btu (tax free basis). (2) "Projected" nuclear fuel costs, oil at 41.1 cents/106 Btu (lax in- clusive basis). - 9. The influence of varying fuel oil prices in Luzon was also con. sidered. In this case all investment, fuel and operating costs asso- ciated with any given plant during its 30-year lifetime were put on a present worth basis. In this regard, discount factors of 10% and 13% representing the composite costs of money for public and private owner- ship, respectively, were used. The difference in total present worth of all costs, then, indicated the savings for a nuclear plant over an oil-fired plant. The results are shown in Table 4, which indicate that publicly-owned nuclear plants can compete with fuel oil at 30€) 106 Btu in all sizes considered. Privately-owned 200 MW units, on the other hand, are competitive with oil at 37 cents per million Btu, whereas 300 MW and 400 Mw nuclear plants are competitive with oil at 33 cents/ 106 Btu and 314/106 Btu, respectively. Table 4 37.412) Present Worth of Saving for Nuclear Plants in Luzon Grid for varying Fuel Oil Prices(I) Present Worth of Total Savings in Investment & Operating Costs, millions (Publicly-Owned Utility) Fuel Oil Price, cents/206 Btu 200 MW 300 MW 400 MW 40 12.7 22.8 33.2 9.5 18.1 27.0 6.5 13.8 21.3 0.2 4.8 9.5 (Investor-Owned Utility) 4.3 12.0 19.6 10.4 17.5 3.3 8..2 -6.2 -3.8 -1.3 (1) Plants operating at 80% capacity factor Present fuel oil price - tax free basis (3) Present fuel oil cost - tax inclusive basis (4) Negative savings indicate nuclear plant not competitive 41.1(3) 3.2, 35 -1.8 30 System Planning Studies The comparison of power costs of individual nuclear and conventional plants of given sizes provides an indication of their relative competi- tiveness under various conditions. However, this is not sufficient to etermine the optimum sizes and schedules of additions of such plants to the Luzon Grid. Such simple comparisons of power costs do not take into consideration the influence of new units on existing hydro and oil-fired plants in the Grid. To develop an optimum expansion programme, detailed system planning studies were carried out by Electricite de France (EDF) under contract with the IAEA. Four Philippine engineers from the - 10 - National Power Corporation, Meralco, and the Philippine Atomic Energy Commission participated in the studies which include 1. Develop monthly demand and energy requirements for the Luzon Grid as a whole for each of the years from 1965 to 1977. 2. Establish the mode of operation of each of the existing and planned hydroelectric stations in the system so that they collectively make the optimum contribution to the Grid Load requirements. 3. Determine the net demand and energy requirement of thermal (conventional or nuclear plants to 1977 from the total power demand on the Grid and the contribution of hydro plants. 4. Calculate the present worth of capital and operating costs associated with various alternative programmes of adding thermal plants to the Grid under varying economic assumptions. In order to cover the entire range of economic conditions which might be encountered, the system planning studies were carried out for the forty eight combinations of the following parameters: oil prices: 30, 35, 40 cents per 106 Btu nuclear plant costs: B&R estimates, B&R estimates + 10% nuclear fuel costs: present day costs, projected costs interest rate: 10%, 13% load growth projection: Case I (median projection), Case II (minimum projection) The results showed that for the first plant added to the Grid in 1971, when conditions tend to favor nuclear plants, the optimum size of such plants is 300 MWE or higher, whereas under conditions favoring oil-fired plants, the optimum size is about 250 MWE. Taking these two optimum sizes under consideration, the plants which will yield maximum savings under the given conditions are shown in Table 5. Similar calculations were carried out for the subsequent new plants to be added to the Grid from which it was found that under conditions which lead to a choice of a nuclear plant as the first unit after 1971, the next two units should also be nuclear. Under conditions favoring the construction of a 250 MW oil-fired plant in 1971, on the other hand, subsequent units should also be oil-fired. At least as long as these conditions remain unchanged. - 11 - Table 5 Choice of First Unit to be added to the Grid in September 1971 Fuel Oil Cost Cents per 106 Btu 20% Interest Rate Nuclear Fuel Cost Projected Present 130 Interest Rate Nuclear Fuel Cost Projected Present Capital Cost Nuclear Plants 40 Nuclear Nuclear Nuclear Nuclear Burns and Roe Estimate Burns and Roe Estimate + 10% Nuclear Nuclear Nuclear 011-Fired Nuclear Nuclear Nuclear Oil-Fired Nuclear Oil-Fired Oil-Fired Oil-Fired 35 Burns and Roe Estimate Burns and Roe Estimate + 10% Burns and Roe Estimate Burns and Roe Estimate + 10% (to) Case I load growth. 30 Nuclear Oil-Fired Oil-Fired Oil-Fired Oil-Fired Oil-Fired Oil-Fired Oil-Fired Proposed Grid Expansion Program for 1971-1975 Using the results of the system studies as a basis it is evident that if the price of oil in the Philippines continues at its present level through September 1971, it is apparent that the most economic unit to be added to the Grid at that time would be a 300 Mw nuclear plant. If the same economic conditions continue to prevail, subsequent new units added up to 1976 would also be nuclear. In order to meet the Case I load growth projection to 1976, a total of 1000 MW of nuclear capacity would be necessary consisting of two 300 Mw units followed by a 400 Mw unit. The scheduling of such units and situation regarding reserves for a brownout. criterion of one year out of ten is summarized in Table 6. Table 6 Optimum Expansion Program for the Luzon Grid 1971-1975 First Unit 300 Size of Unit, MW Date of Operation Sept. 1971 Can Meet Thermal Peak Demand Until Sept. 1972 Total Installed Capacity, MW 1900 System Maxinium Demand, Mw 1540 Thermal Maximum Demand, Mw 1100 Total Reserve, MW 360 Reserve for Thermal Generation, MW 330 Second Unit 300 Sept. 1972 Oct. 1973 2200 1775 1330 425 400 Third Unit 400 Nov. 1973 Sept. 1975 2700 2170 1640 530 490 - 12 - As shown in this table, the first two units would have to be con- structed only one year apart. For this reason, it might prove wise to order two identical units from the same manufacturer for installation on the same site. This approach would certainly result in considerable savings not only because of lower prices from the equipment suppliers but also because of savings in site preparation and civil works. Regarding the third unit to be added to the Grid, no firm decision on this will be necessary until about the end of 1969. At that time tion on oil prices and load growth would be available as a basis for selecting the size and type of unit to be added. to be added to the Grid after 1970 appears to have a sound basis, it must be pointed out that the assumed economic conditions could change. For example, the price of fuel oil could drop considerably leading to the choice of conventional plants for subsequent units. The proposed power expansion program for Luzon is plotted in Figure 2. Financial Analysis of the Proposed Expansion Program In order to establish the overall economic advantages of adding 1000 MWE of capacity to the Luzon Grid, the construction expenditures and associated operating costs of the nuclear plants were compared with those for equivalent oil-fired capacity. Figure 3 shows the on-line schedules for these two alternate programs. The associated construction costs are given in Table 7. Nuclear fuel cost savings relative to oil at 41.1¢/million Btu (after allowing for initial fuel investment costs) are shown in Table 8 along with the additional operation, maintenance, and insurance costs. The net annual savings effectively act as cash generated by the utility out of power revenues and this can be used to reduce the outstanding capital investment as shown in Figure 6. It is seen from this figure that the outstanding investment in nuclear plants matches that for the oil-fired plants in mid 1974. To find the effective "break even" dates of the two programs, however, all costs must be dis- counted back to the date of start of construction. Using a 10% discount factor, it was found that the additional investment in nuclear plants is compensated for by lower annual operating costs by 1979. Thus, it appears that the time during which the nuclear plant program can be considered an investment risk relative to oil-fired plants is relatively short. After 1979, of course, the nuclear plants would represent a decidedly lower investment risk than the oil-fired plants. Implementation of the Program An analysis of the economy of the Philippines and of the financial position of the two major utility groups indicates that even though foreign exchange is in short supply, raising of the capital expenditures for the proposed program ($182 million) can be achieved. It was not the purpose of the study to recommend that either Meralco and/or NPC undertake to 3000 ORNL - DWG 66-8348 -- - - .- C - - TABU C 2500 - TREAL INSTALLED SAPACITY - TOTAL RESERVE NUCLEAR 3 i THERMAL CAPACITY 2000 EXISTING OR COMMITTED . PROPOSED NUCLEAR 2 THERMAL RESERVE INSTALLED CAPACITY (Mw) TOTAL GRID DEMAND . 13. NUCLEAR I . | GARDNER 3 THERMAL DEMAND BATAAN 1 GARDNER 2 GARDNER 1 1000 ANGAT LESS BLAISDELLI TEGEN 2 500 JAN 1966 JAN 1967 JAN 1960 JAN 1969 JAN 1970 JAN JAN 1971 JAN 1972 JAN 1973 JAN 1974 JAN 1975 Fig. 2. Optimum Luzon Grid Expansion Program. • 14 - ORNL - OWO -1919 2600 INSTALLED CAPACITY NUCLEAR -OIL-FIRED 2000 робош NET THERMAL DEMAND 1000 500 JAN JAN 1972 JAN 1973 JAN 1974 JAN 1975 JAN 1976 1971 YEAR Fig. 3. Thermal Plant Schedules for Three Nuclear Plants Versus Four Oil-Fired Plants. - 15 - Table 7 Construction Costs for Alternate Expansion Programs (+) Unit 1968 1974 48 Conventional Oil-Fired, $ millions 1969 1970 1971 1972 1973 13.67 16.65 3.93 2.05 11.90 18.15 4.63 2.48 13.67 3.93 2.48 13.67 16.65 15.72 31.03 38.23 34.95 20.58 18.20 49.23 87.46 122.41 142.99 1st (250 MW) 2nd (250 MW 3rd (250 MW) 4th (250 MW) Annual Total Cumulative 16.65 2.48 2.48 3.93 3.93 346.92 Unit 1967 1.54 1972 1973 1968 7.76 1.54 1st (300 MW) 2nd (300 MW) 3rd (400 MW) Annual total Cumulative Nuclear, $ millions 1969 1970 1971 29.60 13.40 4.80 7.76 29.60 13.40 1.36 7.24 32.30 38.72 50.24 50.50 49.56 99.80 150.30 7.71 4.80 19.60 24.40 174.70 1.54 1.54 9.30 10.84 7.71 182.41 (+) Exclusive of fuel investment. Table 8 Fuel Savings and Additional Annual Operating costs For Nuclear Expansion Program, $ millions Net Annual Savings Year Extra Operating Costs 0.10 0.36 0.60 Fuel Cost Savings 0.79 4.64 8.41 14.03 14.98 15.63 15.34 15.26 15.15 15.05 1971 1972 1973 1974 1975 1976 1977 1978 1979 1980 0.92 0.62 0.62 0.62 0.62 0.62 0.62 0.69 4.28 7.81 13.12 14.36 15.01 14.72 14.64 14.53 14.43 - 16 - ORNL - DWG 66-8320 NUCLEAR PLANTS TOTAL CONVENTIONAL PLANTS TOTAL XNUCLEAR PLANTS NET CUMULATIVE INVESTMENT (dollars x 40) 1967 69 74 73 77 79 81 75 YEAR Fig. 4. Cash Investment Flow Analysis for Four 250 MW Oil-Fired Versus Iwo 300 Mw and One 400 MW Nuclear Plant. - 17 - build nuclear plants, however, the economic studies certainly point toward such a decision. In this regard, it should be mentioned that the proposed program is based upon integrated operation of the Luzon Grid as a single system; therefore, close cooperation of the two utility groups is necessary to implement this program. In other words, the use of available hydro power for peaking purposes and nuclear plants for base load operation is necessary to minimize total generating costs. Thus, free exchange of power between the systems concerned is clearly most advantageous to the country as a whole. With regard to the requirements for technical manpower to operate and maintain auclear power stations, the country can train the needed staff in parallel with the construction of its first nuclear power station by using the facilities of the Philippine Atomic Energy Com- mission, the power plants of local companies, and by sending people abroad. Besides effecting the aforementioned economic gains, the use of nuclear power could help to diversify the sources of energy used for meeting Luzon Grid power requirements and reduce dependence on one particular form of energy, namely, fuel oil. Any competition from nuclear power plants could also have a restraining influence on future prices of fuel oil for conventional stations. Introduction of nuclear power technology would require a re- orientation in scientific and technical education in the country. With proper planning it could have a stimulating effect on the develop- ment of science and technology in the Philippines. If Efter reviewing the Study the Philippine Government and the utilities concerned arrive at the conclusion that the proposed program, including nuclear plants, is economically attractive', then a decision in principle should be made to go ahead with the introduction of nuclear power at the earliest opportunity. Since the completion of a nuclear project requires a lead time of five years, it is essential to make this decision before the end of 1966. International bids should be invited from nuclear and conventional power plant suppliers on the basis of firm prices and warranties re- garding the performance of the plants. Then, on the basis of actual quotations, a detailed economic comparison should be made to confirm if the conclusions regarding the economic merits of nuclear plants as indicated in this study are still valid. If the nuclear plant shows advantage and necessary financing has been arranged, a contract for building a nuclear plant may be entered into. . . .... . . . . . ... . * IN - . .. V 17 BULVARO hm... . - . . ... .... . '. ... Tk... . + . END DATE FILMED 12/ 28 / 66 ..tr . .. i . .