the university of ILLINOIS library G2.1.3G In 2. we t TV <5 t GENERAL INDEX. C. R. per Factory Electrical value at 75° = 132*796. Calculated temperature of cable ,\=58°*9 Fahr. [C.F.T. Tables]. Observed temperature = 56° Fahr. ft D. R. test with 72 cells [110 volts by test] 0 through 1 = 1940. Deflection from each core, nil. S.R. = 10,000 m.p. = l. On the morning of Friday, June 14th, S.S. “ Buccaneer ” was in position over fault about 20 miles from Waterville. A mark- buoy was let go in 52 fms., but unfavourable weather prevented any further work being done till the following morning. On Saturday, June 15th, at 3rd drag (1.0 p.m.) cable was hooked, and brought to bows. Depth of water = 53 fms. Temperature = 48° Fahr. Cable hooked : Siemens’ type 8555, 12/2. Cable was cut, 1 fm. being cut off for damaged end, after which ship spoke Waterville on D.C. morse, and made tests : 40 General Electrical Report. C.R. Plain core = 253*47 ctd. at S.T. Rib „ =252-79 ,, „ Distance to Waterville Office by C.R. = 20-191 n.m. Test for insulation with 30 volts : D.R. ft ft Plain core 1st min. electn. Total = 198 : per n.m. =3998 Rib „ „ „ „ =198 „ =3998 After ship and shore had exchanged messages, ship buoyed Waterville end (3.30 p.m.) and started to pick up on Weston end. At a distance of 7 fms. from end, cable was found badly damaged, with several sheathing wires broken. Cable was cut to seaward of damaged place. (Total cut off =8 fms.) Ship then spoke to Weston and made tests for insulation with 30 volts. Distance to Weston = 310*969 n.m. (core). D.R. Plain core. Total D.R. =2779 ohms. (Res. to earth of fault.) ft ft Rib core 1st min. Total D.R. = 24*750 : per n.m. = 7697. Ship continued to pick up, and at 5 p.m. a splice, followed by a very bad pulled-out kink, came on board followed by much slack cable in festoons. At 5.25 p.m., cable was cut seaward of another bad kink. Cable picked up, called Piece 1=0*182 n.m. Tests to Weston (5.45 p.m.) showed fault in Plain core to be still seaward of ship. Ship continued to pick up, and at 6 p.m. another splice came in beyond which cable was Siemens, type 8554, 12/4. Cable was cut (6.3 p.m.) just beyond this second splice. Piece picked up was called Piece 2 = 0*206 n.m. Fault was found to be in Piece 2 : £) ( Plain core. Total D.R. = 2829 ohms. (Res. of fault to earth.) \ Rib core D.R. perfect. 41 General Electrical Report. Ship’s tests to Weston (6.33 p.m.) were found to give satisfactory results. Insulation tests with 30 volts : ft D.R. ( Plain core 1st min. elec. Z to L. Total = 26-053 : per n.m.= ft 8094. ft ft Rib core 1st min. elec. Z to L. Total = 24-750 : per n.m.= 7689. Ship had started to make test for C.R. when, on a further length of cable being picked up, a bad kink was brought in on board, the cable being subsequently cut (6.50 p.m.) seawards of this bad place. Piece picked up called Piece 3=0-098 n.m. Ship made test for C.R. on Weston end. Distance to Weston = 310-581 n.m. (core). n p f Plain core. Total = 3939-6 ctd. = 12-684 per n.m. at S.T. 1 Rib „ Total = 3934-9 ctd. = 12-669 „ „ Test for insulation (with 30 volts) on Weston end : ft ft -p. P | Plain core. Total = 27-501 : per n.m. = 8530. { Rib core. Total = 23*572 : per n.m. = 7312. Sounding made. Depth = 53 fms. Temp. = 48° Fahr. Two joints and a splice were then effected between the Weston end (twin core cable, Siemens’ type 8554, 12/4) and the new cable in S.S. “Buccaneer’s” after tank (Siemens’ type 8553, 15/9), this operation being completed at midnight. On Sunday, June 16th, 1901, at 0.15 a.m., S.S. “ Buccaneer ” started to pay out cable towards buoy on Waterville end. Total cable in circuit (each core) = 315-628 n.m. (core). ft ft -p. p (Plain core: 1' Elec. Z to L : Total = 27-501 per n.m. = 8680. JJ ” K * (Rib core: V Elec. Z to L : Total = 23-572 per n.m. = 7440. Tests during paying-out were satisfactory. At 2.5 a.m. the Waterville end was brought in on board. 42 General Electrical Beport. The following results of Waterville’s tests on Waterville buoyed end were then communicated to ship : Plain core Rib core ft ft (Z = 103 Total D.R. equivalent to 2079 per n.m. * (C = 69 )) >> >> 1393 „ Z = 165 >» >> j> 3332 ., C = 93*5 >> j» >> 1888 „ ( Plain core : Total = 6-423 mfds. = to 0*3181 mfd. (Rib core: „ =6-269 „ >> 0*3105 At 2.25 a.m. the cable was cut in ship’s after-tank, after a further length had been veered away during the picking up of the Waterville end. Total length each core paid out = 0*365 n.m. (by C.R.). ,, ,, cable paid out = 0*361 n.m. Ship’s tests 310*937 n.m. on new Weston end. Length of each core C.R. (Plain core: Total ==3948*3 calculated = 12*698 per n.m. at S.T. (Rib core: Total = 3944*4 calculated = 12*686 per n.m. at S.T. -i\ /r ,i , _ , (Calculated from Plain core = 52°* 6 Fahr. Mean cable temperature \ - Eib conj = ^ Fahr _ At 3.15 a.m., after despatch of messages from ship to Waterville, “ G.B.” was exchanged between ship and Weston and ship and Waterville respectively, the cable ends being then handed over for effecting of the final splice. At 3.30 a.m. the joints for the twin-cores were started, and by 6.15 a.m. the splice was completed, the bight being slipped at 6.30 a.m. On Monday, June 17th, the fault in Piece 2 was localized by Loop test, and was found at a discolouration in the gutta percha, at a splice (though not at the actual joint) and at a distance of 3 fms. from the top end of Piece No. 2. The fault itself had apparently been caused by the Teredo. A length of 7 fms. of core, including the fault, and cut from top end of Piece No. 2, was taken by Mr. John Gott for microscopic examination. 43 General Electrical Report. At 0.5 p.m. S.S. “Buccaneer” anchored off Weston-super-Mare. On Tuesday, June 18th, the following results of tests made by Weston and by Waterville on the Weston- Waterville 1885 cable after “Buccaneer” repair, were received by Mr. John Gott, the Commercial Cable Company’s Representative on board S.S. “ Buccaneer.” Weston Tests. Plain core : Mean of all readings : ft ft Z : 27*84 abs. 9202 per n.m. C : 25-13 „ 8307 „ „ Rib core: Z: 30-45 „ 10064 „ „ C : 26-81 „ 8860 „ „ C.R. corrected w — -8413 ft Non Earth : ) ( C to Plain 28-08 abs. 9280 n.m. Mean of all readings: j (Z to ,, 26-79 ,, 8854 ,, ft Plain Z = 4592. Rib Z = 14910. Waterville ft C = 9228 C = 6584 Tests. Both by “ non earth ” ft Z to Plain = 10230 C to Plain = 8633 n -p , f Plain = 4207*5 C.K. corrected : | Rib = 42 0 l- 5 Note. — Total C.R. (by Factory Electrical value at 75° Fahr.) of OJ Plain core -f Rib core, including Waterville Land-line = 8835-43. On basis of Weston’s observed C.R., Mean Temperature of sea bottom = 53° Fahr. On basis of Waterville’s observed C.R., Mean Temperature of sea bottom = 52°-8 Fahr. [Using Clark, Forde, Taylor Tables for Copper.] 44 General Electrical Beport. Weston-Waterville (1885) Twin Core Cable. Data regarding Revision of Lengths after Repair by “Buccaneer.” N.M. Original length of cable before repair (not including 0-221 n.m. Waterville L.L.) ... =330-233 Original cable remaining ... ... ... ... =329-738 Cable cut out of line ... = 0-495 Original cable before repair (not including Water- ville L.L.) =330-233 Cable cut out of line = 0-495 Original cable remaining New cable laid in 329-738 0-348 Length after repair 330-086 Cable cut out of line ... New cable laid into line 0-495 0-348 Decrease = 0-147 Original cable before repair (not including Water- ville L.L.) =330-233 Decrease = 0-147 Length since repair ... =330-086 To which must be added 0-221 n.m. Waterville L.L. Total length by core (not including Waterville L.L. of 0-221 n.m.) = 330-902 n.m. EDWARD RAYMOND-BARKER. 45 General Electrical Report. Factory Electrical Values at 75° F. of Twin Core Cable, Shipped on Board S.S. “Buccaneer,” June 11th, 1901. m Core 90 lbs. cu. solid wire Type, Siemens 8553, 85 lbs G P per N,M ’ Type. Length $T.M. No. of Wire. C.R. at 75° F. Capacity. D.R. at 75° Fahr. Total. P^r N.M. Total. Per X.M. Total. Per N.M. 8553 5-000 1 66*372 13-13 1-6702 0-3304 472-81 2390 (Cable) 99 5*055 2 66-424 1314 1-6636 0-3291 580-62 2935 (Core) Cable on Board S.S. “Buccaneer,” June 11th, 1901. Fore Tank. After Tank. Type. Length. N.M. 8553 5-000 7 ~>' Cable on Board S.S. “Buccaneer” on Beturn to Silyertown Works, June 25th, 1901. Fore Tank. After Tank. Empty. Type. Length. N.M. Piece 1. 0-182 Piece 2. 0-199 Piece 3. 0-098 8553 4-639 - 7 f— - 7 ' — ' ~7 — ' ~7 if—' ~7 if—' ~7 if— r >f- v / mfls. mfd. 3-845 52-03 0 ) 13-54 1-185 mftls. 0-3082 “ Bittern.” 14-304 18149 190-80 242-83 13-342 4-342 5-527 0-3036 1022 19-171 13-61 256-44 13-342 0-309 5-836 0-3036 0-671 19-842 8 95 265-39 13-342 0-203 6-039 0-3036 \ “Marmion.” 3-598 23-440 47-67 313-06 13-25 1-202 7-241 0-334 ) 1-109 24-549 14-80 327-86 13-342 0-336 7-577 0-3036 1-089 25-638 14-26 342" .2 13T0 0 329 7-906 0-3022 > “Mirror.” 1-782 27-420 23-77 365-89 13-34 0-539 8-445 0-3025 ) 5-831 33-251 77-80 443-69 13-34 1-765 10-210 0-3027 1-561 34-812 27-32 471-01 17-51 0-498 10-708 0-3192 / “ M.B.” Rockport \ Type. 1-249 36-061 16-63 487-64 13-32 0-377 11-085 0-3019 J 0-285 36-343 3-86 491-50 13-55 .0-087 j 11-172 0-3054 > “ Mirror/’ 0-630 36-976 8-51 500*01 13-51 0-194 11-366 0-3079 ) 12-988 49-964 173*38 673-39 13-35 3-930 15-296 0-3027 8-460 58-424 113-84 787-23 13-46 2-570 17-866 0-3038 18-524 76-948 245-91 1033-14 13-28 5-580 23-446 0-3013 14-431 91-379 19404 1227-18 13-45 4-407 27-853 0-3055 26-201 117-580 346-42 1573-60 13-22 7-845 35-698 0-2995 63-925 181-505 849-38 2422-98 13-29 19-133 54-831 0-2993 31-575 213-080 425-45 2848-43 13-48 9-595 64-426 0-3040 86-660 299-740 1154-08 4002-51 13-32 26-098 90-524 C-3011 10-841 310-581 14307 4145-58 13-197 3-259 93-783 0-3006 0-351 310-932 4-61 4150-19 13-13 0-116 93-899 0-3304 f S.S.“ Buccaneer.” \ June 16th, 1901. 11-692 322-624 156-31 1 4306-50 13-37 3-571 97-4.0 0-..055 0-340 322-964 4-48 4310-98 1 13-17 0-113 97583 0-333 1 “ Marmion.” 7-938 330-902 106T3 1 4417-11 13-37 2-425 100-008 0-3056 WATERVILLE BEACH. 48 FACTORY ELECTRICAL VALUES AT 75° FAHR. of the Weston — Waterville (1885) Twin Core Cable after Repair by S.S. “Buccaneer,” June 16th, 1901. [Not including 0-221 n.m. Waterville Land-line (Core §§).] RIB CORE. Length. Length O.R. at 75° Fahr. Capacity. Remarks. Section. N.M. Total N.M. Total of Section. Sum of Totals. Per N.M. of Section. Total of Section. Sum of Totals. Per N.M. of Section. WESTON. 3-845 51-94 13-51 1-165 0-303 “ Bittern.” 14-304 18-149 191-00 242-91 13-35 4-248 5-413 0-297 1-022 19-171 13-64 256-58 13-35 0-303 5-716 0-2966 ) 0-671 19-842 8-96 264-54 13-35 0-199 5-915 0-2966 L “ Marmion.” 3-598 23-440 47-63 313-17 13-24 1-202 7-117 0-334 J 1-109 24-549 14-80 327-98 13-35 0-329 7-446 0-297 1-089 25-638 14-24 342-22 13-10 0-335 7-781 0-308 1 “Mirror.” 1-782 27-420 23-76 365-98 13-34 0-527 8-308 0-2959 J 5-831 33-251 77-84 443-82 13-36 1-725 10-033 0-2959 1-561 34-812 27-32 471T4 17-5 0-498 10-531 0-3192 / “ M.B.” Rockport \ type. \ 1-249 36-061 16-83 487-97 13-5 0-369 ' 10-900 0-2956 0-285 36-346 3-85 491-82 13-5 0-086 10-986 0-3018 L “ Mirror.” 0-630 36-976 8-49 500-31 13-5 0-191 11-177 0-3031 J 12-988 49-964 173-38 673 69 13-35 3-843 15-020 0-296 8-460 58-424 114-71 788-40 13-56 2-527 17-547 02-987 18-524 76-948 245-56 1033-96 13-26 5*529 23-076 0-2986 14-431 91-379 195-19 1229T5 13-52 4-380 27-456 0-3036 26-201 117-580 347-62 1576-77 13-27 7-744 35-200 0-2956 63-925 181-505 847-69 2424-46 13-26 18-854 54-054 0-295 31-575 213-080 421-04 2845-50 13-33 9-565 63-619 0-303 86-660 299-740 1153-23 3998-73 13-30 25-724 89-343 0-2969 10-841 310-581 142-92 4141-65 13T8 3-209 92-552 0-2960 /SS. “Buccaneer.” 0-351 310-932 4-61 4146-26 1314 0116 92-668 0-3291 \ June 16th, 1901. 11-692 322*624 155-92 4302-18 13-338 3-468 96T36 0-2966 0-340 322-964 4-48 4306-66 13-17 0-113 96-249 , 0-3330 “ Marmion.” 7-938 WATERVILLE BEACH. 330-902 105-80 4412-46 13-338 2-354 98-603 0-2966 49 D Weston— Watemlle (1885) Cable IRepalrs. BRISTOL CHANNEL. IR/EIF-A-IIR, TO THE Meston— Watecvnlle (1885) Cable. 1902 . GENERAL INDEX. Mestoit— Matecville (1885) Cable IRepalr EjpeMtton, 1902. S.S. “BUCCANEER.” PAGE GENERAL REPORT 3 List of Staff, Officers, Cable Hands and Crew ... 9, 10 Constants for Picking-up and Paying-out Drum 11 Distribution of Weight in ship on Leaving Gravesend ... ... ... 15, 16 Description of Cable 17 Steaming from London to Bideford 21 Grappling, etc 24-34 Completing Repairs ... 35, 36 Making Final Splice 37, 38 Steaming to and at London 39, 40 Distribution of Weight in Ship on Arrival in London 43, 44 Expenditure of Cable and Picked- up Pieces 45 Index to Electrical Report 49 ELECTRICAL REPORT 51 COMMERCIAL CABLE COMPANY’S CHARTER, Weston— Watemlle (X8S5) Cable IRepatrs. JANUARY, 1902. S.S. “BUCCANEER.” K 1 GENERAL REPORT. M. H. Gray, Esq., Silvertown. Silvertown, London, E., January 20th, 1902. Dear Sir, We left Silvertown at 11.45 a.m. on January 11th, passing Gravesend at 4.30 p.m. After a fair weather run we arrived off Bideford at 3.45 p.m. on the 13th, and anchored there for the night, as Mr. Gott could not get off to ship before morning. Mr. Gott joined ship Tuesday morning, 14th, and said that the fault in “rib” core was near final splice, 23 miles west of Lundy. The “plain” core was intact and working, the “rib” one giving dead earth. We proceeded to position and dropped mark buoy and started dragging in 38 fathoms. On Drag 3 got cable and spoke Weston. Tests O.K. to Weston, but Waterville side showed com- plete break, giving dead earth close to ship. Buoyed Weston end, and picked up towards Waterville, recovering *109 n.m. to broken end. This proved to be the fault. Cable had been damaged so that only one or two wires were holding, all others showing old fracture. This is supposed to have been done by a trawler. Proceeded to drag again, and on Drag 11 — Wednesday, 15th — hooked cable. Cable still faulty towards Waterville, showing fresh break. Picked up 0-477 n.m. to original fault Waterville end. Some time was lost here, owing to boat which had been sent away to replace lights on Weston buoy not being able to get back to ship on account of wind and tide, so ship had to -go and pick her up. As all hands had been working through previous night, I stopped work for night and dodged till daylight. On morning of 16th picked up towards Waterville 1-066 n.m., and broken end came in. This was a clean break, and appears to have been damaged by a trawler as in the original fault, 3 e 2 General Beport. and the final break caused by grapnel, which, from appearances, had evidently been over cable close to. On the same evening on Drag 18 we hooked cable to westward of fault, and spoke and tested to Waterville “ O.K.” In order to take advantage of the fine weather we spliced Waterville end on to tank end, and paid out towards Weston end 2*638 n.m., dropping final splice on Friday, 17th, in 40 fms., and after clearing the ground of cable and buoys, and as Mr. Gott did not wish to put in anywhere to take final tests, sailed for London at 3.50 p.m., Friday, 17th, arriving after a good run — with the exception of about six hours’ delay off Dangeness owing to fog — at Gravesend, 7 p.m., Sunday, 20th. On arrival there Mr. Gott heard that tests on the cable were “O.K.” I am glad to say that Mr. Gott expressed himself as very pleased with the way the work was conducted. As regards the nature of the sea bottom on which we were working, the Admiralty charts show a depth of 40 fms. with fine sand. We found the bottom hard in places, more like cement, over which the grapnel showed practically no dragging strain, and the cable on this hard bottom was fast to the bottom with marine growth. The amount of new cable used on this repair was 2*638 n.m., and the picked up cable, which is all good for relaying = 2*521 n.m. This is in four pieces, which Mr. Gott wishes spliced up to the remaining new cable. The extra length of cable after repair is 0*133 n.m. Indicator length. I will hand you the Engineering and Electrical Log in a few days. In conclusion I should mention the admirable way in which all departments on the ship worked together during this repair. I am, dear Sir, Yours faithfully, F. C. CRAWFORD. 4 THE COMMERCIAL CABLE COMPANY’S CHARTER. Bristol Channel IRepalrs, JANUARY, 1902. S.S. “BUCCANEER.” ENGINEER’S DIARY. LIST OF STAFF, OFFICERS, CABLE HANDS AND CREW. 7 S.S. “BUCCANEER.” LIST OF STAFF, OFFICERS, AND CREW. Mr. F. C. Crawford, Engineer in Charge. ,, H. E. Cann, Electrician. ,, E. H. Walker, Accountant. ,, T. W. Sharp, Master. ,, A. Troan, Chief Officer. ,, H. A. Ridsdale, 2nd ,, ,, A. J. Clunie, R. Murray, J. Kelly, J. Dickins, 4 Quartermasters. 6 Able Seamen. 3rd Carpenter. Boatswain. ,, Mate. 1 Deck Boy. Mr. A. White, ,, W. McFarlane, ,, C. Ball, ,, J. Ketley, J. Maguire, 6 Firemen. 4 Trimmers. Chief Engineer. 2nd 3rd 4th ,, Donkeyman. A. Patrick, B. Jardine, C. H. Benson, T. Templeton, H. Short, P. Neville, H. Dunlop, J. Gibson, J. Kingston, Chief Steward. 2nd ,, and Storekeeper. Chief Cook and Baker. 2nd ,, and Butcher. Pantryman. Engineers’ Steward. Assistant Steward. Officers’ Boy. Scullion. 9 S.S. “BUCCANEER.” CABLE W. Tillyer, B Butcher, R Keys, R. Schwartz, C. J. Cakebread, R. Duncan, W. Mack, A. Smith, R. Molt, H. Livingstone, A. E. Newton, Mr. J. Gott, Representative of ship off Bideford on January 14th. HANDS. Foreman. Leading Hand. 7 9 7 9 Lamps and Stores. Cable Hand. 99 99 7 7 99 n 7) Jointer. Fitter. Fitter’s Mate. Commercial Cable Co., joined Staff Cable Hands Officers and Crew Total persons on board on leaving London 3 11 42 56 10 COMMERCIAL CABLE COMPANY’S CHARTER. BRISTOL CHANNEL REPAIRS, 1902. S.S. “BUCCANEER. CONSTANTS FOR PICKING-UP AND PAYING-OUT DRUM. Circ. of Drum = 17’ 21" Type. Circ. in inches. Revs. per N.M. Log. Fms. per Revs. Siemens’ L.I. ... 3*465 347*886 2*5414375 2*916 Grappling Rope — 4x6, old 4*646 345*940 2*5390016 2*932 Buoy Rope — (Steel and Manilla) 4x4, new 3*860 347*233 2*5406213 2*922 3x3, new ... 2*700 349*159 2*5430228 2*905 11 COMMERCIAL CABLE COMPANY’S CHARTER. BRISTOL CHANNEL REPAIRS, 1902. S.S. “BUCCANEER.” 13 S.S. “BUCCANEER.” DISTRIBUTION OF WEIGHT IN SHIP ON LEAVING GRAVESEND. Cable in fore tank Tons. Ballast ,, ,, — Cable in after ,, .... 15-86 Ballast in after ,, — Coal in bunkers 265-00 Fresh water in after fresh water tank 13-00 ,, ,, ,, fore cone 8-00 ,, ,, ,, side tanks 4-50 Water in ballast tanks forward 75-00 ,, ,, ,, ,, aft 10-00 Boatswain’s stores forward 2-50 Carpenter’s ,, ,, •50 Cable- stores and buoys 11-00 Engine room stores 3-50 Water in main boilers ... 30-00 Steward’s stores 6-75 Extra chain cable 1-00 Spare anchors’ ropes ... ... ... 200 „ propeller 3-00 Deck machinery 10-00 Total 461-61 Draught of ship j ^° re ^ J mean 12' 1|". January 11th, 1902. DISTRIBUTION OP CABLE IN SHIP ON LEAVING GREENHITHE. January 11th, 1902.. S.S. “BUCCANEER.” DESCRIPTION OF CABLE. TWIN CORE CABLE. Siemens’ L.I. Type.— Their Factory No., 8553. Conductor : — Solid plain copper wire, weighing 90 lbs. per n.m. Dielectric : — Gntta percha, weighing 85 lbs. per n.m. Two cores as above — one marked with a “Rib” the other plain — laid up, wormed and served with tanned jute yarn. Sheathing : — 15 G homo wires, No. 9, L.S.G.="-144 dia. when galvanised. Breaking strain = 57 tons per square inch. Elongation = 9-4%. Outer Serving : — Two coats jute yarn prepared in compound, alternating with 3 coats of compound. Ex. diameter = 1"-103. Weight in air dry = 3*293 tons per n.m. ,, - „ wet = 3*420 „ ,, in sea water = 2-241 ,, ,, The above particulars taken from sample. January, 1902. 17 F COMMERCIAL CABLE COMPANY’S CHARTER. BRISTOL CHANNEL REPAIRS, 1902. ENGINEER’S GENERAL DIARY. S.S. “BUCCANEER.” / 19 v 2 STEAMING FROM LONDON TO BIDEFORD. HOUR, A.M. 8.30 11.30 11.45 P.M. 1.12 3.35 3.45 4.35 6.0 8.45 10.15 10.30 S.S. “ BUCCANEER.” SATURDAY, JANUARY 11th (1st DAY OUT). Commenced unmooring ship (off Works, Silvertown). Finished unmooring. All hands joined ship. Cast off all moorings and proceeded down river, Pilot Twist in charge. Brought up off Greenhithe to mooring buoy for adjusting compasses. Tug “ Rescue” assisting in swinging ship. Note . — This tug was hired on account of tug ordered, not being there. Finished adjusting compasses. Sent the following telegram : — “ Chief Officer, Coastguard Station, Bideford, Devon. Shall be much obliged if you could advise Mr. Gott, Royal Hotel, Bideford, when telegraph steamer ‘ Buccaneer ’ is off bar. Please advise me if any expenses incurred. ‘ Buccaneer ’ due Monday afternoon. M. H. Gray, Telegraph Works, Silvertown, Essex.” Cast off from moorings, and proceeded down river. Off Gravesend. Pilot Twist left ; Pilot Letten boarded. Nore Light vessel abeam. North Foreland abeam. South Foreland abeam. Dover pier works light vessel abeam, distant 1-5 n.m. Moderate S by W breeze, and overcast. 21 MID. Steaming from London to Bideford. S.S. “BUCCANEER.” HOUR. A.M. O. 35 3.55 4.0 8.0 10.30 10.35 10.55 NOON P. M. 1.30 2.51 4.0 7.35 8.0 11.30 MID. HOUR. A.M. 2.10 4.0 SUNDAY, JANUARY 12th (2nd DAY OUT). Dungeness Light abeam, distant 1*5 n.m. Beachy Head Light abeam, 3-25 n.m. Light variable airs. Overcast and hazy. Smooth sea. Swung ship for compass errors. Light S by E wind. Fine clear weather. Bar. 30-10. Ther. 65°. Stopped ship off Yentnor (Isle of Wight). Pilot Letten left ship. Set on full speed again. St. Catherine’s abeam, distant 3 n.m. Moderate WSW wind. Fine clear weather. Bar. 30-05. Ther. 57°. Distance run from London = 183-0 n.m. Passed cable s.s. “Britannia” bound up Channel. Portland Bill abeam, distant 8-8 n.m. Light variable airs. Fine weather. Smooth sea. Bar. 30-08. Ther. 56°. Start Point abeam, distant 8-0 n.m. Light variable wind. Fine clear weather. Bar. 30 07. Ther. 56°. Cable hands employed during the day getting all gear in order for grappling. Mechanics overhauling cable and sounding machinery. Eddystone Light abeam. Light variable airs. Fine weather. Smooth sea. Bar. 30-11. Ther. 65°. MONDAY, JANUARY 13th (3rd DAY OUT). Lizard Lights abeam, distant 7*0 n.m. Light variable airs. Fine clear weather. Smooth sea. Bar. 30-13. Ther. 51°. Wolf Rock abeam, distant 2-0 n.m. 22 4.35 Anchored in Bideford Roads. S.S. “ BUCCANEER.” HOUK. A.M. 8.0 NOON. P.M. 1.0 1.45 2.15 2.20 3.45 4.0 4.30 8.0 MID. MONDAY, JANUARY 13th (3rd DAY OUT) — Contd. Fresh NE breeze and clear weather. Bar. 30-02. Ther. 56°. Fresh NE breeze and overcast. Moderate sea. Bar. 30 25. Ther. 56°. -p ... , , f Lat. 51° 4'-0 N. Position by observation | Lon 4<3 47 ,. 0 w Distance run since noon yesterday = 223-0 n.m. Stopped ship and signalled Lundy Island : “Report me all well.” Proceeded towards Barnstaple Bay. Stopped and took Bristol Channel pilot on board. Proceeded towards Bideford. Anchored in Bideford Roads. Mr. Crawford went on board steam barge “ Ralph,” and sent telegram and letter to Mr. Gott re joining ship. As Channel pilot would not take ship over Bar, and said it would not be safe to send our boat in, Mr. Crawford arranged with a fisherman who was on board “ Ralph ” to bring Mr. Gott to “Buccaneer ” in morning. Mr. Crawford returned to ship. Fresh NE breeze and clear weather. Bar. 30-25. Ther. 53°. Cable hands employed during the day placing 40 class buoys in rigging and preparing moorings for same. Mechanics working at dynamometer. Cable flushed down with water. Moderate E by S wind and overcast. Bar. 30-40. Ther. 50°. A.M. 4.0 8.0 TUESDAY, JANUARY 14th (4th DAY OUT). Fresh ESE wind and overcast. Bar. 30-38. Ther. 49°. Fresh ESE wind and overcast. Bar. 30-51. Ther. 57°. 23 Grappling for Weston — Waterville 1885 Cable. S.S. “BUCCANEER.” HQUR. A.M. 9.30 9.45 9.55 10.40 NOON. P.M. 2.25 2.30 2.35 2.45 3.0 3.5 TUESDAY, JANUARY 14th (4th DAY OUT) — Contd. Mr. Gott came out from shore in schooner, lowered boat and sent her away to same. Mr. Gott arrived on board, hoisted up boat. Hove up anchor and set on for Morte Bay, to pilot cutter. Discharged pilot and proceeded towards cable ground. Moderate ESE breeze and fine weather. Bar. 30-62. Ther. 52°. T 5 ... , , ( Lat. 51° 12'-3 N. Position by observation | Lon ^ 37 ,. Q w Distance run since leaving Bideford = 24*7 n.m. Steamed to North end of Lundy Island to take departure for running 23 n.m. to put down Mark Buoy. Course S 88° W. Distance 23-5 n.m. In position to put down Mark Buoy. Sounding No. 1 = 38 fms. h. n.sn. Paid out buoy’s moorings and streamed buoy No. 42, “ P ” flag. Buoy’s moorings =-§•" bridle, 50 fms. f" chain mushroom = 5 cwts., 0 qrs., 3 lbs. -I-, • i • -p TV/T i -D f Fat. 51° 10'-5 N. Position of Mark Buoy | Lon g0 17 ,. g w Lowered cable cutter and sent her away to put lights on buoy. Boat returned to ship and was hoisted. GRAPPLING FOR WESTON— WATER YILLE 1885 CABLE. Drag No. 1. In position to grapple. Lowered ordinary long prong grapnel with 20 fms. f" chain, and commenced paying out 4x6 rope. Paid out to 70 fms. of rope and chain. Engines slow= (17 revs.). Sounding No. 2 = 38 fms. h. n.sn. 24 3.7 Grappling for Weston — Waterville 1885 Gable. S.S. “BUCCANEER.” HOUR. P.M. 3.30 3.50 4.10 4.20 4.24 4.30 4.45 4.55 5.0 5.5 - 5.20 5.30 6.0 6.25 6.32 6.40 7.15 7.22 7.23 TUESDAY, JANUARY 14th (4th DAY OUT) — Gontd. No strain. Paid out to 80 fms. of rope and chain. No strain. Commenced picking up. Grapnel at bows ; no sign of cable. Set on for new position. Drag No. 2. In position. Lowered same grapnel with 20 fms. -§" chain and commenced paying out 4x6 rope. Paid out to 80 fms. of rope and chain. Engines slow = 17 revs. No strain. Paid out to 100 fms. of rope and chain. Took weights off dynamometer. Strain rose to 18 cwt. ,, ,, ,,25 cwt. and fell to 18. ,, steady at 18 cwt. Stopping ship occasionally to reduce speed. Strain steady at 18 cwt. ,, rose to 50 cwt. Commenced to pick up. ,, fell to 10 cwt. (42 fms. out). Grapnel at bows. No sign of cable. Set on for new position. Drag No. 3. In position. Lowered same grapnel with 20 fms. f" chain, and commenced paying out 4x6 rope. Paid out to 100 fms.. of rope and chain. Engines slow = 17 revs. Strain suddenly rose to 140 cwt. Stopped ship. Paid out a few fathoms. Strain fell. Slow ahead. 25 Grappling for Weston — Waterville 1885 Cable. S.S. “ BUCCANEER.” HOUR. P.M. 7.25 7.30 7.43 8.0 8.5 8.15 8-30 8.50 .9.15 9.20 10.10 10.25 10.35 11.0 11.20 TUESDAY, JANUARY 14th (4th DAY OUT) — Contd. Strain again rose to 30 cwt. Stopped ship. Commenced picking np. 40 fms. of rope and chain out. Strain = 80 cwt. Grapnel at bows with cable. Siemens’ L.I. twin core, No. 8553. Set about bending on seizing chains of drum ropes. Fresh easterly wind. Clear weather. Bar. 30-70. Ther. 47°. Cut cable, got grapnel inboard, and took grappling rope off drum. Hove port end (Weston end) inboard. Cut 1 fm. off (damaged). Commenced testing cable towards Weston. Finished testing Weston end. O.K. Sealed ends. Veered away on Weston end, and picked up on Water- ville end by winch. Enough Waterville end inboard. Opened out and com- menced testing. Finished testing. Reported fault, short distance out- board. Cast Weston end off drum, and made it fast to windlass. Waterville end taken to drum, and commenced heaving it in. Broken end inboard. Ind. = 38 revs. = -109 n.m. Picked up = piece “A.” Preparing to buoy Weston end. Streamed buoy, and let go moorings with Weston end attached. Buoy’s Moorings = Buoy No. 43, “H” flag, 2 Miller’s Globes, 50 fms. f" chain, 10 fms. stray £" chain, mushroom = 4 cwt. 1 qr. 6 lbs. Position of Lat. 51° 10'-85 N. Lon. 5° 20' -85 W. Set on for new grappling position. 26 11.25 HOUR. P.M. 11.50 11.57 MID. A.M. 0.35 0.50 1.3 1.8 1.30 2.0 2.7 2.19 2.30 3.0 3.45 4.0 Grappling for Westo7i — Waterville 1885 Cable. S.S. “BUCCANEER.” TUESDAY, JANUARY 14th (4th DAY OUT)— Contd. Drag No. 4. In position. Lowered ordinary long prong grapnel, with 20 fms. f" chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Mod. WNW breeze. Fine clear weather. Bar. 30-84. Ther. 62°. WEDNESDAY, JANUARY 15th (5th DAY OUT). Strain = 30 cwt. (normal). Commenced picking up. Grapnel at bows. No sign of cable. Set on for new position. Drag No. 5. In position. Lowered same grapnel with 20 fms. f" chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Average strain = 20 cwt. ,, ,, =18 cwt. Commenced picking up. Grapnel at bows. No sign of cable. Set on for new position. Drag No. 6. In position. Lowered same grapnel with 20 fms. f" chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Average strain = 18 cwt. Moderate WNW wind. Fine clear weather. Bar. 31-20. Ther. 57°. 27 Grappling for Weston — Waterville 1885 Cable. S.S. “ BUCCANEER.” HOUR. A.M. 4.20 4.25 4.40 4.50 6.0 7.30 7.45 8.0 8.5 8.10 9.0 9.30 9.45 10.5 10.10 10.20 WEDNESDAY, JANUARY 15th (5th DAY OUT) — Contd. Strain = 18 cwt. Commenced picking np. Grapnel at bows. No sign of cable. Unshackled ordi- nary grapnel and shackled on ordinary centipede. Drag No. 7. In position. Lowered centipede grapnel with 2J- fms. f" trail chain and 20 fms. f" chain, and commenced paying- out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Average strain = 18 cwt. ,, =18 cwt. Commenced picking up. Grapnel at bows. No sign of cable. Set on for new position. Took centipede grapnel off and shackled on ordinary long prong grapnel. Similar wind and weather. Bar. 31*10. Ther. 53°. Drag No. 8. In position. Lowered ordinary long prong grapnel with 20 fms. f" chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Strain suddenly rose to 100 cwt. and fell again. Strain rising. Commenced to pick up. Grapnel at bows. No sign of cable, position. Drag No. 9. Set on for new In position. Lowered same grapnel with 20 fms. f " chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Strain commenced to rise steadily. Stopped ship. 28 Grappling for Weston — Waterville 1885 Cable. S.S. “ BUCCANEER.” HOUE. A.M. 10.25 10.30 10.40 10.45 11.30 NOON. P.M. 1.0 1.20 1.45 2.10 2.20 3.0 3.8 3.10 3.15 3.23 3.30 3.40 WEDNESDAY, JANUARY 15th (5th DAY OUT )-Contd. Strain — 25 cwt. Steady. Commenced picking up. Grapnel at bows. No sign of cable. Set on for new position. Deag No. 10. In position. Lowered same grapnel with 20 fms. f" chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Average strain = 18 cwt. ,, =18 cwt. Moderate NW wind. Clear weather. Bar. 30-68. Ther. 57°. -p f Lat. 51° 12'-0 N. Position by observation | L()n 50 16 ,. Q w Average strain = 18-20 cwt. Strain suddenly rose to 50 cwt. and fell again to 18. Average strain = 18 cwt. ,, =18 cwt. Commenced picking up. Grapnel at bows. No sign of cable. Set on for new position. Deag No. 11. In position. Lowered same grapnel with 20 fms. f" chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Strain suddenly rose to 100 cwt. Stopped ship and strain fell. Slow ahead again. Strain rose again to 140 cwt. Commenced picking up. Picking up strain = 100 cwt. Grapnel at bows -with cable, Siemens’ L.I. twin core, No. 8553. Set about bending on seizing chains of drum ropes. Cut cable and veered away on Starboard rope. 29 Buoying Waterville End and Picking Up Loose Piece . S.S. “ BUCCANEER.” HOUR. P.M. 3.52 3.55 4.0 4.35 4.40 4.45 5.0 8.0 9.5 9.30 9.55 10.24 WEDNESDAY, JANUAEY 15th (5th DAY OUT) — Contd. Took Port rope on Waterville end to drum, and started heaving in. End of cable abaft drum. Cut 2d fms. off damaged end. Light NW’ly breeze, and fine clear weather. Bar. 30-70. Ther. 56°. Commenced testing. Finished testing. Cable faulty towards Waterville. Lowered cable cutter and sent her away to put fresh lamps on cable buoy “ H,” about 3 n.m. distant. Took Waterville end off drum and made it fast to stoppers. Took short end to drum, set Indicator at zero, and commenced heaving in. Strain = 100 cwt. Found it impossible to heave loose piece on board while holding on to Waterville end. BUOYING WATERVILLE END AND PICKING UP LOOSE PIECE. Holding on everything. Light variable winds. Bar. 30-70. Ther. 54°. Awaiting boat’s return. Clear weather. Observed boat, after having lit buoy, being carried to leeward by tide, so instead of picking up towards Waterville decided to buoy that end and pick up short end towards Weston buoy, and go to boat’s assistance. Bent moorings on to Waterville end and commenced paying out same. Moorings all paid out. forward. Position of Buoy “ S ” Streamed buoy “ S ” and let go Lat. 51° IP *4 N. Lon. 5° 17'-8 W. Resumed heaving in on loose piece, coiling cable in fore tank. Sighted boat on Port bow. Broken end passed over drum. Indicator = 166 revs.= 0-477 N.M. = Piece “ B.” Set on to pick up boat. 30 10.55 HOUR. P.M. 11.10 MID. A.M. 4.0 6.0 8.15 8.45 9.0 9.8 9.15 9.40 10.14 10.20 10.25 Grappling for Waterville End of Cable (2nd Time). S.S. “ BUCCANEER.” WEDNESDAY, JANUARY 15th (5th DAY OUT)— Contd. Came up to boat and hoisted same. Finished for night. Set on to lie-to near cable buoys. Light variable airs and calms. Fine clear weather. Bar. 30-72. Ther. 53°. THURSDAY, JANUARY 16th (6th DAY OUT). Calm and clear weather. Bar. 30-72. Ther. 56°. Preparing to pick up buoy on Waterville end. Similar weather. Bar. 30-60. Ther. 53°. Lowered cable cutter and towed her to buoy. Up to buoy. Sent cutter away with drum rope. Commenced heaving in moorings of buoy. Waterville end of cable on drum. Set Indicator 0. Cut 2 fms. off (damaged). Coiling cable in fore tank. Hove up buoy and boat. 0- 50 n.m. of cable picked up. Cable in good condition. Picking up strain = 25 cwt. 1- 00 n.m. of cable picked up. Cable in good condition. Picking up strain = 18 cwt. Broken end passed over drum. Indicator = 371 revs.= 1-066 N.M. = Piece V C.” 4 fms. of this end was badly flattened out. GRAPPLING FOR WATERVILLE END OF CABLE (2nd TIME). Let go a paint drum with rope and sounding sinkers to mark position where end came on board. Lat. 51° IP-1 N. Lon. 5° 19'*5 W. Position Set on for grappling position. 31 10.30 Grappling for Waterville End of Cable (2nd Time). S.S. “ BUCCANEER.” HOUR. A.M. 10.40 10.45 10.50 11.0 11.5 11.25 11.40 NOON. P.M. 0.15 0.30 0.45 1.0 1.30 1.55 2.7 2.25 THURSDAY, JANUARY 16th (6th DAY OUT ) — Contd Drag No. 12. In position. Lowered ordinary long prong grapnel with 10 fms. -J" chain, and commenced paying-out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Strain steadily rose to 40 cwt. and fell again suddenly to 18 cwt. Strain suddenly rose to 25 cwt. Commenced picking up. Grapnel at bows. No sign of cable. Set on to light up cable buoy “ H.” Up to buoy. Lowered cable cutter and sent her away to put fresh lamps on buoy. Boat returned to ship and was hoisted up. Set on for new position to grapple. Calm, fine clear weather. Smooth sea. Bar. 30-58. Ther. 57°. Drag No. 13. In position. Lowered same grapnel with 10 fms. chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Strain = 18 cwt. ,, =20 cwt. Average strain = 18 cwt. Strain steadily rose to 30 cwt. Stopped ship and com- menced to pick up. Grapnel at bows. No sign of cable. Set on for new position. Drag No. 14. In position. Lowered same grapnel with 10 fms. chain, and commenced paying out 4x6 rope. 32 Grappling for Waterville End of Cable ( 2nd Time). S.S. “BUCCANEER.” HOUR. P.M. 2.30 3.0 3.15 3.25 3.35 3.42 3.45 3.47 4.0 4.15 4.30 4.35 4.40 4.42 4.45 4.58 5.15 5.30 5.42 THURSDAY, JANUARY 16th (6th DAY OUT) — Contd. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Strain = 20 cwt. ,, =18 cwt. ,, rose to 30 cwt. Slow astern, and commenced to pick up. 32 fms. out strain fell to 0. Grapnel at bows. No sign of cable. Set on for new position. Drag No. 15. In position. Lowered same grapnel with 10 fms. chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. Sounded in 36 fms. (Thompson’s Tube). No strain. Calm and clear. Bar. 30-40. Ther 60°. Strain = 10 cwt. No strain. ,, ,, Commenced picking up. Grapnel at bows. No sign of cable. Set on for new position. Sounded in 35 fms. (Thomson’s Tube). Drag No. 16. In position. Lowered same grapnel with 10 fms. chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. No strain. Strain = 10 cwt. ,, steadily rose to 20 cwt. Stopped ship and com- menced picking up. 33 G Grappling for Water mile End of Cable {2nd Time). S.S. “BUCCANEER.” II0UE. P.M. 5.47 5.50 6.40 6.45 7.15 7.40 7.48 8.0 8.15 8.5 8.15 8.42 8.45 8.50 9.0 9.10 THURSDAY, JANUARY 16th (6th DAY OUT)— Contd. 36 fathoms out. Strain suddenly fell to 0. Grapnel at bows. No sign of cable. Set on for new position. Unshackled ordinary grapnel, and shackled on Cole’s Centipede, with 2J fms. •§" trail chain. Ran to Cable Buoy and back to check distance off. Deag No. 17. In position. Lowered “Centipede” with 10 fms. f chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. No strain. ,, ,, Commenced picking up. Grapnel at bows. No sign of cable. Set on for new position. Light ENE wind and clear. Bar. 30-70. Ther. 56°. Deag No. 18. In position. Lowered same grapnel with 10 fms. chain, and commenced paying out 4x6 rope. Paid out to 100 fms. of rope and chain. Engines slow = 17 revs. No strain. Strain suddenly rose to 140 cwt. Stopped ship and paid out a few fathoms. Commenced picking up. Strain = 100 cwt. Picking up very slowly. Average strain = 80 cwt. „ „ „ » „ =100 cwt. Grapnel at bows with cable, Siemen’s type L.I., No. 8553. Strain = 120 cwt. Bent on seizing chains of drum ropes. 34 Completing Repairs to Waterville — Weston 1885 Cable. S.S. “ BUCCANEER.” HOUR. P.M. 9.30 9.35 9.40 9.50 10.50 10.52 11.45 MID. A.M. 0.20 2.20 2.25 3.25 3.30 4.0 4.10 4.15 THURSDAY, JANUARY 16th (6th DAY OUT) — Contd. Cut cable. Took grapnel inboard and grappling rope off drum. Veered away on port rope (loose piece).. Took drum rope on Waterville end to drum, and com- menced heaving in. Enough cable abaft drum for splice. Cut 1 fm. off , and commenced testing. Got top end of cable from after tank, and commenced opening out for splice with Waterville end. Finished testing Waterville end, O.K. Testing tank end. Finished testing. Telegram sent to — “ Silvergray, London. About to splice on to Waterville end and lay to Weston end. All well. Crawford.” Light variable airs. Fine clear weather. Bar. 30*72. Ther. 54°. FRIDAY, JANUARY 17th (7th DAY OUT). Commenced joints between Waterville end and cable in after tank. Cut 8 f ms. off after tank end for this splice. Finished joints. Each core brass taped over joint. Commenced splice. Finished ,, Preparing to buoy loose end. Calm and clear. Bar. 30*72. Ther. 56°. Veered away on drum rope on loose piece to end. COMPLETING REPAIRS TO WATERVILLE— WESTON 1885 CABLE. Attached end of drum rope on loose piece to Buoy No. 62 and let it go. 35 G 2 Completing Bepairs to Waterville — Weston 1885 Cable. S.S. “BUCCANEER/’ HOUR. A.M. 4.17 4.18 4.24 4.30 4.38 4.45 4.52 4.59 5.6 5.13 5.20 5.27 5.33 5.40 5.45 5.52 6.8 FRIDAY, JANUARY 17th (7th DAY OUT). — Contd. Commenced paying out cable from after tank towards buoy on Weston end. Engines = slow. Put engine out of gear. Brakes checking. Ind. = 0. Splice on drum. (Eat. 51° 10'*85: N. (Long, 5° 20'-85, W. Position of splice Ind. = 87 revs. = 0*250 n.m. paid out. Engines = 19 revs. Ind. = 174 revs. =0*500 n.m. paid out. Engines = 19 revs. Ind. = 261 revs. = 0*750 n.m. paid out. Engines = 19 revs. Ind. = 348 revs. =1*000 n.m. paid out. Engines = 19 revs. Ind. = 435 revs. = 1*250 n.m. paid out. Engines = 19 revs. Ind. =522 revs. = 1*500 n.m. paid out. Engines = 19 revs. Ind. = 609 revs. = 1*750 n.m. paid out. Engines = 19 revs. Ind. = 696 revs. =2*000 n.m. paid out. Engines = 19 revs. Ind. = 783 revs. = 2*250 n.m. paid out. Engines = 19 revs. Ind. =870 revs. = 2*500 n.m. paid out. Engines = 19 revs. Strain = 10 cwt. Strain = 10 cwt. Strain = 15 cwt. Strain = 15 cwt. Strain = 15 cwt. Strain = 15 cwt. Strain = 15 cwt. Strain = 15 cwt. Strain = 15 cwt. Strain = 15 cwt. Approaching buoy on Weston end of cable. Lowered boat. Put brakes down and engine in gear. Sent boat with drum rope to buoy “ H ” on Weston end. Commenced heaving in on drum rope. Cleared buoy from moorings, and hoisted up buoy and boat. Took cable off drum. Ind. = 908 revs. = 2*610 n.m. 36 HOUE. A.M. 6.10 6.15 6.40 6.45 7.0 8.0 8.20 9.40 11.10 11.15 NOON. P.M. 0.5 0.8 0.15 0.20 0.40 Making and Slipping Final Splice. S.S. “BUCCANEER.” FRIDAY, JANUARY 17th (7th DAY OUT) — Contd. Took buoy’s moorings to drum, and commenced picking up on same. Veered away on cable (Waterville end). Weston end of cable on drum. Enough cable abaft drum for splice. Commenced testing. / Commenced opening out ends ready lor final splice. Gut 8 fms. off tank end (Waterville end). Calm and clear. Bar. 30-60. Tber. 55°. Telegram sent to — “ Graysilver & Silvergray, London. About to make final splice. Expect to sail for London direct this evening. All well. Crawford.” MAKING AND SLIPPING FINAL SPLICE. Finished testing. Commenced joints. Finished joints. (Each core brass taped over joint.) Commenced splice. Sounding No. 3T in 41 fms. n. sn Bottom. Temp. — min. 49°-2 F., max. 51° Light variable wind and clear. Bar. 30-62. Ther. 55°. Finished splice. Bent slip ropes on to cable and commenced veering away on same. Bent slip stopper on to bight of cable. Slipped final bight. Set on for mark buoy “ P.” -p ... - n , r i Lat. 51° IP-5 N. Position of final splice •< Lon _ 5 o 17 ,. Q Total length of netv cable laid in by Ind. = 2-621 n.m. = 8 fms. for splices = 2-613 n.m. Total length of new cable now in after-tank = 2*010 n.m. Up to buoy. Lowered cutter, and sent her with drum rope to dismantle buoy. 37 HOUB. P.M. 0.45 0.50 1.10 2.20 2.25 2.45 2.50 3.15 3.45 3.50 3.57 4.0 4.38 8.0 11.55 Making and Slipping Final Splice. S.S. “ BUCCANEER.” FRIDAY, JANUARY 17th (7th DAY OUT) — Contd. Slipped buoy from moorings, and commenced picking up moorings. Hoisted up buoy and boat. All buoy’s moorings on board. Set on for buoy on short piece of cable. Up to buoy. Lowered boat and sent her with drum rope to buoy. Slipped buoy from moorings and commenced heaving in on drum rope. Hoisted up buoy and boat. End of loose piece of cable on drum set Ind. 0. 0-50 n.m. of cable picked up. Cable in good condition. Broken end in board and on drum Ind. =294 revs.= O' 845 n.m. Piece “ D.” About 50 fms. from end cable showed signs of having been booked previously. Set on for London. On starting the engines it was found that something was foul of the propeller. On inspection the paint drum put down Friday morning was found to be jammed between the blades of propeller and the stern post. Lowered boat and cleared propeller. Calm and overcast. Bar. 30*40. Ther. 50°. Hoisted boat and set on again. Calm apd overcast. Bar. 30*40. Ther. 60°. Longships abeam. Calm and clear. Bar. 30*34. Ther. 60°. 38 MID. Steaming to London. S.S. “BUCCANEER.” HOUR. A.M. O. 15 2.35 4.0 7.10 8.0 9.55 NOON P. M. 4.0 7.0 8.0 MID. A.M. 1.25 2.0 2.30 4.0 4.40 8.0 STEAMING TO LONDON. SATURDAY, JANUARY 18th (8th DAY OUT). Wolf Rock abeam. Lizard Lights abeam. Distant, 6-0 n.m. Light ENE wind, and overcast. Bar. 30-36. Ther. 58°. Eddystone abeam. Distant, 8 n.m. Similar wind and weather. Start Point abeam. Distance, 3-3 n.m. Mod. ENE breeze. Overcast. Bar. 30*33. Ther. 62. Light ENE breeze, and misty. Bar. 30-40. Ther. 70. St. Catherine’s Point abeam. Distance = 7*5 n.m. Cable hands employed during the day clearing up and stowing away cable gear. Mechanics overhauling and dismantling machinery. Light ENE breeze. Fine clear weather. Bar. 30*40. Ther. 69°. Light ENE breeze, and misty. Bar. 30-35. Ther. 54°. SUNDAY, JANUARY 19th (9th DAY OUT). Beachy Head. Bearing north true. Light breeze, smooth sea, with fog. Royal Sovereign abeam. Light ENE breeze. Smooth sea. Clearer. Bar. 30-4. Ther. 64° F. Weather thick. Slowed engines. Hearing fog trumpet from Yarne lightship close by, turned ship round and decided to lie to till fog lifted. Misty. Bar. 30-40. Ther. 50° F. 39 Arrival in London. S.S. “ BUCCANEER.” HOUR. A.M. 8.30 9.30 10.0 11.15 NOON. P.M. 0.45 2.50 4.0 4.35 5.30 6.0 7.0 9.0 9.30 1.0 3.0 SUNDAY, JANUARY 19th (9th DAY OUT) — Gontd. Made the land to westward of Dungeness. Weather setting in thicker. Dropped Port anchor and paid out 30 fms. chain. Sounding whistle for pilot. Pilot boarded. Weighed anchor and proceeded slow. Weather clearing. Weather clearing. Set on full speed. Light ENE breeze. Misty. Bar. 30*40. There 50°. Dover abeam. North Foreland abeam. Passed Prince’s Channel Lightship. Passed Girdler Lightship. Passed Nore Lightship. Mod. NW breeze. Fine and misty. Off Gravesend. Channel pilot left, and river pilot (Twist) came on board. Mr. Gott left for shore. Off Silvertown Works. Ship preparing to make fast to “ Dacia,” inside berth. Ship all fast. All cable hands left ship. Draught { arIT^O'' 6 } Mean = 11 ' 9 " MONDAY, JANUARY 20th. Finished with all hands. Crew signed off Articles. 40 COMMERCIAL CABLE COMPANY’S CHARTER. BRISTOL CHANNEL REPAIRS, JANUARY, 1902. S.S. “BUCCANEER.” DISTRIBUTION OP WEIGHT IN SHIP ON ARRIVAL IN LONDON AFTER COMPLETION OF REPAIR. Cable in fore tank (picked-up cable) Tons. 8-539 „ ii (New) 6-872 Coal in bunkers 165-000 Fresh water in after fresh water tank 13000 Fresh water in fore cone ... ... . 2-000 Fresh water in side tanks ... — Water in ballast tanks — forward ... 75-000 if > > • • • 8-000 Boatswain’s stores forward 2-000 Carpenter’s ,, •300 Cable stores and buoys 10-000 Engine room stores ... 3-000 Water in main boilers 30-000 Steward’s stores 2-500 Extra chain cable 1-000 Spare anchors and ropes 2-000 ,, propeller 3-000 Deck machinery 10-000 Total . . . 342-211 Draught of ship | ^° re ^ q” } mean 1V °" January 20th, 1902. 43 DISTRIBUTION OF CABLE IN SHIP ON ARRIVAL IN LONDON AFTER COMPLETION u Fore Tank, Picked-up Cable —2*497= 8*539 After Tank, New Cable =2*010= G*872 EXPENDITUBE OE CABLE AND PICKED-UP PIECES. p 5 ^73 co US USJ co-^ © J 3 * . 5 ^ o f-l Ci H ' 0) H p'^ ^ P S 03 a 03 30 •- -H ft GO '-'io > c3 £ £ «4-l O a 2 * « O O ©t3 « 8 'SOTZl I 80 i[dy Y_ ,d a | <33 1^73 C3 <33 03 CO V - 1 Ci =657*5 through 1 4 = 13 5 = 12£ zero — 2 G G D.R. total=34-606=8198 per N.M. at sea temperature. Galvanometer No. 222 used for D.R. tests. “Rib” Core. Mins. Zinc. 1 = 26 S.R. 10000 m.p.=l 2 = 22 3 = 21 4 = 20 5 = 19 zero o.k. G G D.R. total=25-289=5991 per N.M. at sea temperature. Final Tests from Ship on Weston and Waterville ends before making final splice , 17/1/02. WESTON END. CORES LOOPED AT WESTON. January 17th, 7.30 a.m. Length each Core = 91-515 n.m. to C.R. (30 volts). Z. C. Leads=0 - 55. Temperature B.C.=63° F., correct at 60° F. Platinoid. 2325 2325 2325 2325 2325 2325 w to C.R. of loop corrected for temperature C.R. Plain Core, total=1163-26=12*712 w per N.M. to w B.C. and leads deducted=2325-3. C.R. Rib Core, total=1162-04=12-698 per N.M. CORES “FREE” AT WESTON. D.R. (30 volts). L.=91*515 n.m. 8.30 a.m. “ Plain” Core. Mins. Zinc. Lead=nil S.R. 10000. 1 = 5 S.R. 10000 m.p =1 2 = 4£ Const. 30 volts through 10 5 3 = 4 =190 S.R. 500 G =380 through 1 G G “Rib” Core. Mins. Zinc. Lead=nil S.R. 10000. 1 = 6 S.R. 10000 m.p.=l 2 = 5 ^ 3 = 5* G G D.R. total=76 - 0=6955 per N.M. at sea D.R. total=63*33=5796 per n.m. at sea temperature. temperature. 62 Electrical Beport. WATERVILLE END. CORES LOOPED AT WATERVILLE. January 17th, 8.50 a.m. Length each Core=239-46 n.m. to C.R. (30 volts). Z. C. Leads=0*55. Temperature B.C.=64 Q F., corrected at 60° F. Platinoid. 6022 6022 6022 6022 (O to C.R. of loop corrected for temperature C.R. “ Plain ” Core, total=3014'l=12-587 to per n.m. to to B.C. and leads deducted=6025. C.R. “Rib” Core, total=3010 , 9=12 , 574 per n.m. CORES “FREE” AT WATERVILLE. D.R. (30 volts). L.=239-46 n.m. 9.20 a.m. “ Plain ” Core. Mins. Zinc. Lead=nil S.R. 10000. 1 = 13 S.R. 10000 m.p.=l. O 2 = 11 $=380 through 1 3 = 10 “ Rib ” Core. Mins. Zinc. Lead=nil S.R. 10000. 1 = 15 S.R. 10000 m.p.= l 2 = 11 3 = 10 D.R. total=25"333=6066 per N.M. at sea temperature. O O D.R. total=29 - 23=7000 per n.m. at sea temperature. Galvanometer No. 65 used for these tests. WESTON— WATERVILLE (1885) CABLE. Bristol Channel Bepairs, January 17th, 1902. FINAL TESTS AFTER REPAIRS. Weston-super-Mare, January 17th, 1902. (C.R. not taken. for traffic.) D.R. 30 volts. “PLAIN” CORE. Cores required Z. to Core. Total. Per n.m. C. to Core. Total. Per n.m. O O O Mean of 1st min .=21-51 7106- Mean of 1st min .=25-71 8493- „ 2nd ,, =24-54 8107- u 2nd » =22-22 7340- „ 3rd „ =27-41 9054- » 3rd „ =26 86 8874- „ 4th „ =28 57 9437' ,, 4th ,, =27*34 903P n 5th „ =3016 9964- „ 5 th ,, =30-33 10210- Mean of all =2668 8815- Mean of all =26-68 8682- Cable discharged for 5 mins, between Z. and C. Test. Earth currents variable. 63 Electrical Report. “RIB” CORE. Z. to Core. Total. Per n.m. C. TO Core. Total. Per n.m. ft ft ft ft Mean of 1st min.=19’88 6569' Mean of 1st min .=22-50 7432- „ 2nd „ =22-40 7401' JJ 2nd „ =2131 7039' „ 3rd „ =24*00 7927' „ 3rd „ =2132 7044- „ 4th „ =25'59 8453- 4th „ =21-86 7221' „ 5th „ =27-34 9031- „ Otll ^ =22-88 7557" Mean of all =24 -24 8009- Mean of all =21-93 7243- Cable discharged for 5 mins, between Z. and C. Test. Earth currents variable. Waterville, January 17th, 1902. Insulation (30 volts) » 5 > 10th min. ft “Plain” Core Z. =10700' per n.m. „ „ C.= 9790' „ ft “ Rib ” Core Z.=10260' „ ,, C.= 8510' „ f “Plain ”=4190' ohms. UK * 1 “ Rib ” =4184- ohms. Electrical Report. WESTON— WATERYILLE (1885) REPAIRS. Distribution of Cable in Tanks on board S.S. “Buccaneer” on Leaving the Thames, January 11th, 1902. AFTER. FORE. 8553 Siemens’ Main=4-639 N.M. Empty. , Factory Electrical Values at 75° Fahr. of Cable on board S.S. “ Buccaneer ” on Leaving the Thames, January 11th, 1902. Type. No. of Wire. Length, N.M. C.R. at 75° Fahr. Capacity. D.R. at 75° Fahr. Cable. Core. Total p ler N.M. Total p er N.M. Total per N.M. 8553 1 2 4-639 4-690 0) 61-580 61-627 13-13 13-14 mfds. 1-5496 1-5435 0-3304 O-32'.tl i 509 6 625-8 2 2390- 2935- 65 i WESTON— WATERVILLE (1885) REPAIRS. Distribution of Cable in Tanks on Board S.S. “Buccaneer” on her Return to the Works, January 19th, 1902. AFTER. FORE. j Piece D=f 0*8450 N.M. Piece C=f P0664 Piece B=f 0*4770 8553 Siemens’ Main=* 2*028 N.M. Piece A=f 0*1092 * Electrical length determined by C.R. f Indicator lengths. Factory Electrical Values of Cable on Board S.S. “ Buccaneer ” on her Return to the Works, January 19th, 1902. Type. No. of Length, N.M. C.R. at 75° F. Capacity. D.R. at 75° F. Remaaks. Wire. Cable. Core. Total. Per N.M. Total. Per N.M. Total. Per N.M. j fm ds. 1 i 2 AFTER TANK. 1 26-916 13-13 *6773 0*3304 1166* 2390* 8553 2 2*028 2-050 26*937 13T4 *6747 0*3291 14*32 2935* FORE TANK. Plain 11*294 13*22 0*2559 0*2995 — — Top in Tank. Piece D Rib 0*8450 0-8543 11-337 13*27 0*2525 0*2956 Picked up, 17.1.02. Plain 14-253 13*22 0-3229 0*2995 - - Piece O Rib 1*0664 1-0781 14-307 13-27 0-3187 0-2956 Picked up, 16.1.02. Pliin 6*375 13*22 0T444 0*2995 — — Piece B Rib 0*4770 0-4832 6*400 13*27 0*1425 0*2956 Picked up, 15.1.02. Plain 1*4595 13*22 0*0331 0*2995 _ — Bottom in Tank. Piece A Rib 0*1092 0*1104 1-465 13*27 0-0326 0*2956 - - Picked up, 14.1.02. 66 Electrical Report. WESTON— WATERVILLE (1885) REPAIR, January 17th, 1902. Expenditure. New Cable, Siemens’ Type 8553, Twin Core. Tank. Type. Cut off for Splices. N.M. Laid in Section. N.M. Remaining on board. N.M. Total Shipped. N.M. After Siemens’ 8553 ■008 I „ •008 f 0016 2*595 2*028 (Core=2*050) 4*639 (Core=4*690) Expenditure. Cable Picked Up During Repairs. Total length = 2*5226 n.m. N.M. *Piece A. = 0*1092 * „ B. =0*4770 * „ C. = 1*0664 * „ D. = 0*8450. Cut off for damaged places and ends = 0*0250 N.M. = 2*4976 Coiled in “Buccaneer’s Fore Tank. Total = 2*5226 n.m. Note. — T hese pieces are electrically and mechanically perfect. Electrical Report. NOTE re mean bottom temperature calculated from tests taken from ship and shore. WESTON— WATERVILLE (1885) CABLE. Bristol Channel Repairs, January, 1902. January 17th, 1902. C.R. test from ship to Weston: Length in circuit = 91*515 n.m. each. 0 } Total C.R. at 75° F. (of Plain and Rib cores) = 2459-93. Total C.R. measured of Loop (corrected) =2325-2. Calculated temperature by Silvertown co-efficient = 48° F. By C.F. and T’s co-efficient = 49°-8 F. Mean=48°-9 F. January 17th, 1902. C.R. test from ship to Waterville : Length in circuit = 239-46 n.m. each core. Total C.R. at 75° F. (of Plain and Rib cores) = 6370*98. Total C.R. measured of Loop (corrected) =6025-0. Calculated temperature by Silvertown co-efficient = 48°-25 F. By C.F. and T’s co-efficient = 50°*0 F. Mean of the two = 49°T2 F. Waterville ’ s Test after Completion of Repairs. Total C.R. at 75° F. (of Plain and Rib cores) = 8830*91. Total C.R. measured of Loop = 8374- Calculated temperature by Silvertown co-efficient = 49 0, 5 F. By C.F. and T’s co-efficient 51°-1 F. Temperature at position of Final Splice, 17.1.02, taken by Deep Sea Thermometer : Surface = 51° F. Bottom =49°-2 F. 68 WESTON— WATERVILLE (1885) CABLE. cq o P p s 55 < o o p p GQ QQ p w EH >H P 02 P M PH P P P o £3 53 o? a ' * fi “ {Z5 ea I? ^ t> a P 3 “ H H w iJ £ JH □ s cd W rvi H _ <1 P O <1 II 1 IS ii 3 a © 3 55 3 305 N & N g 05 0 } gs| H 3 s ■& '&0T9I ‘'wrd 6 'SlSBJa •p3J[00q 8iqi3Q •80T9I *11 SBj a •paqooq 0[qi3O - S fl ^ £ ii h 3 - S 55 CD ^ »-H OHO U ■> •cqn'Rj pettiSuo •goTti ‘8 SBj a: •p95[00q eiq’BQ 3 Sz* .S lip „ S 3 05 OJ o O IH «® Ph II H o S3 ft a * lb C3§ 1? 'll -4-3 02 o CS W 7a £i P-H a a y §.2 (M 6 05 H £ His Di cd , o. §1 ■EH =° a •as a * £ £ s. £ cslcsg S ell .a. i TO THE Meston— Materville 1885 Cable. 19 0 1 - ’ resented by ®|e |nM;r '§ubkx, itttta | wfta ;mt> ®dep*j$ Harks Company (pmitrir). r ■ . ' A lb a v re W at erv t Ue Cable Iftepalr lEypebltlon. SEPTEMBER, 1902. S.S. “BUCCANEER.” 1 COMMERCIAL CABLE COMPANY’S CHARTER, ©awe— Watecvllle Cable IRepaic Ejpebitlon. FEBRUARY, 1902. S.S. “BUCCANEER,” IFBRARY . CF THE V. ''VERT .'TV OF ILII.'CIS I GENERAL INDEX ibavrc— Watecvtlle Cable IRepair Ejpebttion, jfebruarp, 1902. S.S. “BUCCANEBE.” PAGE GENERAL REPORT 9 List of Staff, Officers, Cable Hands and Crew 15, 16 Distribution of Weight, in Ship on Leaving Gravesend ... ... ... 19,20 Constants for Picking-up and Paying-out Drum 21 Description of Cable 22, 23 Steaming from London to Cable Ground ... ... ... ... ... 27-31 Grappling, etc 32-34 Joining up Havre and Waterville ... ... ... ... ... ... 35-37 Steaming to and at Plymouth 38, 39 Picked-up Pieces of Cable in Fore Tank after Completion of Repair 41 New Cable in After Tank after Completion of Repair ... ... ... 41 Index to Electrical Report ... ... ... ... ... ... ... 45 ELECTRICAL REPORT ... ... 47 5 2 K COMMERCIAL CABLE COMPANY. HAVRE— WATERVILLE REPAIR, FEBRUARY, 1902. S.S. “BUCCANEER.” GENERAL REPORT. 7 GENERAL REPORT. M. H. Gray, Esq., Silvertown. Silvertown, London, E., February 24 th, 1902. Dear Sir, The “Buccaneer” was ordered on January 27th to get ready for sea, news having been received that the Havre — Waterville Cable had broken down on the previous day. As there was an Engine Survey on at the time she was not able to sail before January 30th, when she left Silvertown at 4 p.m., having taken in 6*356 n.m. of Commercial Co.’s cable, sent from Messrs. Siemens. Mr. Gott, representing the Commercial Cable Co., joined the ship off the Works. The same evening we anchored in Prince’s Channel owing to heavy snow and sleet squalls. On 31st we ran down Channel with a strong NE gale, and when off the Tongue Lightship a heavy cross sea struck the ship on Port Bow, starting five intermediate frames in forecastle, but not causing damage enough to demand immediate attention. As the weather showed no signs of moderating it was decided to run into Spithead, and we anchored there at 10 p.m., landing the Channel Pilot the next morning, we being unable to land him before on account of the weather. On Monday, February 3rd, the weather having moderated, we proceeded to cable ground, 15 n.m. NW of Cherbourg, and the same evening on the 2nd Drag got the cable and spoke Havre. As tests were O.K. to Havre the end was buoyed, and 0*086 n.m. picked up 9 General Report. westward, to fault. This proved to be a break, the wires being badly corroded and showing signs of chafe. While picking up this end the- lights of our Mark Buoy suddenly disappeared, and on investigation the next morning it was found that the clamps on the lamp-hanger had been unscrewed, and that the lanyards had been cut. This was evidently the work of fishermen, who were observed in the vicinity. On Tuesday afternoon, on Drag No. 4 we got the Waterville end of cable and spoke Waterville. Tests O.K. We picked up 0-313 n.m. of cable to westward to ascertain condition of cable, which after one bad place, close to ship, was found to be in good condition. Previously to this we had picked up 0*080 n.m. to a broken end. This length was much corroded, and in places only one or two wires holding. The inner serving was covered in parts with red rust. When splicing tank section on to Waterville end the lights on the Havre end cable buoy suddenly disappeared. This necessitated our hanging on to the cable till daylight. On coming up to the buoy it was found that one Dioptric lamp had been taken off and that the other lamp — a Miller’s Globe — had been taken off but put back again and roughly lashed to the hanger. On Wednesday, February 5th, the final splice was slipped in 41 fms. and we proceeded to Plymouth to land Mr. Gott, reaching there on Thursday morning. Mr. Gott received telegram here that final tests taken from Waterville were highly satisfactory. Mr. Gott left tne ship at 9.30 a.m. on Thursday, February 6th, and pro- ceeded by train to London. As before mentioned the cable near the fault was much corroded and chafed in places, the soundings which we took indicated “ hard bottom,” probably gravel, as given on Admiralty Charts, but we could not obtain any specimen of the bottom, which would have been interesting in order to ascertain if any special cause existed for the corrosion. At Mr. Gott’s request all joints were brass taped and the yarn serving over splices was compounded. 10 General Beport. As when we spoke Waterville, on Tuesday, February 4th, we had received instructions from Mr. Gott and also “ Silvergray,” that on completion of Havre — Waterville repair we were to proceed to Brignogan to repair the French Co.’s cable off there, we took extra provisions in while at Plymouth, also splicing cable up to be in readiness for work, and would have sailed for Brignogan on Thursday evening, February 6th, but, on account of unfavourable weather reports, did not do so till the Friday morning. After completion of this repair, which is the subject of further report, we arrived in London on February 18th. Yours faithfully, F. C. CRAWFORD. 11 S.S. “BUCCANEER.” LIST OF STAFF, OFFICERS, CABLE HANDS AND CREW. 13 . S.S. “BUCCANEER.” LIST OF STAFF, OFFICERS, CABLE HANDS 6 Mr. F. C. Crawford, Engineer in Charge. ,, H. E. Cann, Electrician. ,, E. H. Walker, Accountant. ,, T. W. Sharp, ,, A. Troan, ,, Viptor Jones, ,, F. G. Ramsay, R. Murray, J. Kelly, Boatswain’s Mate. 4 Quartermasters. 7 Able Seamen. 1 Deck Boy. Mr. A. White, Master. Chief Officer. 2nd ,, 3rd Carpenter. Boatswain. Chief Engineer. ,, W. McFarlane, 2nd ,, ,, C. Ball, 3rd ,, ,, J. Ketley, 4th ,, J. Maguire, Donkeyman. 6 Firemen. 4 Trimmers. A. Patrick, Chief Steward. 2nd Steward and Storekeeper. Chief Cook and Baker. 2nd Cook and Butcher. Pantryman. 1 Assistant Steward for Saloon. 1 Engineers' Steward. 1 Officers’ Boy. 1 Scullion. CREW. 15 S.S. “ BUCCANEER.” CABLE HANDS. D. Smith, R Keys, A. Day, James Ayers, Thomas Ayers, George Ayers, William Ayers, M. Coleman, C. Brown, A. E. Newton, R. Welsh, Foreman. Leading Hand. Cable Hand. y y n 99 99 9 9 9 9 Fitter. Fitter’s Mate. Jointer. Staff Cable Hands Officers and Crew 3 11 43 57 Mr. J. Gott, Commercial Cable Company’s Representative. \ 16 S.S. “BUCCANEER DISTRIBUTION OF WEIGHT IN SHIP ON LEAVING GRAVESEND. 17 S.S. “ BUCCANEER.” DISTRIBUTION OF WEIGHT IN SHIP ON LEAVING GRAVESEND. Tons. Cable in fore tank ... 8-539 ,, after ,, 39-87 Coal in bunkers 230-00 Fresh water in after fresh water tank 13-00 „ „ „ cones 8-00 ,, ,, ,, side tanks 4-50 Water in ballast tanks forward 70-00 ,, ,, ,, ,, aft 15-00 Boatswain’s stores forward . . . 2-00 Carpenter’s ,, ,, •50 Cable stores and buoys 11-00 Engine room stores 3-00 Water in main boilers ... 30-00 Steward’s stores 5-00 Extra chain cable 1-00 Spare anchors’ ropes 2-00 ,, propeller 3-00 Deck machinery 10-00 Total 456-409 Draught of ship j J mean 13' 2". 19 I. TABLE SHOWING DISTRIBUTION OE CABLE IN SHIP ON LEAVING GRAVESEND. I xh f 5 O b* 'A PS ◄ a p cc 20 Fore Tank Picked-up Cable = 2*497 — 8*539 After Tank, New Cable ... ... = 8*366=39*872 COMMERCIAL CABLE COMPANY’S CHARTER. / HAVRE — WATERVILLE REPAIR, 1902. S.S. “BUCCANEER.” CONSTANTS FOR PICKING-UP AND PAYING-OUT DRUM. Circ. of Drum = 17' 2}" Type. Circ. in inches. Revs. per N.M. Log. Fms. per Rev. Siemens’ H.I. (new) ... 8514 4-375 346-385 2-5395594 2-929 ., L.1 8513 3-650 347-580 2*5410551 2-919 „ L.I. (twin core) 8553 3-465 347-886 2-5414375 2-916 „ H.I. (old) ... 8514 4-250 346-590 2-5398169 2-927 Grappling Rope — 4x6 (old) 4-646 345-940 2-5390016 2-932 Buoy Rope — (Steel and Manilla) 4x4 (new) 3-860 347-233 2-5406213 2-922 3x3 (new) 2-700 349-159 2-5430228 2-905 i i 2 21 S.S. “BUCCANEER.’ DESCRIPTION OF CABLE. Siemens’ L.I. Cable— Their Factory No. 8553. TWIN CORE CABLE. Conductor : — Solid plain copper wire, weighing 90 lbs. per n.m. Dielectric : — Gutta percha, weighing 85 lbs. per n.m. Two cores as above — one marked with “ Rib ” the other plain — laid up, wormed and served with tanned jute yarn. Sheathing : — 15 G homo wires, No. 9 L.S.G.="T44 dia. when galvanised. Outer Serving : — Two coats jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = 1"-103. Weight in air, dry = 3-293 tons per n.m. „ „ wet = 3-420 „ ,, in sea water = 2-241 ,, ,, Siemens’ L.I. Cable.— Their Factory No. 8513. Conductor: — Strand of 7 copper wires. "-023, weighing 70 lbs. per n.m. Dielectric : — Gutta percha to "*205, weighing 75 lbs. per n.m. Serving : — Tanned jute yarn. Sheathing : — 10 B.B.G.I. wires = "*180 dia. when galvanised. Outer Serving : — Two coats jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = 1"T60. Weight in air, dry = S.S. “BUCCANEER” Siemens’ H.I. Cable —Their Factory No. 8514. Core and Serving same as in No. 8513. Sheathing: — 10 B.B.G.I. wires ="’238 dia. when galvanised. Outer Serving : — Two coats jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = 1"*393. Weight in air, dry = 5*437 tons per n.m. ,, ,, wet = 5*526 ,, ,, ,, in sea water = 3*873 ,, ,, Note. — All the above particulars taken from samples. 23 HAVRE— WATERVILLE REPAIR, 1902. S.S. “BUCCANEER.” ENGINEER’S GENERAL DIARY. 25 STEAMING DOWN CHANNEL. HOUE, A.M. 8.0 9.0 10.0 P.M. 1.50 4.0 6.40 7.35 8.45 9.50 10.30 MID. A.M. 4.0 ! S.S. “ BUCCANEER.’ THURSDAY, JANUARY 30th (1st DAY OUT). Hands joined ship off Silvertown. Commenced unmooring ship. Finished unmooring ship and made fast with ropes. Commenced taking in 6*356 n.m. of cable, H.I. 8514, barged from Messrs. Siemens’, and coiling it into after tank. Mr. Gott (C. C. Co.’s representative) joined ship. All cable and stores on board. Let go moorings and proceeded down river, Pilot Twist in charge. Off Gravesend Pilot Twist left, and Pilot Letten boarded and set on for Cherbourg. Mucking Light abeam. Nore Light abeam. Girdler Light Vessel abeam. Let go anchor in Princes Channel in 13 fms. and veered to 60 fms. Mod. SE gale, with heavy squalls and sleet. Bar. 30*52. Ther. 46°. Draught leaving Gravesend j ^ re * g„jMean 13' 2" STEAMING TOWARDS CHERBOURG. FRIDAY, JANUARY 31st (2nd DAY OUT). At anchor. Mod. NE gale, with heavy squalls of sleet. Bar. 30*60. Ther. 40°. 27 HOUR. A.M. 8.0 9.5 10.0 11.0 NOON. P.M. 1.35 3.50 4.0 4.35 6.0 7.30 8.0 9.40 MID. A.M. 4.0 Anchored in Spithead Harbour . S.S. “BUCCANEER.” FRIDAY, JANUARY 31st (2nd DAY OUT) — Contd. Wind increasing to fresh gale. Weighed anchor and proceeded towards Cherbourg. Bar. 30-60. Ther. 42°. Passed Tongue Lightship. On passing Tongue lightship a heavy sea struck ship on Port bow, starting five intermediate frames in Port forecastle. Gull Lightship abeam. Passing Dover signalled for boat to take off pilot. Stood in close to pier, but could not get any reply, the wind blowing a fresh north-easterly gale and a high sea running. Observed Channel boats unable to go alongside pier. Stood on for Dungeness. Bar. 30-50. Ther. 42°. Passed Dungeness. Royal Sovereign Lightship abeam. Strong NE gale. Overcast and squally. Bar. 30-50. Ther. 41°. Decided to go to Spithead and await finer weather. Beachy Head Lighthouse abeam. Strong ENE gale. Overcast and squally. Bar. 30-50. Ther. 40°. Passed Owers Light vessel. Similar wind and weather. Bar. 30-50. Ther. 40°. Brought up in 9 fms. with starboard anchor, and veered to 60 fms. Strong ENE gale, and clear weather. Bar. 30-50. Ther. 39°. ANCHORED IN SPITHEAD HARBOUR. SATURDAY, FEBRUARY 1st (3rd DAY OUT). Strong NE gale and clear weather and rough sea. Bar. 30-50. Ther. 54°. 28 HOUR. A.M. 8.0 8.30 8.45 NOON. P.M. 4.0 7.45 8.0 MID. A.M. 4.0 8.0 10.30 NOON. P.M. 4.0 Anchored in Spithead Harbour. S.S. “BUCCANEER” SATURDAY, FEBRUARY 1st (3rd DAY OUT) — Contd. Similar wind and weather. Bar. 30-50. Ther. 54°. Hailed a fishing boat, and got her to send boat to take Pilot Letten ashore. Boat came along side and Pilot Letten left ship. Telegram sent by pilot to — “ ‘ Silvergray and Gray silver, London.’ 10 p.m. Friday, anchored Spithead owing to stress of weather. All well. Crawford.” Strong NE gale and clear weather. Bar. 30-40. Ther. 53°. Strong NE by E gale, with heavy squalls. Clear weather. Bar. 30-28. Ther. 48°. Veered away to 75 fms. of chain. Strong NE by E gale. Heavy squalls. Clear weather. Bar. 30-20. Ther. 51°. Similar wind and weather. Bar. 30-15. Ther. 52°. SUNDAY, FEBRUARY 2nd (4th DAY OUT). Mod. NE gale and clear weather. Bar. 30-08. Ther. 50°. Strong NE gale and overcast. Light snow squalls. Bar. 30-06. Ther. 50°. Tug “ Empress ” came alongside and took telegrams ashore. Telegram sent to : “ ‘ Silvergray, London.’ Spithead, Sunday, still weather bound. All well. Crawford.” Fresh ENE gale and overcast with fine snow. Bar. 30-09. Ther. 51°. Strong ENE breeze and overcast. Fine sleet. Bar. 30-01. Ther. 51°. Fresh ENE breeze. Drizzling rain and misty. Bar. 30-00. Ther. 50°. 29 8.0 Steaming to Cable Ground. S.S. “ BUCCANEER.” HOUIi. MID. A.M. 4.0 7.0 - 8.0 8.5 NOON. P.M. 0.10 0.50 1.20 1.30 1.40 2.40 3.0 4.0 4.45 4.47 SUNDAY, FEBRUARY 2nd (4th DAY OUT) — Contd. Fresh NE breeze. Overcast with occasional snow and sleet. Bar. 30-00. Ther. 55°. STEAMING TO CABLE GROUND. MONDAY, FEBRUARY 3rd (5th DAY OUT). Mod. ENE breeze and overcast. Mod. sea. Bar. 30 00. Ther. 47°. Weighed anchor, and set on for position of fault off Cher- bourg. From Nab Lightship S., 32° E. (true), 52 n.m. Similar wind and weather, and hazy. Passed Nab Lightship. Mod. NE breeze and overcast, and hazy. Bar. 29-80. Ther. 53°. Sounded in 31 fms. (Thomson’s Tube) Hard. 42 >> }) >> n >> >> „ 36 „ „ „ Rocky. In position. Decided to make land to check position. Sounded in 26 fms. (Thomson’s Tube) Rocky. n ) ) 21 ,, ,y t } Off Cherbourg. Ran 15 n.m. N, 18° W (true). Mod. NE breeze and overcast. Bar. 30-00. Ther. 49°. Sounded in 41 fathoms (Thomson’s Tube) Hard. In position to put down mark buoy “ P ” No. 42. Paid out buoy’s moorings and streamed buoy. Buoy's Moorings. 2 dioptric lamps. -f" Bridle, 20 fms.; f" and 30 fms.; chain; room 7 cwt. Position of buoy “ P „ [Lat. (Long. 49° 57'-6 N. 1° 39'-9 W. 30 Mush- HOUR. P.M. 4.52 5.0 6.35 6.40 7.0 7.30 8.0 8.15 8.20 8.25 8.45 8.50 8.55 8.57 9.7 9.12 9.45 9.45 10.0 Steaming to Cable Ground . S.S. “ BUCCANEER,” MONDAY, FEBRUARY 3rd (5th DAY OUT) — Contd. Lowered cutter, and sent her to put lamps on buoy. Cutter returned to ship and was hoisted. In position to grapple, lowered ordinary wooden protected grapnel, with 10 fms. chain, and commenced paying out 4x6 rope. Drag No. 1. Paid out to 100 fms. of rope and chain. No strain. >> >> ,, ,, Mod. NE wind and overcast. Bar. 30-00. Ther. 49°. No strain. Commenced picking up grapnel. Grapnel at bows. No sign of cable. Set on for new position to grapple. In position, lowered same grapnel and chain, and com- menced paying out 4x6 rope. Drag No. 2. Paid out 100 fms. of rope and chain. Strain steadily rose to 25 cwt. ,, steady at 25-30 cwt. Commenced picking up grapnel. 50 fms. of rope and chain out. Strain = 30 cwt. Grapnel at bows with cable H.I., No. 8514, 10 No. 3’s. Got drum ropes along, and made fast to each side of cable. Cut cable and hove grapnel inboard, took grappling chain off dr uni. Suddenly lost sight of lights on mark buoy. Took starboard drum rope (Havre end) to drum, and commenced heaving in on same. 31 HOUE. P.M. 10.5 10.15 10.30 10.45 MID. A.M. 0.20 0.27 0.55 1.0 1.15 1.20 Grappling for Waterville End. S.S “BUCCANEER.” MONDAY, FEBRUARY 3rd (5th DAY OUT) — Contd. End of cable on board, opened out end, and commenced testing. Got Havre O.K. Preparing to buoy Havre end, and pick up short piece towards fault. Finished testing. Tests to Havre O.K. Sealed end, and bent mooring chain on to end of cable. Paid out buoy’s moorings and streamed buoy “ S ” No. 43. Buoy's Moorings. 2 globe lamps. ■£" Bridle, 20 fms.; and 30 fms.; -£q” chain; Mush- room 4 cwt. 1 qr. 16 lbs. This buoy drifted aft, close alongside, and on rising to a swell the flagstaff went through the cable cutter which was swung out. Fresh NE breeze. Overcast and misty. Bar. 30-04. Ther. 53°. Position of buoy “ S ” fLat. 49° 57 f, 3 N. (Lon. 1°4P-4W. GRAPPLING FOR WATERVILLE END. TUESDAY, FEBRUARY 4th (6th DAY OUT). Commenced picking up short piece towards fault. End on board and opened out. Commenced testing. Finished testing. Waterville end faulty. Break reported close to ship. End of cable off drum. Set Ind. Zero. Ind. 22 revs. Broken wire passed inboard. Last end on board. Cut 4 fms. off. End off drum. Ind. 28 revs. = *082 n.m. picked up. Piece “E” Set on to dodge off buoys till daylight. Fresh NE breeze and overcast. Bar. 30-05. Ther. 50°. 32 4.0 Grappling for Waterville End. S.S. “BUCCANEER.” HOUR. A.M. 8.0 9.40 9.50 10.0 10.15 10.25 10.55 11.25 11.30 11.45 NOON. P.M. 0.20 0.25 1.7 TUESDAY, FEBRUARY 4th (6th DAY OUT) — Gontd. Similar wind and weather. Bar. 30*05. Ther. 50°. In sight of Mark Buoy “ P.” Observed that both lamps were gone. Up to buoy. Lowered cutter and sent her away with drum rope to dismantle it. Found that lamphangers had been unscrewed and lanyards cut. Knocked up tumbler and commenced heaving up buoy’s moorings. All moorings on board. Set on to put fresh lamps on cable buoy “ S.” Up to cable buoy “ S.” Lowered cutter and sent her away to put lamps on buoy. 1 Dioptric and 1 Miller’s Globe. Cutter returned to ship and was hoisted. In position to grapple. Lowered ordinary wooden pro- tected grapnel with 10 fms. ■§-" chain, and commenced paying out 4x6 rope. Drag No. 3. Paid out 100 fms. of rope and chain. No strain. ,, Fresh NE breeze. Overcast. Bar. 30-05. Ther. 57°. ^ ... i tv f Lat. 49° 45'-18 N. Position by D.E. | Lon ^ 4Q ,. 0 w> No strain. Commenced picking up grapnel. Grapnel at bows. No sign of cable. Set on for new position. In position. Lowered same grapnel, and commenced paying out 4x6 rope. Drag No. 4. Paid out to 100 fms. of rope and chain. 33 1.12 Grappling for Waterville End. S.S. “ BUCCANEER.” HOUR. P.M. 1.30 2.0 2.11 2.20 2.25 2.55 3.0 3.15 3.20 3.28 3.35 3.40 4.0 4.15 5.8 TUESDAY, FEBRUARY 4th (6th DAY OUT) — Contd. No strain. Strain rose to 25 cwt. steadily. Commenced picking up grapnel. 50 fms. of rope and chain out. Strain = 22 cwt. Grapnel at bows with cable H.I., No. 8514, 10 No. 3’s. Got drum ropes along and secured to each side of cable. Hove grapnel inboard. Took grappling chain off drum. Cut cable. Took Port drum rope to drum and commenced heaving in on it. End off drum. Set Ind. 0. Commenced testing. Finished testing. Found this to be a short faulty piece. Resumed picking up. Last end inboard. Cut 4 fms. off (badly damaged). End off drum. Ind. =26 revs. = # 076 n.m., Piece “ F.” The whole of this piece was greatly corroded and in places holding together by one wire. Commenced heaving in on Starboard drum rope. End on drum. Set Ind. zero. End abaft drum. Commenced testing. Got Waterville O.K. Moderate NE breeze. Overcast and misty. Bar. 30-02. Ther. 50°. Finished testing. Waterville O.K. Resumed picking up to ascertain the condition of cable. Silvergray ’ to Crawford. <£ Commercial Cable Coy. have agreed to allow ‘Bucca- neer ’ to repair French cable off Brest after completion Havre — Waterville repairs. You will have to land Mr. Gott at nearest convenient port, and receive telegraphic confirmation from there of the Havre- Waterville cable being in good working order. When you have this message from .Havre or Waterville you can proceed to Brignogan, near Brest. There report your arrival to the Superintendent of the French Company. He will have 34 Joining Up Havre and Water villa. S.S. “BUCCANEER.” HOUR. P.M. 5.10 5.40 6.10 7.0 8.0 9.0 9.35 10.0 11.0 11.15 MID. TUESDAY, FEBRUARY 4th (6th DAY OUT) — Contd. charts and instructions from his principals. The Com- mercial Company agree that any cable remaining over after the Havre — Waterville repair may be used by the French Company.” Ind. = 50 revs. = -145 n.m. Cut cable at bad place (Piece “ 6r”) and resumed picking up. Reset indicator. Cable coiling badty. Ind. = 63 revs. = T83 n.m. Stopped picking up, cable in good condition. Commenced testing to Waterville again. Finished testing. Tests O.K. to Waterville. Got end of H.I., No. 8514, from after-tank and commenced opening out same for splice. Finished opening out after-tank end for splice. Mod. NE breeze. Overcast and misty. Bar. 30-02. Ther. 50°. JOINING UP HAVRE AND WATERVILLE. Cut Waterville end 15 fms. abaft drum (thus reducing Piece “H ” to ’168 n.m.) and commenced opening out for splice. Waterville end to make splice with new cable in after- tank. Commenced joint. Cut 8 fms. off tank end. A yawl was seen hovering about the buoy on Havre end. He was seen to put out his lights. A few minutes after the buoy lights disappeared. Finished joint. (All bare core and joint brass taped.) Commenced splice. Copy of telegram sent : “ Gott to S.H.R. Oh Monday night and again last night (Tuesday) w T e had the lighted lamps stolen from our buoys, by some fishermen we suppose. Three of these lamps are Ridsdale’s copper dioptric buoy lamps, and one Miller’s globe lamp. The names are on the lamps — Ridsdale, Minories, London. Our operations have been seriously delayed by these acts of brigand- age, and danger to navigation results from them. A 35 m HOUR. A.M. 1.20 4.0 7.50 8.0 8.5 8.6 8.11 8.15 8.18 8.22 Joining Up Havre and Waterville. S.S. “BUCCANEER.” TUESDAY, FEBRUARY 4th (6th DAY OUT) — Gontd. yawl was seen hovering about the buoy on Monday. Last night the lamps were stolen at ten o’clock. The fellow put out his own light to mystify us. The buoys were moored eighteen miles off Cherbourg, and seventeen from La Hogue. Can you bring this before the authorb ties in this vicinity ? ” WEDNESDAY, FEBRUARY 5th (7th DAY OUT). Finished splice. Stopped work for night on account of lamp being stolen off cable buoy on Havre end, and not being able to see buoy. Mod. SE breeze. Overcast. Bar. 30-00. Ther. 46°. i Copy of telegram to : “ ‘ Silvergray, London.’ Your message re French Com- pany’s repair understood. Now about to pay out to buoy on Havre end, and after splice proceed to Plymouth to get results and land Mr. Gott. We need four buoy lamps, having had ours stolen off buoys. Please ask Works to send these to Plymouth, also new cable reglulation lamps ordered before leaving. Will wire, cable remaining later. All well. Crawford.” Fresh SE breeze. Overcast. Bar. 29-97. Ther. 46°. Commenced paying out H.I. cable, No. 8514, towards buoy on Havre end. Course S 60° E true. First end of splice on drum. Ind. Zero. Ind. =86*75 revs. =0*250 n.m. = 20 revs. Strain = 18 cwt. Engine Ind. = 173-50 revs. = 0-500 = 20 revs. N.M. Strain = 18 cwt. Engine Ind. = 260-25 revs.=0'750 = 20 revs. N.M. Strain = 18 cwt. Engine Ind. = 347-00 revs. = 1-000 = 20 revs. N.M. Strain = 18 cwt. Engine 36 Joining Up Havre and Waterville. S.S. “BUCCANEER.” HOUE. A.M. 8.26 8.31 8.35 8.40 8.45 8.48 9.3 9.10 9.15 9.48 10.25 11.24 11.45 WEDNESDAY, FEBRUARY 5th (7th DAY OUT )—Contd. Ind. = 433*75 revs. = 1*250 n.m. Strain = 18 cwt. Engine = 20 revs. Ind. = 520*50 revs. = 1*500 n*m. Strain = 18 cwt. Engine = 20 revs. Ind. = 607*25 revs. = 1*750 n.m. Strain = 18 cwt. Engiee = 20 revs. Ind. = 694*00 revs. = 2*000 n.m. Strain = 18 cwt. Engine = 20 revs. Approaching buoy on Havre end. Observed that the buoy lamp had been stolen, and the Miller’s Globe had been unhooked from hanger. Up to buoy, lowered boat, and sent her away with drum rope to dismantle buoy. Ind. = 761 revs. = 2*195 n.m. paid out. Took cable off drum, and took drum rope to. Knocked up tumbler, and commenced heaving up buoy’s moorings. Hoisted buoy and boat. Boat’s crew reported that Miller’s Globe had been unhooked and lashed on to flag- staff, so that in swinging the lamp had broken up. All Havre buoy’s moorings on board. Picked up enough on Havre end for splice. Gut 8 f ms. off at kink. Put hanging ropes and stoppers on both cables, opened out Havre end for splice, and commenced testing. Telegram sent to : “ Silvergray, London. About to make final splice and proceed to Plymouth. Cable remaining on board, about four knots Havre — Waterville, two knots new twin core, and two and half knots picked up twin core. All belonging to Commercial Co. Crawford.” Finished testing. Havre and Waterville O.K. Cut 7 fins, off Havre end , and cut tank (Waterville) end. Total length laid in =2*153 n.m. Expended for splice = *008 ,, Total length expanded = 2*161 ,, Remaining in after tank = 6*205 n.m. 37 m2 HOUK. NOON. P.M. 0.30 2.10 2.15 3.20 3.30 3.35 3.40 4.0 8.0 MID. A.M. 0.5 3.15 3.20 3.40 3.55 Anchored in Plymouth Harbour. S.S. “BUCCANEER.” WEDNESDAY, FEBRUARY 5th (7th DAY OUT )—Contd. Fresh SE breeze. Overcast. Bar. 29-90. Ther. 50°. Commenced joint between Havre — Waterville ends. Cut 8 f ms. off Havre end. Finished joint between Havre — Waterville ends (brass taped). Commencedsplice between Havre — Waterville ends (brass taped). Finished splice between Havre — Waterville ends (brass taped). Took stoppers off cable and veered away on hanging ropes. Bent slip stopper on to bight of cable and cut hanging ropes. Lot go final splice. Set on full ahead for Plymouth. -p. ... , n i r (Lat. 49° 57'-3 N. Position of final splice | Lon 40 4^.3 yy Fresh easterly breeze. Overcast. Bar. 29 ; 79. Ther. 56°. Fresh easterly breeze and overcast. Bar. 29-76. Ther. 50°. Similar wind and weather. Bar. 29-67. Ther. 60°. ANC BORED IN PLYMOUTH HARBOUR. THURSDAY, FEBRUARY 6th (8th DAY OUT). Start Light abeam. Distant, 5 miles. Stopped and took Pilot H. Glenn on board. Full ahead. Passed Plymouth Breakwater. Let go anchor in Plymouth harbour. 38 Anchored in Plymouth Ilarbouf. S.S. “BUCCANEER” HOUR. A.M. 8.0 9.25 10.5 10.10 THURSDAY, FEBRUARY 6th (8th DAY OUT) — Contd. Mod. ENE breeze and overcast. Bar. 29-50. Ther. 48°. Mr. Cook came alongside in shore boat with three Cable Regulations and two Dioptric Lamps. Messrs. Fox’s launch “ Rescue” came alongside. Messrs. Gott, Crawford, Cook, and Chief Steward went ashore in Agent’s launch. 39 PICKED-UP PIECES OF CABLE IN FORE TANK AFTER COMPLETION OF HAVRE— WATERVILLE REPAIR. Piece. Type. Fac. No. Length. Remarks. Top. IT. H.l. 85.14 N.M. 0-168 February, 1902, Repairs. G. 55 55 0*145 55 F. 55 55 0-076 55 E. » „ 0-082 55 D. L.l. 8553 0-845 January, 1902, Repairs. C. 55 55 1-066 ' B. 55 5? 0-477 55 Bottom. A. r 0-109 55 Total 2-968 NEW CABLE IN AFTER TANK AFTER COMPLETION OF HAVRE— WATERVILLE REPAIR. Type. Siemens- Factory No. Length. N.M. Weight. Tons. H.l. 8514 1-195* i = 21-82 , H . i) 3-000 J L.l. 8553 2-010 = 6.87 Total = 6-205 H 28-69 * 0-220 (?) N.M. is L.I. 41 ' ■ COMMERCIAL CABLE COMPANY. HAVRE— WATERVILLE REPAIR, 1902. S.S. “BUCCANEER.” ELECTRICAL REPORT. 43 INDEX. PAGE Havre — Waterville Repair ... ... ... ... ... ... ... 47 Factory Electrical Values at 75° Fahr. after Repair, Feb. 5th, 1902 ... 61 Types and Lengths of Cable Sections after Repair, Feb. 5th, 1902 ... 62 Tests from Ship towards Havre, on recovering Havre End, Feb. 3rd, 1902 63 Tests from Ship towards Waterville, on recovering Waterville End, Feb. 4th, 1902 63 Tests from Ship on Waterville End, after splicing on 3'348 N.M. in After Tank, Feb. 5th, 1902 ... 64 Tests from Ship on Havre End, before making Final Splice, Feb. 5th, 1902 65 Tests from Ship on Waterville End, before making Final Splice, Feb. 5th, 1902 66 Distribution of Cable in Tanks on Board S.S. “ Buccaneer ” on leaving the Thames, Jan. 30th, 1902 67 Factory Electrical Values of Cable on board S.S. “ Buccaneer ” on leaving the Thames, Jan. 30th, 1902 68 Distribution of Cable in Tanks on board S.S. “Buccaneer” after com- pletion of Repair, Feb. 5th, 1902 69 Factory Electrical Values of Cable on board S.S. “ Buccaneer ” after completion of Repair, Feb. 5th, 1902 70 Expenditure Tables (New Cable and Old Cable) 71 Diagram of Repair by S.S. “Buccaneer,” Feb. 1902 72 45 COMMERCIAL CABLE COMPANY. HAVRE— VVATEIIVILLE REPAIR, 1902. ELECTRICAL REPORT. F. C. Crawford, Esq., Engineer in Charge, S.S. “Buccaneer.” February 18 th, 1902. Dear Sir, On Sunday the 26th ult. communication was suddenly interrupted on the Commercial Cable Company’s Havre — Waterville Section, and the following day, 27th, orders were received at Silver- town that the “Buccaneer” was to be got ready for sea at the earliest possible date, having been chartered to effect the repair. From information received through the Commercial Cable Company, the break in the cable was 16 miles off Cap de la Hague, approxi- mately 15 miles from Cherbourg on a line to the Needles. At 5.30 p.m. on the 29th ult. a barge containing 6-356 n.m. of cable, Type 8511, was received alongside “ Buccaneer ” from Messrs. Siemens Bros.’ Works, Charlton. This was in two pieces, respec- tively 3-356 and 3-000 n.m. The shipment of this cable into the after tank “ Buccaneer ” was finished on the following day at 3 p.m., 30th. iVccording to a memo, received by Mr. Gott from Mr. F. Jacob, Electrician in Chief to Messrs. Siemens Bros., the longer piece (3-356 n.m.) was made up of a number of short pieces returned from S.S. “ Chiltern ” and S.S. “Amber,” the shorter length being new. Mr. J. Gott, Electrician in Chief to the Commercial Cable Company, joined the ship at Silvertown (1.50 p.m.), and at 4 p.m., 47 Electrical Beport. 30th nit., the “ Buccaneer ” let go her moorings and proceeded down river, and at 6.40 p.m. discharged Biver Pilot off Gravesend and proceeded in charge of Channel Pilot, Mr. Letten. Owing to the prevalence of a SE gale, with heavy squalls of sleet and thick weather, we anchored in Prince’s Channel at 10.30 the same evening, getting under way again at 8 a.m. the following morning, 31st ult., the wind during the night having increased to a fresh gale. Passed Dov^r at noon and signalled for boat to take Pilot ashore, but no communication was possible, a fresh NE gale blowing with high sea. By 4 p.m. the wind had increased to a strong gale (NE) and it was then decided to run for Spithead in order to land Pilot and await finer weather for cable operations. We anchored off Spithead at 9.40 p.m. same night, a strong ENE gale blowing. The following morning, February 1st, a strong NE gale prevailed with rough sea, and the Pilot had great difficulty in getting a boat to land him. However, at 8.45 a.m., a passing fishing smack was hailed and the Pilot obtained a passage in her to Portsmouth, taking with him the following message for transmission to London : “ Silvergray and Graysilver, London. “ 10 p.m., Friday. Anchored Spithead owing to stress of weather. All well. Crawford.” During the whole of the day a strong NE by E gale prevailed and the following day, 2nd inst., it was still blowing a strong gale. Opportunity was taken whilst lying at anchor, Spithead, to test the cable received from Siemens Bros, on the 29th ult. for C.R., I.C. and D.R., and satisfactory results were obtained. The signalling con- densers were overhauled and standardized and batteries compared. The following data, re Havre — Waterville Section, &c., was handed to me by Mr. J. Gott : 0 > The C.B. from B16ville to break = 1188* at sea temperature 47° F. Last C.R. of cable complete from office to office (19.1.02) = 8411- From Waterville to Bleville = 8303* 48 Electrical Beport. C. E. of underground lines looped between Bleville and Havre = 108* Length of underground line at Havre = 3*217 n.m. ft D. E. per n.m. at sea temperature (winter) between 5000 and 6000. To “ Mirror’s” Western splice from Bleville = 70*595 n.m. C.E. at 75° F. = 1174*36 Capacity = 22*078 mfds. Estimated distance to fault = 5*5 n.m. to westward of this splice. At 7 a.m., 3rd inst., the weather moderating, we weighed anchor and proceeded towards position of fault off Cherbourg, and at 2.45 p.m. stopped engines and took bearings off that Port, putting on again at 2.50 p.m. for position of break. Being in position at 4.50 p.m. streamed Mark buoy (No. 42 “P” flag) and sent boat away to place 2 Dioptric lamps on same. After boat’s return set on to take up position for grappling. Down grapnel at 6.35 p.m. for Drag 1, up grapnel at 8.25 p.m., no cable. Lowered grapnel again at 8.50 p.m. for Drag 2, and at 8.58 steady strain showing on dynamometer commenced picking up, and at 9.15 p.m. had cable to bows. Havre end of cable was handed to Testing Eoom at 10.14 p.m. ( Called Havre — using Sullivan’s Galvanometer as speaking instrument and received an immediate reply to call. The cable was put to “ Earth ” at H&vre C.H. for ship to test at 10.18 p.m.., and the following C.E. was obtained : N.M. * 75-595 Ship to Bleville. C.B. 30 volts. Length in circuit 3*217 L.L. to Havre. 78*812 Mean of Z = 1250*5 „ ,, C = 1310*75 Temperature B.C. = 55° F. Correct at 60° F. Platinoid. to Total C.E. corrected for temperature B.C. etc. = 1279. Position of “cut in” settled by Mr. Gott. 49 Electrical Report. At 10.30 p.m. (3rd inst.) Havre “ free’d ” for ten minutes whilst an insulation test was taken from ship which gave Ship to Bl6ville 75*595) n.m. D.R. 30 volts. Length in circuit L.L. to Havre 3*217] 78*812 0 u 1st min. Z. Total D.R. = 27*8 = 2192 per n.m. at sea temperature. All readings steady. (For full tests see Appendix.) Tests 'being satisfactory the following S.G’s. were sent at 10.40 p.m. “ 3rd February, 1902. Gott to G.M. and M.E. Monday 10.30 p.m. Cut in this evening O.K. to Havre, now buoy and pick up towards fault, weather promising.” “Gott to S.H.R. Your end will be sealed. Tell W.V.' to look out.” Sealed Havre end at 10.55 p.m., and at midnight buoyed same, 43 buoy, “S” flag. On February 4th, at 0*47 a.m., commenced picking up towards fault. A test had previously been taken to ascertain length in circuit to break (Cann’s method), and a report was handed to you stating that the length outboard was anything under quarter a mile. The broken end came inboard when the Indicator = 28 revs. = 0*082 n.m. (4 fins, having been cut off for damaged end) making total length of cable picked up = 0*086 n.m. This was labelled Piece “E” top and bottom. Coiled in fore tank. Character of Break : The sheathing wires along the whole length were greatly corroded, and at the actual break the wires were worn to needle points. Half inch of conductor exposed. At 1.30 a.m. work was discontinued until daylight, and at 9.50 a.m. picked up mark buoy and found that both lamps had been stolen. After renewing lamps on Havre cable buoy, we set on at 10.55 a.m. to take up position to grapple for Waterville end. Lowered grapnel at 11.25 a.m. and caught cable at the second drag 50 Electrical Report. (Drag 4). Cable to Bows at 2.18 p.m., which was handed to Testing Room at 3 p.m. This proved to be the Eastern end, and a test taken (H.E.C’s.) gave a negative result. You were immediately notified that only a very short length was in circuit between ship and break, and at 3.4 p.m. the end was given out to coil down in fore tank and pick up towards break, which came in at 3.14 p.m. Length picked up = 26 revs. =0-076 and 0-004 cut off damaged = 0-080 n.m. Length coiled down in Fore tank = 0-076 n.m. Labelled Piece “F” top and bottom. Character of Break : The whole length picked up was greatly corroded, and in places only one sheathing wire and core holding. Red coloured matter observed in places. J inch of conductor exposed. At 3.40 p.m. Waterville end of cable was on p.u. drum, and at 3.50 called Waterville, who put cable to “ Earth ” for ten minutes. Took C.R. 30 volts. Length in circt. = 433-05 N.M. approx. Mean total C.R. corrected for E.C.’s and temperature B.C.= w 7073 (see Appendix). At 4.2 p.m. Waterville “freed” end, and an Insulation test taken from ship gave highly satisfactory results. D.R. 30 volts. ft ft 1st min. Z total = 13-906 = 6022- per n.m. at sea temperature. Tests being O.K., the end was given out to prepare for picking up, Mr. Gott having decided to pick up for some little distance in order to ascertain if cable was in good condition near break. Between 4.42 and 5.8 p.m. the following S.G.’s were received from Waterville : “ S. to Gott. Immediately after repair, ship required to repair P. Q. Brest — Penzance cable. After putting you ashore and ascer- taining that our cable is O.K. she is to proceed direct to Brignogan 51 N Electrical Report. where charts and tests will await her. She may use what is necessary of the remainder of onr spare cable for purpose. Pse. acc. me.” “ S. G. to Crawford. Commercial Cable Company have agreed to allow ‘ Buccaneer ’ to repair French cable off Brest after com- pletion Havre — Waterville repairs. You will have to land Mr. Gott at nearest convenient port, and receive telegraphic confirmation from there of the Havre — Waterville cable being in good working order. When you have this message from Havre or Waterville you can proceed to Brignogan, near Brest. There report your arrival to the Superintendent of the French Company. He will have charts and instructions from his principals. The Commercial Company agree that any cable remaining over after the Havre — Waterville repair may be used by the French Company. — Silver- GRAY.” At 5.10 p.m. cut cable at bad place. Ind. = 50 revs. =0T45 n.m. (coiled in fore tank). Piece labelled G. top and bottom. Resumed picking up on Waterville side at 5.18 p.m., when the following S.G. was received : “ To Crawford. Please telegraph us the length of cable remaining on board after the Havre — Waterville repairs. — Silver- gray.’’ Between 5.40 and 5.45 p.m. sent S.G.’s to Waterville : “ Gott to G.M. and M.E. .Tuesday afternoon got Waterville end. Have cut out several breaks over a bad patch of ground. Now picking up on Wv. end to make sure of good cable, then shall splice on and pay out to Havre end a little over a mile. Weather promising.” “ Gott to M.E. Message about ‘ Buccaneer ’ repairing French cable and using our spare cable received. I shall land at Ply- mouth.” 52 Electrical Report. At 5.50 p.m. received from Waterville the results of tests taken from Havre on buoyed end (end sealed). Insulation to sealed end thirty-one megohms (31*) Capacity ,, ,, ,, twenty-five point three seven mfds. (25-37 mfds.). Note. — According to the capacity obtained from 75 sheets this test places the cut in at 81-121 n.m. from Havre Statn., and deduct- ing 3*217 n.m. — length of underground from BlAville to Havre, — and assuming the capacity per N.M. of this length to he the same as the submarine cables 79-904 n.m. from B16ville hut to buoyed end. This result is evidently much too high. At 6.10 p.m. a C.R. and D.R. test was taken on cable in after tank. Results O.K., and at 6.15 p.m. this cable was given out to prepare for splicing to Waterville end. At 9 p.m. cut cable, Waterville end, 15 fms. abaft drum. Length picked up = 0-168 n.m. Labelled “ H ” top and bottom, and coiled in fore tank. At 9.35 p.m. (4th inst.) commenced joint between cable in after tank and Waterville end, which was finished at 11 p.m., the joint and all bare core being covered with brass tape. The splice was started at 11.15 p.m. and finished at 1.20 a.m. 5th inst., the splice being compounded over the yarn. The following S.G. was sent to Waterville at 0.5 a.m., Feb. 5th : “ Gott to S.H.R., February 5th, 1902. ‘ On Monday night and again last night, Tuesday, we had the lighted lamps stolen from our buoys, by some fishermen we suppose. Three of these lamps are Ridsdale’s copper Dioptric buoy lamps and one Miller’s Globe lamp. The names are on the lamps, Ridsdale, Minories, London. Our operations have been seriously delayed by these acts of brigandage, and danger to navigation results from them. A yawl was seen hovering about the buoy on Monday. Last night the lamps were stolen at 10 o’clock ; the fellow put out his own light 53 n 2 Electrical Report. to mystify us. The buoys were moored 18 miles off Cherbourg and 17 from La Hague. Can you bring this before the authorities in this vicinity ? ’ ” At 0.9 a.m. Waterville was instructed to “ Earth ” for 15 minutes and a C.R. test was taken from ship, giving total C.R. corrected for E.C.’s (by Kempe’s formula) and also for temperature of bridge = CO 7128*4 = total resistance in circuit from “Buccaneer’s” western splice + the resistance of 3*348 n.m. spliced up in after tank. Length in circuit = 436*09 n.m. approximate (including 3*348 n.m. in after tank). Note. — The measured resistance of cable in after tank before CO CO (O making splice, Waterville end; = 54* app. therefore 7128*4 — 54* CO = 7074*4 C.R. of cable to Waterville from 11 Buccaneer's " western splice. At 0.40 a.m. (5th) cable was “ earthed ” on board for Waterville to take C.R. and at 0.53 ship received his results. CO CO CO Total C.R. = 6940* — 54* (resistance of cable in tank) = 6886* Too low— unreliable. Waterville was asked to test again, which he did, and obtained the following results : CO Total C.R. both currents = 7110* CO Deducting 54* (resistance of cable in tank spliced on to Waterville CO end) this leaves 7056* — resistance from ivestern splice to Waterville CO C.H. being 18*4 less than that obtained from ship. At 1.35 a.m. (5th), Waterville was instructed to “free” end and ship took capacity and Dielectric Resistance tests. Capacity by Kelvin's Null method. 20 cells = 30 volts [using K. and V.'s slides). Standard Condenser = 30*2977 mfds. Length in circuit = 436 n.m. approx. 54 Electrical Report. Slide Reading = 8183. Total capacity measured * 136-45 mfds. 2-154 n.m. was laid of this' piece, leaving 1-194 n.m. in tank, when cable was cut and spliced up to Havre end. Therefore, if we deduct 0-425 mfds. (the capacity of the 1-194 n.m.) from 136-45 mfds. this will give us the total capacity (measured) from final splice to Waterville = 136*025 mfds. An insulation test was then taken with 30 volts which gave the following result : ft ft 1st min. Zinc total = 13-906 = 6063- per n.m. at sea temperature. (See Appendix.) Called Waterville at 2.5 a.m. and instructed him to look out for ship’s call from 6.30 this morning and to insulate end in office until that time. Note. — Ship riding to cable all night. At 7.43 a.m. (5th) Waterville was called and the following S.G. was sent One from Crawford to Silvergray, acknowledging receipt of orders re Trench cable repairs, and at 8.5 a.m. we started paying-out cable towards Havre buoy. During the whole of the time ship was paying-out, a control test (20 cells) was kept on cable — results entirely satisfactory — and at 9.47 a.m. we had the Havre end on board. At 10 a.m. sent S.G. : “ Gott to G.M. and M.E. Wednesday 10 a.m., both ends on board, now going to make final splice. Have paid out about two and a quarter miles of ship’s cable. Delay has been caused by fishermen stealing lighted lamps from our buoys during nights which have been intensely dark. Wind now SE, fresh.” Havre end was handed to testing room at 10.15 a.m., and Havre was called and instructed to “ Earth ” seven minutes. * This includes the capacity of 3-348 n.m. of cable spliced up in after tank for paying-out to Havre buoyed end. 55 Electrical Report. C.R. test to Havre end. Length 75-595 n.m. to B16ville. 3-217 L.L. to Havre, 20 cells. 78-812 Total C.R. corrected = 1277-5. ( See Appendix.) Havre was then instructed to free for fifteen minutes (10.26 a.m.), and capacity and D.R. tests were taken from ship. Kelvin's Capacity test. Null method. 20 cells = 30 volts approx. Standard Condenser = 20*2379 mfds. {Total capacity measured = Slide Reading = 5525 j 24*987 mfds. which at 0*3125 mfds. per n.m. gives a length of 79-956 n.m. in circuit between Ship and Havre Cable Station. Length of land line between Bleville and Havre = 3-217 n.m. D.R. test from ship to Havre station before making final splice. Length (accepted) 75*595 n.m. to Bleville. 3-217 n.m. Bleville to Havre 20 cells = 30 volts approx. Total = 78-812 n.m. u o 1st min. zinc total = 33*37 = 26*30 per n.m. at sea temperature. (See Appendix.) From 10*45 to 11*5 Havre was testing for C.R., the end being “ Earthed ” on board. Havre results C.R. = 1280 (resistance from Havre C.H. to Skip). At 11-15 a.m. (5th), said G.B. to Havre, having previously in- structed him to look out for Waterville at one o’clock, and gave out end to prepare for final splice, and at 11.19 a.m., called Water- ville and sent the following S.G. : “ * Silvergray, London.’ About to make final splice and proceed to Plymouth, cable remaining on board, about four knots Havre — 56 Electrical Report. Waterville, two knots new twin core, and two and half knots picked up twin core, all belonging to Commercial Co. Crawford.” At 11.29 a.m., Waterville “Earthed” ten minutes, and ship took C.R. test. Length in circuit = 436*09 n.m. approx. C.R. 30 volts. Total C.R. corrected for E.C.’s (Kempe’s formula), and temper- ature B.C. =7111*6. (See Appendix.) Note. — This includes the resistance of 1*194 n.m. remaining in CO After Tank, which was cut off before splicing, viz., 19*2. The resistance therefore of Waterville side — before final splice = 7in*6— 19*2 = 7092*4. At 11*45 a.m., the end being “free” at Waterville a D.R. test was taken from ship which gave, viz. : D.R. 30 volts. Length in circuit = 436*09 n.m. approx, ft 12 1st min. zinc total = 13*91 = 6088 per n.m. at sea temperature. (See Appendix.) Note. — No correction has been made to reduce for the 1*194 n.m. cut off before splicing, as the D.R. is approximately the same as laid cable, and the temperature likewise. Tests being highly satisfactory, said G.B. to Waterville at 11*57 a.m., instructing him to look out for Havre at one o’clock, and gave out end to prepare for splicing. The joint was commenced at 0.30 p.m., and finished at 2.10 p.m., all bare core and joint being brass taped. The splice was finished at 3.30 p.m., and at 3.40 p.m. the final splice was slipped, thus completing the repairs to the Havre — Waterville Cable, and ship then set on full speed for Plymouth. 57 Electrical Report. Immediately after slipping final splice, a C.R. test was taken on Cable (top piece) remaining in After Tank to verify indicator length paid out, results of which test are as follows : C.R. =19-78. Leads = 0*55. Temperature B.C.=52° F, Correct at 60° F. Platinoid. 19-23. c<> C.R. corrected = 19-210 [C.R. per n.m. at tank temperature (from previous test) = 16-085] therefore 19-210 — 16-085 = 1-194 n.m. of top piece remaining in After Tank. Original length = 3-356 n.m. — 1-194 n.m. = 2-162 n.m. expended [ = 2-154 n.m. laid in Havre — Waterville Section, and 0-008 expended for splice]. We arrived and anchored in Plymouth Harbour at 4 a.m., February 6th, and at 9 a.m. Mr Gott received a telegram from Waterville giving results of tests taken on tne Havre — Waterville Cable after repairs by T.S.S. “Buccaneer.” Insulation after repairs Z abs. = 12. per n.m. = 6142. „ C „ =11-3 „ =5787. At 9.30 a.m. same day, Mr Gott took leave of ship, and left for shore to entrain for London, and the “Buccaneer” remained at Plymouth taking in provisions and awaiting finer weather until 8.40 a.m. on the 7th inst., when she sailed for Brignogan, Finisterre, France, to repair the Brignogan— Treen Section belonging to La Compagnie Fran 9 aise des Cables Telegraphiques, which repair will form the subject of a separate Report. In the Appendix will be found the following Tables, etc. : Revised Lengths and Factory Values at 75° F. of the Havre — Waterville Cable. Types and Length of Cable Sections after Repair of the — Havre Waverville Cable. Tests from Ship towards Havre and Waterville on recovering ends. 58 Electrical Report. Tests from Ship towards Havre and Waterville before making final splice. Distribution of Cable in Tanks, “Buccaneer,” and 75° F. values before repair. Distribution of Cable in tanks, “Buccaneer,” and 75° F. values after repair. Expenditure Tables of New and Picked up Cable. Diagram of Operations during repairs. I am, Dear Sir, Yours faithfully, HEBBEBT E. CANN, Electrician. 59 Electrical Report , FACTORY ELECTRICAL VALUES AT 75° FAHR. After Repair by S.S. “ Buccaneer,” February 5th, 1902. Length. N.M. O.R. Total. Capacity. Total. Remarks. Bleville. 20-632 359-2 6-376 2-892 26-89 1-012 9-228 160-7 2-861 0-407 373 0133 3411 5938 1054 12-813 223-00 3-970 0-845 7-76 0-276 1-290 21-44 0-460 9-222 1605 2-847 2-406 2209 0-787 “Mirror’s” Splice. 7449 129-67 2-302 5-000 86-94 1-546 (S.S. “Buccaneer.” 2154 37-05 0-767 j 5.2.02. 41-267 71758 12-757 3-251 30-12 1-095 13-994 245-3 4-215 1-593 16-47 0-471 4-189 38-88 1-483 3321 57-28 1-026 20-239 354-9 6-095 0445 7-67 0-138 8-545 147-4 2-649 0-260 2-38 0121 36-875 636-00 11-455 0-770 8-68 0-231 6-307 108-8 1-959 2-787 4632 0995 33835 586-8 10-515 48-889 855-36 15-783 43-633 761-44 13-327 48-788 844-6 15-16 1-258 21-77 0-391 2-409 41-7 ' 0-748 2-822 32-72 0-926 1-673 1529 0-560 13-08 22645 4-065 67-201 117717 20-347 Waterville. 25-294 43952 7-678 510-474 8718-95 158*581 Underground at Waterv ille. 0-225 3-536 0-0701 61 Electrical Beport. TYPES AND LENGTHS OF CABLE SECTIONS After Bepair by S.S. “Buccaneer,” February 5th, 1902. Type. Length of Section. N.M. Total Length. N.M. Remarks. Bleville C.H. 8512 o-iio o-iio Beach 0-050 0-160 8517 1-000 1-160 8516 6-000 7-160 5 9000 16-160 1 4-472 20-632 E.T.C. B 2-892 23-524 “Amber.” 8514 9*228 32-752 E.T.C. B 8514 0*407 3-411 33-159 36-570 j- “ Mirror,” April, ’98. 8514 12-813 49383 E.T.C. B •845 50-228 j “ Mirror.” 8514 1-290 51-518 8514 9-222 60-740 E.T.C. B 2-406 63-146 | “ Mirror,” May, ’98. 8514 7-449 70-595 8514 5-000 75-595 8514 2-154 77-749 * “Buccaneer,” 5.2.02. 8514 41-267 119-016 E.T.C. B 3-251 122-267 “Amber.” 8513 A 13-994 136-261 E.T.C. B 1-593 , 137-854 E.T.C. B 4-189 142-043 >“ Chittern.” 8513 A 3-321 145-364 J 8513 A 20-239 165-603 8513 A 0-445 166-048 8513 A 8 545 174-593 V“'Electra.” E.T.C. B 0-260 174-853 J 8513 A 36-875 211 728 8147 0-770 212-498 “ Bittern.” 8513 A 6-307 218-805 8514 8513 A 2-787 0-724 221- 592 222- 316 |“Marmion.” 8513 82-000 304-316 8512 92-421 396-737 8512 1-258 397995 8512 2-409 400-404 >“ Mirror.” E.T.C. B 2-822 403-226 E.T.C. D 1-673 404-899 ) 8512 81*525 486-424 8513 2-000 488-424 8514 4-000 492-424 8515 9000 50T424 8516 8-000 509-424 8517 l'OOO 510-424 Waterville Beach 0-050 510-474 Office. Underground 0-221 510695 62 Electrical Report. Tests from Ship toivards Havre (on recovering Havre End , 3 / 2 / 02 ). T micrfh in mivniif f to Bleville =75*595 N.M. I _ 7 o. ai9 „ ,, Length in cncuit ^ B16viUe to Ha vre= 8*217 „ ) ~ 78 812 N * M * (Cable to Earth at Havre C.H.) Conductor Resistance 18 cells. Zinc. Carbon. 1000:1000. 1249 1314 1247 1315 1250 1308 Temperature B.C.=55° F. Correct at 60° F. ( Platinoid). 1256 1306 4)5002 5243 * 1250*5 1310*75 Total C.R. corrected=1279. D.R. Test on Havre End (30 volts), Mins. Zinc. Lead=nil S.R. 10000. 1 = 21 S.R. 10000 m.p.=l. 2 = 23 3 = 22 1 = 22 5 = 21 End Free at Havre C.H. ft Total D.R.=27*8. ft Per n.m.=2192 at sea temperature. ft Constant 20 cells through 10 s =267 S.R.=400=667*5 through 1. Tests from Ship towards Waterville (on recovering Waterville End , 4 / 2 / 02 ). (Cable to Earth at Waterville Station). Conductor Resistance 18 cells. 1000:1000. Length=!33 n.m. approximate. Zinc. Carbon. 7301 6862 Temperature B.C.=50° F. Correct at 60° F. (Platinoid). 7338 6860 7314 ' 6874- 7306 6850 Mean total C.R. corrected for E. C.’s (by Kempe’s formula) and also for 0 } temperature B.C.=7073’ D.R. Test on Waterville End. End Free at Waterville C.H. (30 volts). Mins. Zinc. Lead=nil S.R. 10000. 1 = 48 S.R.=10000 m.p.— 1 (mean). ft D.R. Total=13*906. ft D.R. per n.m.= 6022 at sea temperature. ft Constant 30 volts through 10 s =267 S.R. 400=667*5 through 1. 63 2 = 40 3 = 39 4 = 35 5 = 35 Electrical Report. Tests from Ship on Waterville End ( after splicing on 3*348 n.m. in After Tank , 5 / 2 / 02 ). 0.12 a.m. (Cable Earthed at Waterville). Conductor Resistance 20 cells. 10000 : 10000. Zinc. Carbon. Length in circuit=436*09 N.M. approximate. 7289 6989 7249 7190 7189 7019 Temperature Bridge Coils=53° F. Correct at 60° F. ,7205 7059 (Platinoid). 7110 7120 7090 7140 7100 7090 7144 7145 Mean C.R. corrected for E. C.’s (by Kempe’s formula) and 7150 7010 for temperature B.C.=7128*4. 7240 7150 co 10 Note.— T he C.R. of cable spliced up in After Tank=54*, therefore 7128*4- CO CO 54-=7074*4=total resistance in circuit up to “Buccaneer’s” Western Splice. * D.R. Test on Waterville End. 1.59 A.M. (30 volts.) Mins. Zinc. Lead=nil S.R. 10000. 1 = 48 S.R. 10000 m.p.=l. 2 = 40 3 = 35 4 = 32 5 = 31 Cable Free at Waterville Station. 12 D.R. total=13*906. 12 D.R. per n.m.= 6063 at sea temperature. 12 Constant 30 volts through 10 5 =267 S.R.=400=667*5 through 1. * Capacity Test on Waterville End. Cable Free at Waterville Station. Kelvin's “Null” Method (using K. & V.’s Slides). 1.35 a.m. (30 volts.) Standard Condensei— 30*2977 mfds. (K) S.R. Slide Reading =8183* *= 10000- S.R. Total Capacity= 136*45 mfds. Note. — The total capacity of the 3*318 n.m. spliced up in After Tank=l*3 mfds., therefore 136*45— 1*3=135*15 mfds.=.otal capacity in c rcuit up to “Buccaneer’s” Western Splice. 64 Electrical Report. Tests from Ship on Havre End ( before making Final Splice, 5/2/02J. 10.18 A.M. T pn(Hh itl p : rpn jf f Ship to B16ville =75*595 N.M. Length in cncuit j B16ville to Havre= 3*217 „ Total=78*812 „ (Cable Earthed at Havre). Conductor Resistance 18 cells. 1000:1000. Zinc. Carbon, 1284 1268 1289 1268 1288 1276 1282 1270 1287 1272 Temperature Bridge Coils=54° F. O.K. at 60° F. (Platinoid). 10 Mean total C. R. corrected=1277*5. Capacity 20 cells. Cable Free at Havre. Kelvin’s “ Null ” Method (using K. & V.’s Slides). 10.26 a.m. Standard Condenser=20*2379 mfds. Slide Reading =5525. Total Capacity of Cable= 24*987 mfds. D.R. 20 cells (30 volts). Cable Free at Havre. Mins. Zinc. Lead=nil S.R. 10000. 1 = 20 S.R. 10000 m.p.=l. 2 = 19 3 = 18 4 = 19 5 = 18 ft D.R. total=33'37. ft D.R. per n.m.= 2630 at sea temperature. ft Constant 20 cells through 10 s =267 S.R. 400=667*5 through 1. 65 Electrical Report. Tests from Ship on Waterville End (before making Final Splice , 5 / 2 / 02 J. 1.29 a.m. (End Earthed at Waterville). Conductor Resistance 20 cells. 10000 : 10000. Zinc. Carbon. Length in circuit=436'09 N.M. approximate. 6802 7452 Temperature B.C.=52° F. Correct at 60° F. (Platinoid). 6815 7430 6800 7460 6800 7435 Total mean C.R. corrected for E. C.’s (Kempe’s formula) and temperature of Bridge Coils=7111*6. This includes the resistance of 1194 N.M. remaining in tank, which was cut off 0 } before splicing, viz., 19 2. The resistance, therefore, of cable (Waterville side) to 10 co w Havre buoyed end before splicing up=71ir6— 19 , 2=7092 , 4. D.R. Test (30 volts). End Free at Waterville. Mins. Zinc. Lead=nil S.R.=10000. 1 = 50-2 S.R.=10000 m.p.=l. 2 = 42 Q 3 = 38 D.R. total=13-91. 4 = 35 O 5 _ 33 D.R. per n.m .=6068 at sea temperature. Q Constant 30 volts through 10 5 =267 S.R.=400=667’5 through 1. 66 p p p !Z <1 O o p m 03 03 P w EH n p <1 P P P O 67 o * Electrical Length — determined by C.R. * Indicator lengths. FACTORY ELECTRICAL VALUES OF CABLE On Board S.S. “Buccaneer,” on Leaving the Thames, January 30th, 1902. No. Length in N.M. C.R. at 75° F. Capacity. i i D.R. at 75° F. Type. | Remarks. of Wire. Cable. Core. Total per N.M. Total per N.M. Total per n.m. Siemens FORE TANK. Top in Tank. 8553 Plain 11-294 13-22 0-2559 0-2995 Piece 0-8450 0-85 3 Picked up, 17.1.02. D* Rib 11-337 13-27 0-2525 0-2956 - Plain 11-253 13-22 0-3229 0-2995 Piece 1-0664 1-0781 Picked up, 16.1.02. C* Rib 14-307 13-27 0-3187 0-2956 - - Plain 6-375 13-22 0T444 0-2995 Piece 0-4770 0-4832 Picked up, 15.1.02. B* Rib 6-400 13-27 0T425 0-2956 - - Plain 1 -4595 13-22 00331 0-2995 Piece 0-1092 0-1104 Picked up, 14.1.02. A.* Rib 1-465 13-27 0-0326 0-2956 — Bottom in Tank. AFTER TANK. Siemens’ \ 3-356 57-723 17-2 1-195 0-356 113-8 382- 8514 3-000 49-80 16-60 1-074 0-358 100-7 302- 1 26-916 13-13 0-6773 0-3304 1166- 2390- Siemens' 2-028 2-050 8553 2 26-937 13T4 0-6747 0-3291 1432- 2935- * Picked up during Repairs to Weston— Waterville (1885) Cable, January, 1902. 68 DISTBIBUTION OP CABLE IN TANKS ON BOARD THE S.S. “BUCCANEER,” cq o cq gq tf i— i <1 CH W P3 Ph O £ O i— i EH Pn a O o I. r 69 Electrical Length — determined by G.K.. * Picked up cable — (Havre — Waterville and Weston — Waterville), Indicator lengths. FACTORY ELECTRICAL VALUES OF CABLE Remaining on Board S.S. “Buccaneer,” After Completing Repairs, February 5th, 1902. No. Length in N.M. C.R. at 75° F. Capacity. D.R. at 75° F. Type. Remarks. Wire. Cable. Core. Total per N.M. Total per N.M. Total per N.M. 8514 FORE TANK. Piece H. Core 70/75 0-168 2-921 17-39 0-0519 0-3091 - - Top in Tank. Piece G. Core 70/75 0-145 2-521 17-39 0-0448 0-3091 - - Pieces E, F, G and H, were picked up during Re-\ Piece F. Core 70/75 0-076 1-322 17-39 0-0235 0-3091 pairs to the Havre — W ater- ville Section off Piece E. Core 70 75 0 082 1-426 17-39 0-0253 0-3091 - ~ Cherbourg, Feb- ruary, 1902. No use for relaying, mechanically 8553 bad. Piece D. Plaiu 0-8450 0-8-543 11-294 13-22 0-2559 02995 - - Bib 11-337 13-27 3-2525 0-2956 - - Pieces A to D were Plain picked up dur- Piece C. 1-0664 , 1-0781 14-253 13-22 0-3229 0-2995 — — ing Repairs to Weston-Water- Rib 14-307 13-27 0-3187 0-2956 - - ville 1885 Cable. All O.K., elec- trically and me- Plain Piece B. 0 4770 0-4832 6-375 13-22 0-1444 0-2995 — — chanically. Rib 6-400 13-27 0-1425 0-2956 _ - Piece Plain 1-4595 13-22 0-0331 0-2995 A. Rib 0-1092 0-1104 1-465 13-27 0-0326 0-2956 - - Bottom iu Tank. AFTER TANK. Siemens’ 8514 Core 1-194 — 20-537 17-2 0-4251 0-356 319-9 382- Top in Tank. 70/75 3-000 _ 49-80 16-6 1-074 0-358 100-7 302- Siemens’ 8553 1 26-916 13-13 0-6773 0-3304 1166- 2390- Core 2-028 2-060 Bottom iu Tank. 90/85 2 26-937 13-14 0-6747 0-3291 1432- 2935- 70 Electrical Report. EXPENDITURE TABLE. New Cable. Siemens’ 8514. Received from Messrs. Siemens Bros, off Telegraph Works. Silvertown, 29.1.02 Laid in Havre— Waterville Section, 5.2.02 = 2154 Splice = 0-008 | = 2162 Remaining on board in “Buccaneer’s” After \ _ Tank after completion of repairs, 5.2.02 j N.M. 6356 = 6356-' Old Cable. Cable picked up, abandoned, etc., etc., during Havre— Waterville Repairs. ) _ Total - J i Coiled in “Buccaneer’s” Fore Tank. Piece E = 0 082 „ F = 0076 „ G = 0145 „ H = 0-168 Cut off for damaged ends, '004 ‘004 -j- ’003 Cut off for Splice Abandoned between Havre and Waterville Buoys = 0-471 = 0-011 = 0-007 = 1-415 Y N.M. = 1-904 Increase in Length of Havre — Waterville Section. N.M. New Cable laid in Section = 2’154 Cable picked up, abandoned, etc. ... = 1"904 Increase in length = 0'250 71 HAVRE— WATERVILLE CABLE. m § & a 5 z w 5*43 3£ cq o 05 p P3 m w pH P3 H H £ <1 o o p pp CQ CQ P w Eh >h P3 m P3 HH Ph Ph Pi O C3£ cq II S3 CO +3 pH 0)0 _• H ' H P ’ZO’Z'2. ‘pa^onq pu-e « s H S P £ P$ ° t> W £ po^ooq oiqBQ 'z Suiq a Piece “ B ” L =0-082 -f 0-004 N.M. •!Hnnj i^utSuo fc •pua u95[oag s £ 1 o "S iO •pua uo^ojg; 'S S3 O •O S3 pi' a 3 s* o3 ■§ Il8 •ZO'Z'f ‘pasiooq oiqtJO si 0 PP® •t Suia ■M- O fc £ a w« 3 00 o' 3«j g ® CO S> II G? n Itf . Vi a & » a Hi ftg P3 o id OS a a3 j-. -s P “i >* S. +2 5a H p. ■g 2 0 n aS 3 >-i 0) <1) O ° abandoned, . OripzrzaC line of cable ols given 1 1 Jill positions are from DP. no sights ohlainable , COMMERCIAL CABLE C 2 HAVRE -WATERVILLE REPAIR BY S.S.BUCCANECR FEB:i9©a A/OT£ LES. SCALE I HAVRE— WATERVILLE CABLE. ID u £ cq o 05 pH <1 PP « PH P5 S S £ <1 o o p w GQ GQ P w EH P3 m Ph w <1 Ph P Ph Ph O bo 3H> •c S > II 8 'S' 5 9 'ZO’Z'2 ‘pa^onq pn-e p93[Ooq 9[qi30 "z S^jq; •iqn'Eij 1'BntSi.TO •pua U93[0Ja •pna U95[0aa ■ZO'Z'f ‘P92[00TI 9iqBQ •f S'BJd ± <0 rH So £ •> a: .g-o jz oJ II Csj u n . • a; g Q< <2 'O o ■g 2 8 o JM ci O Q. S CQ PQ 3 >-i a> a) o a> ^ <1 7 o 32 ,. 2 Buoy's Moorings . — 15 fms. 4x4 side rope, 2 20 and 2*10 fm. lengths chain, mushroom = 4 cwt. Dodging ship round buoy, awaiting to check position of same. Light NW wind. Fine and clear. Bar. 30 00. Ther. 75° F. Lowered boat and sent her away to dismantle Mark Buoy, it being 4 miles S of position. 22 On Cableground. S.S. “ BUCCANEER.” HOUR. P.M. 2.15 2.27 3.0 3.5 3.10 3.20 3.25 3.40 4.0 4.5 4.30 5.0 5.30 6.0 6.35 6.50 7.5 WEDNESDAY, JULY 23rd (3rd DAY OUT) — Contd. Knocked up tumbler and commenced picking up buoy’s moorings. Hove up buoy and boat. All moorings on board. Set on for new position to place Mark Buoy. Stopped ship and sounded No 2 — 55 fms., sand. Sounded No. 3 — 55 fms., sand. On Cableground. In position. Commenced paying out buoy’s moorings. All moorings paid out. same moorings as before. Lat. 50° 53' -5. Lon. 7° 38' -5. Position Slipped Mark Buoy, “ J,” with Lowered boat and sent her to put lamps on buoy. Boat returned to ship and was hoisted. Light NW wind and fine weather. Bar. 30-00. Ther. 70° E. Drag No. 1. Lowered ordinary grapnel, with 10 fms. f" chain, and commenced paying out 4x4 rope. Paid out to 100 fms. of rope and chain. No strain. Engines moved as required. n n )) 9f Strain steadily rose, commenced to pick up. Grapnel at bows with cable. Got drum ropes along and secured to each side of cable. Cut cable, hove grapnel inboard, and took grappling chain off drum. 23 On Cableground. S.S. “ BUCCANEER.” HOUR. P.M. 7.15 7.35 8.0 8.12 8.20 8.25 8.35 8.40 9.14 10.30 10.45 10.50 11.5 11.25 11.27 WEDNESDAY, JULY 23rd (3rd DAY OUT) — Contd. Took drum rope attached to Waterville end to drum and commenced heaving in. Enough cable abaft drum for testing. Commenced testing to Waterville. Cable — Type No. 8552, §§ core. Sheathing = 17 wires, 0"*124 dia. Light NW wind. Fine weather. Bar. 30-00. Ther. 70° F. Finished testing. Tests showed cable to be “ O.K.” to Waterville. Sealed Waterville end, and prepared to buoy same. Commenced paying out buoy’s moorings. Decided to hang on to Waterville end until Weston end was tested. Veered away on Waterville end and picked up on Weston end. Weston end abaft drum. Commenced testing. Finished testing. Tests showed fault to be about three miles outboard. Sounded No. 4 T — 54 fms. Temp. 50'5° F. Veered away on Weston end and picked up on Waterville end to fix buoy’s moorings afresh. Commenced paying out moorings attached to Waterville end. All moorings out. Slipped buoy No. 42. Position Lat. 50° 52'-2 N. Lon. 7° 34'*7 W. Buoy's Moorings. — bridle, 15 fms. 4x4 side rope, 7-10 fm. lengths -§" chain, 2J fms. f" mushroom chain, mush- room =4 cwt. Took drum rope attached to Weston end to drum and commenced picking up to fault. 24 On Cableground . S.S. “BUCCANEER.” HOUR. P.M. 11.30 MID. A.M. 0.10 0.32 1.0 1.22 1.45 2.6 2.10 3.15 3.25 3.35 4.0 4.44 6.50 WEDNESDAY, JULY 23rd (3rd DAY OUT) — Contd. End of cable off drum. Set Ind. 0. Coiling cable into No. 1 tank. Mod. W wind. Fine clear weather. Bar. 29*97. Ther. 76° F. THURSDAY, JULY 24th (4th DAY OUT). 0*50 n.m. of cable picked up. Cable in good mechanical condidion. 1*00 n.m. of cable picked up. Cable in good mechanical condition. 1*50 n.m. of cable picked up. Cable in good mechanical condition. 2-00 n.m. of cable picked up. Cable in good mechanical condition. 2*50 n.m. of cable picked up. Cable in good mechanical condition. 3*00 n.m. of cable picked up. Cable in good mechanical condition. Ind. = 1084 revs. = 3*115 n.m. of cable picked up and coiled in fore tank. Cut cable at this length in fore tank and found fault in the piece in tank. Tests on cable out- board to Weston satisfactory. Continued picking up on cable very slowly, coiling cable on deck. Ind. = 1218 revs. = 3*502 n.m. total cable picked up on Weston end less 3*115 n.m. = 0*387 n.m. on Weston end on deck. Lowered 4 cwt. mushroom with 100 fins, of drum rope, to act as moorings during making of splice. Got up top end of cable, Type 8553, from after tank and opened out to splice on to Weston end. Mod. NW breeze and clear. Bar. 29*96. Ther. 64° F. Commenced joint, Cut 7 fms. off after tank end. Finished joint. 25 On Cableground. S.S. “ BUCCANEER.” HOUR. A.M. 7.0 8.0 9.30 9.50 9.55 10.4 10.7 10.10 10.14 10.22 10.23 10.36 THURSDAY, JULY 24th (4th DAY OUT).— Contd. Commenced splice. Finished splice. Light WNW breeze and fine. Bar. 29-94. Ther. 64° F. Commenced picking up mushroom, mooring ship. Mushroom up. Set on “ Slow ” ahead, paying out cable (Type No. 8553), from after tank, to Waterville buoyed end. Put engine out of gear. Splice between cable in after tank = Pt. Piece “ C,” and Weston end passed off drum. Ind. = 134 revs = 0’387 n.m. of cable paid out. Position of splice (Lat. 50° 52'-4. {Lon. 7° 29'-5. Splice in cable, Type 8553, between Pt. Piece “C” and Pt. Piece “ C ” in after tank passed outboard. 0-277 n.m. cable from after tank laid. Ind. = 348 revs. = 1-000 n.m. of cable paid out, less 0-387 n.m. = 0-613 n.m. of cable laid in from after tank. Splice in type No. 8553 from after tank between Part Piece “C” and Piece “A” passed out board. Ind. =480 revs. = l-382 n.m. of cable laid — 0*387 n.m. = 0*995 n.m. of new cable laid in from after tank. Splice in type No. 8553 from after tank between Piece “ A ” and Piece “ B ” passed out board. Ind. =502 revs. = 1-445 n.m. of cable laid — 0-387 n.m. = 1-058 n.m. of cable laid in from after tank. Splice in type No. 8553 from after tank between Piece “ B ” and Piece “ D ” passed out board. Ind. = 655 revs. = 1-885 n.m. of cable laid — 0-387 n.m. = 1*498 n.m. of cable laid in from after tank. Ind. = 696 revs. = 2-000 n.m. of cable laid -0-387 n.m.= 1-613 n.m. of cable laid in from after tank. Splice in Type No. 8553 from after tank between Piece “D” and New Type No. 8553 passed outboard. Ind.= 944 revs. = 2-716 n.m. of cable laid — 0-387 n.m. = 2*329 n.m. of cable laid in from after tank. 26 On Cableground. S.S. “BUCCANEER.” HOUR. A.M. 10.41 11.0 11.5 11.7 11.25 11.40 NOON. P.M. 0.12 0.20 0.25 0.45 1.25 2.0 3.30 3.45 THURSDAY, JULY 24th (4th DAY OUT)— Gontd. Ind. = 1044 revs. = 3 000 n.m. of cable laid — 0*387 n.m. = 2 613 n.m. of cable laid in from after tank. Ind. = 1254 revs. = 3-607 n.m. of cable laid — 0-387 n.m.= 3-220 n.m. of new cable laid in from after tank. Stopped ship and put brakes down, and put engine in gear, ap- proaching buoy on Waterville end. Lowered boat and sent her away with drum rope to dis- mantle buoy on Waterville end. Took turns of cable off drum, and took drum rope attached to buoy’s moorings to and commenced picking up. Ind. = 1254 revs. = 3-607 n.m. when cable was taken off drum. Veered away 36 fms. of cable. All moorings on board, and enough Waterville end abaft drum for splice ; put hanging ropes, stoppers, and rounding on. Light WNW wind. Fine and clear weather. Bar. 29-92: Ther. 75° F. Commenced testing to Waterville. Cut Weston end (tank end). Length paid out by Indicator. Total cable paid out from after tank = 3-220 N.M.+ •036 n.m. veered away +'012 cut off for splices = 3-268 n.m. Sounded No. 5 T — 54 fms. Temp. 50° F. Finished testing Waterville end, “ O.K.’’ Commenced testing Weston end from cut. ^Finished testing Weston end, “O.K.” Commenced opening out end for joint and preparing for splice. Commenced joints. Cut 5 fms. off Weston end (tank end). Finished joints. Commenced splice. 27 Slipping Final Splice and Homeward Bound . S.S. “BUCCANEER.” HOUR. P.M. 4.50 4.55 5.0 5.25 5.45 5.50 5.57 8.0 11.0 MID. A.M. 0.38 1.56 4.0 4.50 THURSDAY, JULY 24th (4th DAY OUT) — Contd. SLIPPING FINAL SPLICE AND HOMEWARD BOUND. Finished splice. Veered away on hanging ropes. Cut hanging ropes, letting go the final splice, thus com- pleting the Repair to the Weston — Waterville (1885) Cable. -d ... (Lat. 50°52'-2. Position |l 0 ii_ 7° 34'-7. Set on to pick up Mark Buoy “ J.” Up to buoy. Lowered boat, and sent her away with drum rope to dismantle same. Knocked up tumbler and commenced heaving up moorings. Hove up buoy and boat. All moorings on board. Set on “full ahead ” for London. Light W wind. Fine and clear weather. Bar. 29-92. Ther. 63° F. Observed Sendeen and Round Island lights. Light variable wind. Fine and clear. Bar. 29-90. Ther. 66° F. FRIDAY, JULY 25th (5th DAY OUT). Round Island Light abeam. Longships Light abeam, 6 n.m. distant. Light WNW wind. Cloudy and overcast. Bar. 29-92. Ther. 68° F. Lizard Point abeam, 4 n.m. distant. Signalled number. 28 Steaming Up Channel. S.S. “BUCCANEER.” HOUK. A.M. 8.0 8.6 10.4 NOON. P.M. 2.5 4.0 8.0 11.50 MID. A.M. 0.33 2.30 3.0 4.0 4.10 5.50 8.0 8.50 10.55 FRIDAY, JULY 25th (5th DAY OUT) — Contd. STEAMING UP CHANNEL. Light SW Wind. Cloudy and overcast. Bar. 29-94. Ther. 65° F. Eddystone Lighthouse abeam, 7*5 n.m. distant. Start Point abeam, 4*5 n.m. distant. Light S wind. Cloudy and overcast. Bar. 29-92. Ther. 67° F- Distance run = 195 n.m. from Mark Buoy. Portland Lighthouse abeam. Light SSE wind. Cloudy and overcast. Bar. 29-92. Ther. 64° F. Mod. ESE wind. Overcast and raining. Bar. 29-91. Ther. 64° F. Beachy Head abeam, 4-5 n.m. distant. Mod. ESE wind. Overcast and raining. Bar.. 29-87. Ther. 64° F. SATURDAY, JULY 26th (6th DAY OUT). Royal Sovereign Light Vessel abeam, 2 n.m. distant. Reduced speed off Dungeness. Stopped ship. Pilot boarded. Proceeded again. Light SSE wind. Overcast and occasional showers. Bar. 29-72. Ther. 68° F. Signalled to Dover. Passed North Foreland. Fresh SW breeze. Cloudy and showery. Bar. 29-68. Ther. 66° F. Passed Nore Light Ship. Stopped off Gravesend. Discharged Channel Pilot and took River Pilot Letten. 29 Arrived off Silvertoivn. S.S. “BUCCANEER” HOUR. A.M. 11.10 NOON. P.M. 0.30 SATURDAY, JULY 26th (6th DAY OUT). — Contd. Set on full ahead for moorings at Silvertown. Strong SW wind. Fine and clear. Distance run since Noon yesterday = 243 n.m. Arrived off Silvertown and made ship fast to buoys. During the morning tests were made on the 3T15 n.m. piece of cable in fore tank picked up on Weston end, and the fault was localized at 2*855 n.m. from bottom end of tank. The fault was cut out and handed to Mr. Gott ; 0*040 n.m. was expended in removing the damaged portion, thus reducing the length to 3*075 n.m., in four pieces. These pieces were spliced up July 31st as below : Original Cut off Present Length. for Splices. Length. Piece 1 . . . 2*715 n.m. 0*007 N.M. 2*708 N.M. „ 2 ... 0*250 „ 0*007 „ 0*243 „ „ 3 ... 0*060 „ 0*007 „ 0*053 „ „ 4 ... 0*050 „ — 0*050 „ 3*075 n.m. 0*021 N.M. 3*054 n.m. 30 COMMERCIAL CABLE COMPANY’S' WESTON— WATERYILLE (1885) CABLE REPAIR. S.S. “BUCCANEER,” JULY, 1902. Q S3 EH < P > HH g P o EH W o ►H £ l P PQ < O P O P O HH EH P PQ HH fl EH CQ Q P <5 O PQ O H P PQ <1 O P <1 P o EH 31 Fore Tank ... ... 3*075 n.m. = 8*90 Tons. After Tank 4*992 „ = 24*06 „ COMMERCIAL CABLE COMPANY'S WESTON— WATERVILLE (1885) CABLE REPAIR. S.S. “ BUCCANEER,” JULY, 1902. DISTRIBUTION OF WEIGHT IN SHIP ON ARRIVAL AT GRAVESEND. Cable in fore tank ,, after ,, Coal in bunkers Fresh water in after fresh water tank ,, ,, cones ... ,, ,, side tank Water in ballast tanks — forward ,, ,, aft ... Boatswain’s stores — forward ... Carpenter’s ,, Cable stores and buoys Engine room stores Water in main boilers Steward’s stores Extra chain cable Spare anchors, ropes, etc. ,, propeller ... Deck machinery Tons. 8*90 24-06 7000 2-00 7000 15-00 2-00 •20 8-50 1- 50 28-00 •50 1-00 2 - 00 3-00 10-00 Total ... 246*66 tons 32 ELECTRICAL REPORT. 4 WESTON— WATERVILLE (1885) CABLE REPAIR. JULY, 1902. o c 33 INDEX TO ELECTRICAL REPORT. PAGE Weston — Waterville Repair Report .. 39 Factory Electrical Values at 75 Q Fahr. of Cable after Repair, 24.7.02, Plain Core 47 Factory Electrical Values at 75° Fahr. of Cable after Repair, 24.7.02, Rib Core 48 Tests from Ship towards Waterville, 23.7.02 49 Test from Ship towards Weston, 23.7.02 49 Tests from Ship towards Weston, after cutting out fault, 24.7.02 ... 50 Test on Cable in After Tank, before splicing to Weston End, 24.7.02 ... 50 Tests from Ship towards Waterville, before making Final Splice, 24.7.02 51 Tests from Ship towards Weston, before making Final Splice, 24.7.02 ... 52 Tests from Weston and Waterville after Repair, 25.7.02 ... ... 53 Distribution of Cable in Tanks on Leaving Thames, 21.7.02 ... ... 65 Factory Electrical Values at 75° Fahr. of Cable on Leaving Thames, 21.7.02 56 Distribution of Cable in Tanks on Return to Works, 26.7.02 57 Expenditure Tables ... ... ... ... ... ... ... ... 58 Notes re Mean Bottom Temperatures .. . ... ... ... ... ... 60 Distribution of Cable in Tanks after Splicing up and Transferring Picked up Cable ••• ... 61 Factory Electrical Values at 75° Fahr. of Cable after Splicing up and Transferring Picked up Cable 62 Tests on Cable in After Tank, 7.8.02 ... 63 35 ELECTRICAL REPORT. 37 o d ELECTRICAL REPORT. F. C. Crawford, Esq., Engineer in Charge. S.S. 11 Buccaneer.” August 11th , 1902. Dear Sir, The object of this Expedition was the removal of a high resistance fault which existed in the Plain core of the above- mentioned cable, and which had been located from Weston at 149 n.m. from Waterville, and 182 n.m. approx, from Weston. On July 21st, 3.25 p.m. — Mr. Gott, Electrician in Chief to the Commercial Cable Company, and Staff having joined ship shortly after noon — the “Buccaneer” cast off her moorings and proceeded down river, arriving off Dover at 9.15 p.m. same night, where the Channel Pilot was discharged. After a fine passage down Channel the ship ar- rived on the cableground (Lat. 50° 53' N, Lon. 7° 35' W) at 11.30, p.m. and July 23rd sounded in 56 fms., let go Mark Buoy and stood by to verify position by p.m. sights. At 1 p.m. finding the Mark Buoy out of position, it was taken on board, and ship set on to take up new position. At 3 p.m. sounded in 55 fms., and at 3.20 let go Mark Buoy, lowering grapnel at 3.52, and commenced Drag 1, the cable being hooked and brought to bows at 6.50 p.m. Waterville end was handed to Testing Room at 7.30 p.m., and called on Morse instrument, ship receiving an immediate reply. Tests were then taken from the ship on Weston end, and gave the following results : D.R. (30 volts). Length in circuit = 149-5 n.m. ft ft Plain core, 1st min., Zinc total = 52-274 = 7815 per n.m. at sea temperature. 39 o 2 d Electrical Report. fi Rib core, 1st min., Zinc total = 41-072 = 6140 per n.m. at sea temperature. C.B. -p • , n A Q r 7 Ci r 7 4 . (Plain core = 1901-49. Resistance ot looped cores = 3797 corrected | —1895-51 OJ C.R. at 75° (from Factory values) Plain core = 1995*5. Rib = 1989*365. Calculated temperature = 52° F. (For full tests on this and subsequent tests sec Appendix.) Tests on Waterville side being satisfactory, the following S.G. was sent — 8.7 p.m. Gott to Y.P. and M.E., “Wednesday, 8 p.m. Cut in 7 p.m. ‘ O.K.’ to Waterville. Now buoy that end and pick up to fault on Weston side. Weather fine.” The cores of Waterville end were then sealed, and cable veered away in order to pick up on Weston end. At 9.14 p.m., called Weston on Morse, and instructed him to “loop” cores. A loop test was then taken (Vafley’s) from ship in order to locate fault in Plain core. The fault proved to be very- variable, and of high resistance. The results of several tests were as follows : OJ The two lowest results gave distance to fault = 37-18, which OJ divided by 12-74 the C.R. per n.m. (mean) = 2-918 n.m. from ship. OJ OJ The mean of tests = 38*88 h- 12*74 = 3-052 n.m. from ship. OJ Note. — The C.R. of looped cores (corrected) = 4635*1 | Plain core = 2316*85. (Rib „ =2318-25. Weston was then instructed to take a loop test as an additional check against ship’s figures — the ends being looped on board, and at 10.25 p.m. ship received shore’s results. “ Added resistance to plain to balance = 70 ohms. ” = 2*75 n.m. approx. = distance from ship to fault. OJ Note. — The C.R. of “looped” cores by Weston’s test = 4640- corrected. 40 Electrical Report. At 11.25 p.m., July 23rd, slipped buoy No. 42 Red “ B ” attached to Waterville end and commenced picking up towards fault on Weston end, coiling down in fore tank. During the process of pick- ing up, a control test was maintained, in the hope that when the fault was disturbed on the bottom or at the time of leaving the water, certain indications would be noticed on the galvanometer, but owing, doubtless, to the high resistance of the fault, no marked changes were observed, in fact, nothing which justified cutting the cable before the full length indicated by the loop test had been recovered. ft ft The resistance of fault during picking up varied from *958, *166 ft to l - 87, falling at one time to 71560 units. Picking up was continued until 2.10 a. m. (July 24th), when current was taken off to cut cable. Length picked up = 3T15 n.m. by ship’s indicator. Tested and found fault inboard. At 2.40 a.m., Weston was instructed to free both cores for 15 min- utes, and a D.R. test, taken with 30 volts, gave the following result : ft ft Plain Core 1st min. Zinc total = 27*381 = 4884 per n.m. Rib „ „ „ =30*264 = 5398 Length in circuit = 178*33 n.m. each core. The cores were then looped for ship’s C.R. test. n d f i , A rnn Plain core = 2280*4 C.R. of loop, corrected = 4562*2 1 l Rib „ =2281*8 (For full tests see Appendix.) The cable in after tank, Type 8553, was then tested, the D.R. with 300 volts, and the tests being highly satisfactory (see Appendix) the end was given out to prepare for splicing. The following S.G. was then forwarded to Weston at 4.5 a.m. — “ Gott to V. P. andM. E. Thursday, 4 a.m. Have taken out fault and now splicing on ; about three miles to pay out. Weather fine.” At 4.45 a.m., commenced jointing cores of after tank cable to Weston end, the same being finished at 6.50 a,m f , the joints and all 41 Electrical Report. bare core on each side of joints being brass taped. The splice was finished and compounded by 8 a.m. 7 fms. cut off tank end for splice. Immediately the splice was finished, Weston was instructed to free both cores for 15 minutes, and tests were then made from ship for capacity. Capacity from ship to Weston by Kelvin’s Null Method : At 8.30 a.m. (July 24th), received the following message from Weston, re Waterville’s tests on sealed and buoyed end. “ Here Waterville’s results — Insulation 10th minute, Plain Z. = 82-48, C.= 56*48. Rib Z. = 85*96, C. = 54*15. Non-earth Zinc to Rib = 63*72, C. to Rib = 60*94 megohms absolute. Capacity, Plain = 46*73, Rib = 46*28 mfds. The cable towards Weston was then tested from ship for D.R. 30 volts, both cores being “ free ” at Weston. Tests were highly satisfactory, the cable giving : ft ft Plain Core 1st min. Zinc total = 35*938 = 6569 per n.m. At 9.50 a.m. (24th), ship started paying out cable towards Water- ville buoy, a control test being maintained during the whole time — 20 cells being used — cores being “free” at Weston. At 11 a.m., the buoy on Waterville end was reached, and at 11.25 a.m. Waterville end was on board. The following S. G. was then sent from ship via Weston (11.27 a.m.) — “ Gott to V. P. and M. E. Thursday, 11.20 a.m. Both ends on Plain Core =55*830 mfds. Rib ,, =55*235 mfds. Spliced Rib „ „ =35*938 = 6569 Length in circuit = 182*79 n.m. This includes the capacity of 4*3805 n.m. of cable in after tank, 42 Electrical Beport. board. Tests all right both ways. About to make final splice. Weather fine.” From 0.13 to 0.40 p.m., tests for C.E., D.E., and I.C. were made on Waterville end. Length in circuit = 149-5 n.m. 0 } C. E. Eesistance of loop (cor.) = 3796-4 = D. E. 30 volts. o o Plain core, 1st min., zinc total = 61-25 = 9157* per n.m. to to Eib „ ., „ =47-116 = 7044* „ Capacity 30 volts. Plain core. Total Capacity = 46*108 mfds. Eib „ ,, ,, =45*904 ,, (For full tests see Appendix.) Plain core = 1901*19. Tests being “ O.K.” said G.B. to Waterville, and gave out end to prepare for Final Splice, and attention was then given to Weston end — tests being made for C.E., D.E., and Capacity. Weston End. Length in circuit = 181*620 n.m. / it) C.E. Eesistance of loop (corrected) = 4642* = J -^ a i n core = 2320*3. Eib = 2321 7. D.E. 30 volts. to to Plain core, 1st min., zinc total = 40*834 = 7416* per n.m. to to Eib „ „ „ „ =36*034 = 6544* „ Capacity 30 volts. Plain core. Total Capacity = 55*372 mfds. Eib „ „ „ =54*805 „ Tests being highly satisfactory at 1.20 p.m., Weston was called and informed that ship was about to make final splice, and instructions were given to call Waterville at 4 p.m. Closed at 43 Electrical Report. 1.25 p.m. with Weston, and gave out end to prepare for Final Splice. The joints were completed at 3.30 p.m. — all bare core and joints brass taped — and at 4.50 splice was finished — splice being compounded as before. 5 fms. were cut off tank cable for splice. At 5 p.m. (24.7.02) the Final Splice was slipped — the bottom temperature at this position being 50° F. The ship then proceeded to pick up Mark Buoy and moorings, w T hich operation being completed at 5.51 p.m., she set on full speed for London. Removal of Fault in Picked Up Cable. During the passage home, the picked up cable in fore tank — 3T15 n.m. (Indicator length) — containing fault was dealt with. Great difficulty was experienced in locating position of fault, as since picking up the cable the fault had sealed, and even the application of 260 cells = 390 volts, failed to break the fault down, the resistance n rising at times to 1-9. First operation : — Turned down cable on deck and cut at 0*2500 n.m. This \ mile tested “ O.K.,” and the cable in tank faulty. Cable remaining in tank = 2*865 n.m. A further length of 150 fms. was then coiled down on deck from tank cable and cut. The fault was found to be in this 150-fm. length. A loop test (Yarley’s) taken on this piece was very unsatisfactory, the results varying greatly, as the resistance of the fault was very high. The tests placed fault nearly in centre of cable (natural resultant). A cut was then made at 60 fms. from top end of coil ; this piece tested ‘ 5 O.K.,” fault being in the 90 fms. piece. A further length of 50 fms. was then cut off which tested “ O.K.,” leaving 40 fms. which contained the fault. This piece was halved, and the fault found to be in the last 10 fms. remaining on deck. Therefore the position of fault was at — 2*715 n.m. 0*150-0*010 = 0*140 n.m. 2*855 n.m. from the bottom end in tank, i.e., 2*855 from “ cut in ” by “ Buccaneer,” 23.7.02, 44 Electrical Report. The 10-fm. length was stripped on board, and the fault removed. A length of one yard of core — both plain and rib — on either side of fault was cut out and handed to Mr. Gott at Gravesend. The fault was in plain core. Nature of Fault. At the position of fault the G.P. of plain core had a discoloured patch — yellow — about J inch long, and extending about half round circumference of core. The core was sticky at this patch, and had small fibres of jute attached to it. No sign of any puncture what- ever. The sheathing and serving at this place were perfect, with no sign of any shell fish or teredo. The only surmise is, that this was a Factory fault caused by some foreign substance on the core. The rib core was perfect at this point. On arrival at Gravesend on the morning of July 26th, Mr. Gott received a letter from the Superintendent at Weston, containing copies of tests taken from Weston and Waterville respectively, after Final Splice had been slipped, which proved the cable to be in perfect electrical condition. The “Buccaneer” arrived at her moorings off Silvertown at 0.15 p.m. same day. Since the return of the “ Buccaneer ” to Silvertown, the picked up cable in fore tank has been spliced up and transferred to after tank. All cable on board belonging to the Commercial Cable Company was tested on the 7th inst. with highly satisfactory results, and copies of these tests will be found in the Appendix, together with revised Loading Table and 75° values. In the Appendix will be found the following tables, etc. : Bevised lengths and Factory values at 75° F. of Weston — Water- ville Cable (both cores). Tests from ship towards Weston and Waterville at position of “ cut in.” Tests from ship towards Weston after removal of fault. 45 Electrical Report. Test on cable in after tank before splicing to Weston end. Tests from ship towards Weston and Waterville before making Final Splice. Final tests from Weston and Waterville after repairs. Distribution of cable in tanks on board “Buccaneer,” and 75° F. values before repairs. Distribution of cable in tanks on board “ Buccaneer,” and 75° F. values after repairs. Expenditure tables of new and picked up cable. Notes on mean bottom temperature. Distribution of cable on board “ Buccaneer ” after splicing picked up cable. Factory values at 75° F. of cable on board “Buccaneer” after splicing picked up cable. Tests on cable on board S.S. “Buccaneer” after splicing up, 7.8.02. I am, Dear Sir, Yours faithfully, HERBERT E. CANN. Electrician. 46 FACTORY ELECTRICAL VALUES AT 75° FAHR. OF THE WESTON— WATERVILLE (1885) TWIN CORE CABLE After Repairs by S.S. “Buccaneer,” July 24th, 1902. [Not including 0-221 n.m. Waterville Land-line.] Length of Section. C.R. at 75° Fahr. Capacity. Length. Remarks. Total Total Sum Per N.M. Total Sum Per N.M. N.M. of of of of of of Section. Totals. Section. Section. Totals. Section. WESTON. Plain Core. 3-845 52-03 13*54' 1-185 0-3082 “ Bittern.” 14-304 18-149 190-80 242-83 13-342 4-342 5-527 0-3036 1-022 19T71 13-61 256-44 13-342 0-309 5-836 0-3036 1 0-671 19-842 8-95 265-39 13-342 0-203 6-039 0-3036 [• “ Marmion.” 3-598 23-440 47-67 . 313-06 13-25 1-202 7-241 0-3340 i 1-109 24-549 14-80 327-86 13-342 0-336 7*577 0-3036 1-089 25-638 14-26 342-12 13-10 0-329 7-906 0-3022 V “Mirror.” 1-782 27-420 23-77 365-89 13-34 0-539 8-445 0-3025 ) 5-831 33-251 77-80 443-69 13-34 1-765 10-210 0-3027 1-561 34-812 27-32 471-01 17-51 0-498 10-708 0-3192 1 “ M.B.” Rockport 1-249 36-061 16-63 487-64 13-32 0-377 11-085 0-3019 J Type. \ 0-285 36-346 3-86 . 491-50 13-55 0-087 11T72 0-3054 [- “ Mirror.” 0-630 36-976 8-51 500-01 13-51 0T94 11-366 0-3079 i 12-988 49-964 173-38 673-39 13-35 3-930 15-296 0-3027 8-460 58-424 113-84 787-23 13-46 2-570 17-866 0-3038 18-524 76-948 245-91 1033-14 13-28 5-580 23-446 0-3013 14-431 91-379 194-04 1227T8 13-45 4-407 27-853 0-3055 0T36 91-515 1-80 1228-98 13-222 0-041 27-894 0-2994 ) S.S. “ Buccaneer,” 2-623 94-138 34-44 1263-42 13-13 0-867 28-761 0-3304 ^ 17.1.02. Bot. tem- 23-515 117-653 310-90 1574-32 13-22 7-040 35-801 0-2994 ) perature 49°-2 F. 60-672 178-325 806-16 2380-48 13-29 18T60 53-961 0-2993 t Eastern Splice. J “Buccaneer,” 24.7.02. 1 0-280 178-605 3-70 2384-18 13-22 0-084 54-045 0-2995 0-758 179-363 10-02 2394-20 13-22 0-227 54-272 0-2995 ) „ 18.7.02. 1 0-064 179-427 0-85 2395-05 13-22 0-019 54-291 0-2995 j „ 19.7.02. ) 0-443 179-870 5-86 2400-91 13-22 0T33 54-424 0-2995 1 „ 17.7.02. 1 0-836 180-706 11-05 2411*96 13-22 0-250 54-674 0-2995 J „ 17.7.02. 0-916 181-622 12-03 2423-99 13-13 0-303 54-977 0-3304 j „ 26.5.02. 0-103 181-725 1-37 2425-36 13-29 0-031 55-008 0-2993 } “Buccaneer’s” 31-575 213-300 425-45 2850-81 13-48 9-595 64-603 0-3040 Final Splice, 24.7 02. Bot. tem. 50 y t ° Fah. 86-660 299-960 1154-08 4004-89 13-32 26-098 90-701 0-3011 Depth, 54 fms. 10-841 310-801 143-07 4147-96 13-197 3-259 93-960 0-3046 0-351 311-152 4-61 4152-51 13-13 0T16 94-076 0-3304 I S.S. “Buccaneer,” [ 16.6.01. 11-692 322-844 156-31 4308-88 13-37 3-571 97-647 0-3055 J 0-340 323T84 4-48 4313-36 13-17 0T13 97-760 0-3330 “ Marmion.” 7-938 331-122 106-13 4419-49 13-37 2-425 100-185 0-3056 WATERVILLE. 47 FACTORY ELECTRICAL VALUES AT 75° FAHR. OP THE WESTON— WATERVILLE (1885) TWIN CORE CABLE After Repairs by S.S. “Buccaneer,” July 24th, 1902. [Not including 0-221 n.m. Waterville Land-line.] Length of Length. O.R. at 75° Falir. Capacity. Remarks. Total Section. Total Sum Per N.M. Total Sum Per N.M. N.M. of of of of of of Section. Totals. Section. Section. Totals. Section. WESTON. Rib Core. 3-845 51-94 13-51 1-165 0-303 “ Bittern.” 14-304 18T49 191-C0 242-94 13-35 4-248 5-413 0-297 1-022 19T71 13-64 256-58 13-35 0-303 5-716 0-2966 \ 0-671 1.9-842 8-96 265-54 13-35 0T99 5-915 0-2966 L “Marmion.” 3-598 23-440 47-63 313T7 13-24 1-202 7*117 0-334 ) 1-109 24-549 14-80 327-98 13-35 0-329 7-446 0-297 1-089 25-638 14-24 342-22 13T0 0-335 7-781 0-308 t “Mirror.” . 1-782 27-420 23-76 365-98 13-34 0-527 8-308 0-2959 J 5-831 33-251 77-84 443-82 13-36 1-725 10-033 0-2959 1-561 34-812 27-32 471T4 17-5 0-498 10-531 _ 0*3192 \ “ M.B.” Rockport 1-249 36-061 16-83 487-97 13-5 0-369 10-900 0-2956 J Type. 0-285 36-346 3-85 491-82 13-5 0-086 10-986 0-3018 L “ Mirror ” 0-630 36-976 8-49 500-31 13-5 0T91 11T77 0-3031 I 12-988 49-964 173-38 673-69 13-35 3-843 15-020 0-2960 8-460 58-424 114-71 788-40 13-56 2-527 17-547 0-2987 18-524 76-948 245-56 1033-96 13-26 5-529 23-076 0-2986 14-431 91-379 195T9 1229-15 13-52 4-380 . 27-456 0-3036 0-136 91-515 1-80 1230-95 13-267 0-040 27-496 0-2956 \ S.S. “Buccaneer,” 2-623 94-138 34-47 1265-42 13T4 0-863 28-359 0-3291 l 17.1.02. Bot. tem- 23-515 117-673 311-97 1577-39 13-267 6-950 35-309 0-2956 ) perature 49°-2 F. 60-672 178-325 804-57 2381-96 1326 17-895 53-204 0-295 ) Eastern Splice. 0-083 f -Buccaneer, 24.7.02. 1 0-280 178-605 3-72 2385-68 13-27 53-287 0-2956 0-758 179-363 10-06 2395-74 13-27 0-224 53-511 0-2956 / „ 18.7.02. i 0-064 179-427 0-85 2396-59 13-27 0-019 53*530 0-2956 f „ 19.7.02 0-443 179-870 5-88 2402-47 13-27 0T31 53-661 0-2956 ; „ 17.7.02. ) 0-836 180-706 11-10 2413-57 13-27 0-247 53-908 0-2956 ; „ 17.7.02. 0-916 181-622 12-04 2425-61 13-14 0-301 54-209 0-3291 / „ 26.5.02. 0-103 181-725 1-37 2426-98 13-26 0-030 54-239 0-295 } “Buccaneer’s” 31-575 213-300 421-04 2848-02 13T3 9*565 63-804 0-303 Final Splice, 24.7.02. Bot. tem. 50yi Q Fah. 86-660 299-960 1153-23 4001-25 13-30 25-724 89-528 0-2969 Depth, 54 tins. 10-841 310-801 142-92 4144T7 13-18 3-209 92-737 0-2960 | S.S. “Buccaneer,” ( 16.6.01. 0-351 311T52 4-61 4148-78 13T4 0-116 92-853 0-3291 11-692 322-844 155-92 4304-70 13-338 3-468 96-321 0-2966 0-340 323184 4-48 4309-18 13T7 0-113 96-434 0-3330 “ Marmion.” 7-938 331T22 105-80 4414-98 13-338 2-354 98-788 0-2966 WATERVILLE. 48 Electrical Report . Tests from Ship towards Waterville ( 23 / 7 / 02 ). Position : “Buccaneer’s” cut in. (Cores looped at Waterville.) 7.40—8.5 p.m. Length in Circuit=149*5 n.m. each core. Conductor Resistance 20 cells=(30 volts). Zinc. Carbon. 3790 3790 Temperature Bridge Coils=74° F. Correct at 60° F. (Platinoid). 3790 3790 3790 3790 3790 3790 CO C.R. of loop corrected for leads and temperature B.C.=3797. co CO Plain Core=1901*49=12*72 per n.m. Calculated temperature=52° F. co co Rib Core=1895*51=12*68 per n.m. co co C.R. at 75° F. (from Factory values). Plain Core=1995*5. Rib Core=1989*365. (Cores Free at Waterville.) Dielectric Resistance (30 volts). Plain Core. Mins. Zinc. Lead=nil S.R.=10000. 1 2 3 4 11 S.R.=10000 m.p.=l. 7 7 6 5 = 6 Rib Core. Mins. Zinc. 1 = 14 S.R.=10000. 2 = 10 3=8 4=7 5=7 D Constant 20 cells (30 volts) through 10 5 =230 S.R.=400=575* through 1. o a D.R. total, Plain Core=52*274 D.R. total, Rib Core=41072. D O D.R. per n.m. „ '=7815' at sea temperature. D.R. per n.m. „ =6140’ at sea temperature. Test from Ship towards Weston ( 23 / 7 / 02 ). Position : “Buccaneer’s” cut in. 9.20 p.m. Length in Circuit=181'475 n.m. Conductor Resistance 20 cells=(30 volts). co Z. and C.=4626. Temperature B.C.=75° F. Correct at 60° F. (Platinoid). co C.R. of loop corrected for temperature, etc.=4635'l. co co C.R. of Plain Core=2316*85=12*767 per n.m. „ Rib ,, =2318*25=12774 „ CO f Plain Core=2422*33. C.R. at 75° F.< co (Rib „ =2423*715. (Fault in Plain Core=3N.M. approx, from Ship.) 49 Electrical Report. Tests from Ship towards Weston ( after cutting out fault , 24 / 7 / 02 ). (After picking up and cutting off 3115 N.M., cable=3"150 n.m. each core.) 2.40 a.m. Length in Circuit=1 78*33 n.m. each core. (Cores Free at Weston.) Dielectric Resistance (20 cells). Plain Core. Mins. Zinc. Lead=nil S.R.=10000. 1 = 21 S.R.=10000 m.p.=l. 2 = 17 3 = 16 4 = 15 5 = 15 Rib Core. Mins. Zinc. 1 = 19 S.R.=10000. 2 = 17 3 = 15 4 = 14 5 = 14 0 Constant 20 cells through 10 5 =230 S.R.=400=575- through 1. ft ft D.R. Total. Plain Core=27‘381. D.R. Total. Rib Core=30-264. ft ft D.R. per n.m. „ =4884* at sea temperature. D.R. per n.m. ,, =5398" at sea temperature. 3 A.M. Zinc. Carbon. co 4555' co 4555* 4555* 4555* ( Cores Looped at Weston.) C.R. 20 cells=30 volts. Temperature B.C.=72° F. Correct at 60° F. (Platinoid). CO C.R. of Loop corrected for temperature B.C., etc.=4562*2. ( O CO C.R. of Plain Core=2280*4-— 12-788 per n.m. C.R. of Rib =2281-8=12-796 Test on Cable in After Tank ( before splicing to Weston End, 24 / 7 / 02 ). Length=4-4308 n.m. Cable=4'4301 N.M. each Core'. Length of Loop=8'86 n.m. Core. 3.30 a.m. (Cores Looped.) < o C.R. of Loop. Leads deducted=l 12-410 Z. & C. Temperature B.C.=72° F. Correct at 60° F. (Platinoid). ( o C.R. of Loop corrected=112-59. Dielectric Resistance (200 cells)=300 Mins. Zinc. E.R. 1 = 28 S.R.=10000 6 2 = 25 3 = 24 4 = 23 5 = 22 Temperature tank=68° F. volts. Lead=l S.R.=10000. Carbon 24 D D.R. Total =226-86. ft D.R. per n.m.=2010* at 68° F. ft Constant 200 cells through 10 s =245 S.R.=40=6125* through 1. 50 Electrical Report. Test from Ship towards Waterville '(before making Final Splice , 24 / 7 / 02 ). (Cores looped at Waterville.) 0.13 p.m. Length in Circuit=149-5 n.m. Conductor Resistance 18 cells. Zinc. Carbon. W o> 3791 3791 3791 3791 Temperature Bridge Coils=71° F.. Correct at 60° F. (Platinoid). 3791 3791 OJ C.R. of loop corrected for temperature, etc.=3796 , 4. (O 0} Plain Core=1901*19=12*72 per n.m. Rib „ =1895'21=12"68 „ 0.20 P.M. (Cores Free at Waterville.) Dielectric Resistance (30 volts). Plain Core. Mins. Zinc. Lead=nil S.R.=10000. 1 = 10 S.R.=10000 m.p.=l. 2=8 3=7 4=7 5=6 Rib Core. Mins. Zinc. 1 = 13 S.R. =10000 2 = 11 3 = 10 4=9 5=8 n Constant 20 cells through 10 5 =245 S.R.=400=612*5 through 1. O D.R. Total Plain Core =6125. D.R. per n.m. Plain Core=9157* at sea temperature. D.R. Total Rib Core =47‘116 D.R. per n.m. Rib Core=7044’ at sea temperature. Kelvin’s Capacity Test (Null method — 20 cells). Using K. & V.’s Slides. Value of Standard Condensers=39 , 119 mfds. Plain Core, Slide Reading=5410. Total Capacity=46"108 mfds. Rib „ „ „ =5399. „ „ =45*904 „ Note.— The mean I.C. per n.m. (from 75 sheets) from Waterville to position of splice=0‘3024 mfds., Plain. The mean I.C. per n.m. (from 75 sheets) from Waterville to position of splice=0'2982 mfds., Rib. Therefore the length to Waterville from “Buccaneer’s” cut in (23/7/02) by measured capacity =46’108-i-0 3024=152-5 n.m. Plain Core ) =45-904-5-0-2982=153-9 n.m. Rib Core J By Waterville’s test to buoyed and sealed end, 24/7/02. Capacity of Plain Core=46'73 mfds.=154'53 n.m. „ Rib „ =46-28 „ =155-20 „ ! Meau=153"2 N.M. Evidently too long, 149'5 being taken as correct length (see O.R. test). 51 Electrical Report. Tests from Ship towards Weston ( before making Final Splice , 24 / 7 / 02 ;. (Cores looped at Westou.) Length in Circuit=181 , 62 n.m. (accepted). * Conductor Resistance 18 cells. Zinc. Carbon. co co 4636 4636 Temperature Bridge Coils=71° F. Correct at 60° F. (Platinoid). 4636 4636 » i> ' » j> C.=22‘10 „ Rib „ „ „ „ Z.=23’63 „ » » ?» » » C.=18‘50 C.R. Rib and Plain= 8145 ohms. Waterville's Tests. Plain Core, Insulation 10th mi ute Z.=8080 per n.m. a „ ,, ,, „ C.=9390 „ Note. — Rib not given. C.R. Plain=4227'5. Rib=4219 5. Note. — T he above results were received — by letter — by Mr. Gott on the “Buccaneer’s” arrival at Gravesend, 26.7.02, from Mr. Gorton, the Commercial Cable Co.’s Superintendent at Weston-super-Mare. o e 53 WESTON— WATERVILLE (1885) CABLE REPAIR. S.S. 41 BUCCANEER,” JULY. 1902. \ cq CO H SS < M EH w EH 55 V- 1 ’» 0-4371 0-4429 J J: C. X> Rib 5-8770 13-27 0-1310 0-2956 — — “ Bucoaneer,” h 17.7.02. OKKO Plain 11-0550 13-22 0-2605 0-2995 — — ouuo ~D^ u „ 0-8270 0-8362 Rib 11-0970 13-27 0-2472 0-2956 — — | “ Buccaneer,” 26.5.02. qkko No. 1 26-798 13-13 0-6743 0;3304 1171- 2390- ODOo Original No. 2 20190 2-0410 26-820 13-14 0-6717 0-3291 1438- 2935- 1 Twin Core Plain 58-3833 1318 1-3900 0-3137 — i 4-3805 4-4301 splic’d Rib 58-5237 13-21 - 1-3780 0-3111 — — up J 8514 Single Core 0-915 15-738 17-2 0-3257 0-356 417-5 382- } i Core 2-992 49-667 16-6 1-0711 0-358 100-9 302- 70/75 3-907 65-405 16-74 1-3968 0-3575 81-26 317-5 56 WESTON— WATERVILLE (1885) CABLE REPAIR. S.S. “BUCCANEER,” JULY, 1902. oq p co cq cq" Pm i— i Pm P « p EM Pm <1 C/2 M « o £ P W EM O EM 55 Pm P Em P P3 CQ P 55 <1 EM 55 P P PQ <1 o Pm O 55 O i— i EM P w S EM CQ 57 Note. — T he Factory values at 75° F. will be found in a revised loading table compiled after splicing operations on board S.S. “Buccaneer,” July 30th, 31st, and August 1st, 1902, when the 4 pieces of Type 8552 Twin Core Cable were spliced up and transferred to After Tank. Weston — Waterville (1885) Cable Repairs. July, 1902. EXPENDITURE OF CABLE, TYPE 8553, TWIN CORE. Ex. After Tank. n.m. Length of Section coiled on board on leaving the Thames | Qore^^*4301 } ’3805 Laid in Section. Expended. Pt. Piece “ C ”=02770 n.m.+ 0 ; 007 (Splice)=0*2840 N.M. „ „ “C ”=0*7500 „ =07500 „ „ “A ”=0-0634 „ =0-0634 „ „ “B ”=0-4371 „ =0-4371 „ ,, “D ”=0-8270 „ =0-8270 „ Original 8553=0*9055 N.M. + 0*005 (Splice)=0"9105 „ 3-2600 (3-2970 Core) 3-2720 Cable. =3-2720 (3-3090 Core) Remaining in tank (After). Twin Core, 8553=1 1085 =(1-1211 Core) SUMMARY. Total Cable expended =3"2720 N.M. „ „ laid in Section=3"2600 n.m. Cut off for Splices=0 0120 n.m. 58 Electrical Report. Weston — Waterville (1885) Cable Repairs. July, 1902. EXPENDITURE OF CABLE, TYPE 8552, TWIN CORE. Picked Up, July 23rd and 24th, 1902. N.M Total Cable Picked Up and Coiled in Fore Tank = 3*115 59 Electrical Report. Weston — Waterville (1885,) Cable Repairs. July, 1902. Notes re mean bottom temperatures calculated from tests taken from Ship and Shore. C.R. Test from Ship to Waterville. July 23rd, 1902. Length in Circuit=149 5 n.m. w Total C.R. at 75° F. (of PLAlN.and Rib cores )=3 984 86 „ „ measured, of loop, corrected =3797* Calculated temperature by Silvertown Coefficient s=52° F. „ „ C., F.andT’s „ =53°* 3 F. C.R. Test from Ship to Weston. July 24th, 1902. Length in Circuit=181'475 n.m. (O Total C.R. at 75° F. (of Plain and Rib Cores )=4846 04 „ ,, measured , of loop, corrected =4635 1 Calculated temperature by Silvertown Coefficients=53°'75 F. „ „ C., F. and T.’s „ =55° F. Weston’s Test after completion of Repairs. July 25th, l;;02. Length in Circuit=331*122 n.m. J. Maguire, 6 Firemen. 4 Trimmers. 4th Donkeyman. Mr. A. Patrick, C. Martin, A. Thiselton, Chief Steward. 2nd Steward and Storekeeper. Chief Cook and Baker. J. Griffen, 2nd Cook and Butcher, J. Nolan, Pantryman. Engineer’s Steward. 2 Assistant Stewards. 1 Scullion. 9 S.S. “BUCCANEER.” CABLE HANDS. W. Tilly er, Foreman. R Keys, Leading Hand. W. Mack, Cable Hand. R. Knights, > ’ 7 7 J. Blaza, , , , , R. Barber, 7 7 7 7 S. Ransome, 7 7 7 7 J. Smith, 7 7 7 7 H. Hills, Fitter. A. E. Newton, Fitter’s Mate. R. Welsh, Jointer. Representatives of the Commercial Cable Company. Mr. J. Gott. Mr. W. Hensman. SUMMARY. Staff ... ... ... ... ... ... 3 Cable Hands ... ... ... ... ... 11 Officers and Crew ... ... ... ... 42 Visitors .. ... 2 Total on board leaving London .. . ... ... 58 10 MECHANICAL DESCRIPTION OF CABLE. 6 N.M. Main Cable, sent from Messrs. Siemens & Co., No. 8512. 3.9.02. Conductor : — Strand of 7 copper wires each "-023 dia., weighing 70 lbs. per n.m. Dielectric : — Gutta percha one coat to "-205 dia., weighing 75 lbs. per n.m. Serving : — Tanned jute yarn. Sheathing : — 10 B.B.G.I., wires "T43 dia. Outer Serving : — Two coats prepared jute yarn alternating with three coats of compound. Ex. diameter = "0-915. Weight in air, dry = 2- 138 tons per n.m. „ ,, wet = 2-175 ,, ,, ,, in sea water = 1-433 ,, ,, HAVRE— W ATE RVILLE REPAIR. S.S. “BUCCANEER,” SEPT., 1902. xn Cable stores and buoys Engine-room stores ... Water in main boilers... Steward’s stores Extra chain cable Spare anchors, ropes, etc. ,, propeller ... Deck machinery TONS. 12-6 Nil. 34-7 Nil. 150-0 130 7-0 5-0 70.0 15-0 1-0 15-0 0- 5 28-0 5-0 1 - 0 2-0 3 0 10-0 Total = 372-8 tons Draught Fore IF 6" Aft. 13' 6". Mean 12' 6" 15 COMMERCIAL CABLE COMPANY’S CHARTER. HAVRE— WATERVILLE REPAIR, SEPTEMBER, 1902. S.S. “BUCCANEER. DRUM CO-EFFICIENTS. Circ. of Drum = 17' 2J" Type. Circ. in inches. Revs. per N.M. Log. Fms. per Rev. Main 8512 Single Core 2-875 348-867 2-5426596 2-908 H.I. 8514 „ „(new)... 4-375 346-385 2-5395594 2-929 „ „ ,, „ (old)... 4-250 346-590 2-5398169 2-927 L.I. 8553 (twin core) 3-465 347-886 2-5414375 2-916 Int. 8552 „ 3-387 348-016 2-5415988 2-915 Grappling Rope — 4x6 (used) 4-646 345-940 2-5390016 2-932 Buoy Rope — 4x4 (new) 3-860 347-233 2-5406213 2-922 3x3 (new) 2-700 349-159 2-5430228 2-905 16 HAVRE- -WATERVILLE CABLE REPAIR EXPEDITION. SEPTEMBER, 1902. STEAMING FROM LONDON TO POSITION OF FAULT. 8.S. “BUCCANEER.” STEAMING FROM LONDON TO POSITION OF FAULT. HOUR. A.M. 9.0 P.M. 1.0 2.20 4.30 9.35 11.20 A.M. 2.30 4.0 7.30 8.0 ' NOON. P.M. 4.0 S.S. “BUCCANEER.” FRIDAY, SEPTEMBER 5th, 1902 (1st DAY OUT). Hands joined ship off Silvertown. Mr. J. Gott (Commercial Cable Company’s Representative), Mr. Hensman (Navigating Officer C.S. “ Mackay Bennett ”), and Messrs. F. W. Robinson, H. E. Cann and R. G. Wood joined ship. Let go moorings and proceeded down river, Pilot Twist in charge. Off Gravesend, Pilot Twist left and Pilot Lygo took charge. Pilot Lygo left at Dover, taking letters and telegrams. Dnngeness abeam. SATURDAY, SEPTEMBER 6th, 1902 (2nd DAY OUT). Beachy Head abeam. Light breeze, fine and clear. Bar. 30-07. Ther. 72°. St. Catherine’s abeam, dist. 3 n.m. Gentle wind and fine clear weather. Bar. 30-10. Ther. 70°. Light breeze, fine and clear. Bar. 30-10. Ther. 72°. -d ... f Lat. 50° 19' N. Position | Lon 20 u , w Distance run from Dungeness 137-5 n.m. Bar. 30 05. Temp., Dry Bulb 76°, Wet Bulb 74°, 19 HOUR. P.M. 7.15 7.28 8.0 11.0 11.20 MID. A.M. 4.0 8.0 9.40 10.5 10.30 10.37 Putting Dozen Mark Buoy and Grappling for Cable. S.S. “ BUCCANEER.” SATURDAY, SEPT. 6th, 1902 (2nd DAY OUT) — Cozitd. Stopped and sounded in 41 fms. Bottom temperature 58*2° E. Sea surface 59° E. -p ... f Lat.-49°45'-0 N. Position sounding No. 1 | Lon 30557.5 w Set on. Light airs and overcast with rain. Bar 30*08. Ther. 62°. PUTTING DOWN MARK BUOY AND GRAPPLING EOR CABLE. Stopped and sounded in 48 fms. Bottom temperature 56*5° E. Sea surface 59-5° E. -d -r ' a- at o f Eat. 49°30'-3 N. Position sounding. No. 2 | Lon 4 o 45 -. 0 w Set on. N. 70 W. Light breeze and overcast with rain. Bar. 3010. Ther. 74°. SUNDAY, SEPTEMBER 7th, 1902 (3rd DAY OUT). Light breeze, fine and clear. Bar. 30-10. Ther. 77° E. Light breeze, fine and clear. Bar. 30-13. Ther. 76° E. Sounded in 66 fms., fine sand. -p ... r xt q f Eat. 49°42 r -l N. Position sounding No. 3 | Lon W. Let go mark buoy “42 P.” Position same as sounding. Moorings. — f" bridle, 15 fms. side rope, 20 fms. f" chain, 65 fms. 4 x 4 rope, 20 fms. -§" chain, mushroom 4 cwts. 1 qr. i 16 lbs., lamphanger and lamps. Ship in position to lower grapnel. Grapnel (ordinary) down, 100 fms. 4x4 and 10 fms f" I chain. Commenced. 20 Buoying Waterville End and Picking Up toivards Havre S.S. “BUCCANEER,” HOUE. A.M. 11.25 11.30 NOON. P.M. 0.15 0.30 0.38 1.50 2.0 2.8 2.25 2.50 SUNDAY, SEPT. 7th, 1902 (3rd DAY OUT) — Contd. Deag No. 1. Position Lat. 49° 43'-l N. Lon. 7° 28'*8 W. Commenced to pick up grapnel so as to get back to mark buoy to verify its position by noon latitude. Position — mark buoy “P” bearing N 25 E dist. 2 n.m. Grapnel up. Set on for mark buoy 2-0 N.M. Position Lat. 49° 41' *5 N. Lon. 7°29'*3 W. c ( P.” Distance run Moderate breeze, fine and clear. Bar. 30-15. Tber. 70°. BUOYING WATERVILLE END AND PICKING UP TOWARDS HAVRE. Sounded in 64 fms. Bottom temperature 50° F. -d V h. XT „ f Lat. 49°42'-l N. Position sounding No. 4 | Lon r 2g ,. 8 w . Ship in position to lower grapnel for Drag No. 2. Two grapnels (ordinary and centipede as trailer) down ; 100 fms. 4x4 rope, 10 fms. f" chain with 2 fms. f" chain between grapnels and 2| fms. trail chain. Commenced. Deag No. 2. ^ ... f Lat. 49° 42'-9 N. Position | Lonj 7 o 29 ,. 7 w Mark buoy “ P ” bearing S 35° E dist. 1-0 n.m. Strain rose to 2J tons. Commenced to pick up. During drag Strain nil, and working engines as required. 30 fms. rope and chain out. Strain, 2 tons. Cable D.S. type No. 8512 at bows on second prong of centipede grapnel, put on bending-on chains. Cut cable on grapnel. Havre end handed over to testing room. Cut 2 fms. off Havre end for damaged sheathing. 21 Buoying Waterville End and Picking Up toivards Havre. S.S. “ BUCCANEEB.” HOU±i. P.M. 3.10 3.45 3.55 4.35 4.50 5.0 5.20 5.30 5.40 6.15 6.18 7.0 7.30 7.50 8.0 8.15 8.45 9.10 9.30 SUNDAY, SEPT. 7th, 1902 (3rd DAY OUT) — Contd. Testing room finished with Havre end, which is faulty. Bent drum rope on again, veered away this end and picked up on Waterville end. Waterville end on board. Waterville end handed to testing room. Spoke Waterville, tests “ O.K.” Cablehands and crew getting buoy and moorings ready for buoying Waterville end. Electrician finished with end. End sealed, and moorings of buoy “ H ” bent on. Commenced to pay out cable buoy moorings, and com- menced to pick up on Havre end. Slipped cable buoy “ H ” on Waterville end. ^ ... f Lat. 49° 40 r, 3 N. Position -I t to oii.i Lon. 7° 3P-9 W. Mark buoy “ P ” bearing N 47-J° E dist. 2-7 n.m. Moorings . — -f" Bridle, 15 fms. side rope, 20 fms. ; f" chain, 50 fms. 4x4 rope, 20 fms. chain ; 10 fms. -f" stray chain ; Mushroom 4 cwt. 1 qr. 7 lb. Sent cable boat away to put lamps on cable buoy “ H.” Havre end on board and taken to Testing Boom. Cable boat returned. Deported from Electrician that fault is 5 n.m. from ship. Commenced picking up towards fault, coiling cable in fore tank. 1 n.m. of D.S. No. 8512 picked up, cable coiling well, strain from 0-25 cwt. 1- 5 n.m. of D.S. No. 8512 picked up, strain from 0-25 cwt. 2 ,, ,, ,, ,> )> >} Bar. 30-20. Ther. 71° F. 2- 5 n.m. of D.S. No. 8512 picked up, strain from 0-25 cwt. 3 j> )) }} >> >> >> ^ 5 ,, ,, >j ?> >> Ind. = 1326 revs. = 3-8 n.m. of D.S. No. 8512 picked up. Cut cable, tested and found fault inboard. 22 Laying Cable Bach to Waterville Buoyed End. S.S. “ BUCCANEER.” HOUR. P.M. 9.40 10.15 11.0 MID. A.M. 0.30 2.0 4.0 4.45 5.15 5.35 5.45 5.55 5.57 SUNDAY, SEPT. 7th, 1902 (3rd DAY OUT) — Contd. LAYING CABLE BACK TO WATEBYILLE BUOYED END. Spoke Havre and tested, results satisfactory. Note. — A loop test taken on picked-up piece in fore tank placed the fault '380 n.m. from bottom end. End handed over for splice between Havre end and D.S. No. 8512 in after tank. Commenced joint. Light breeze, fine and clear. Bar. 30T5. Ther. 74° E. MONDAY, SEPTEMBER 8th, 1902 (4th DAY OUT). Finished joint. 7 fms. cut off for splice from seaward end (Havre). Commenced splice. Finished splice. Men went below till daylight. Moderate breeze and clear weather. Bar. 30-12. Ther. 70° F. All hands called. Commenced to pay out, making N 69° W, true course. Splice D.S. — D.S. on drum, Ind. set at zero. Ship’s engines 24 revs. -d ... , r (Lat. 49° 38'-9 N. Position of splice | Lon . ?0 2 g,. 4 w Ma,rk buoy “ P ” N 25° W, dist. 3-6 n.m. Increased ship’s engines to 26 revs. Ind. = 349 revs. = 1*0 n.m. D.S. type paid out from after tank. Ship’s engines 26 revs. Ind. = 680 revs. = l'95 n.m. cable laid. Splice between D.S. No. 8512 tape and D.S. No. 8512 yarn. Position (Lat. 49° 39'-6 N. (Lon. 7° 29 f, 2 W. Ind. = 698 revs. = 2‘0 n.m. D.S. type laid from after tank. Ship’s engines 26 revs. 23 HOUR. A.M. 6.10 6.22 6.30 6.50 7.15 7.25 7.55 8.0 9.30 10.45 11.45 11.53 NOON. P.M. 1.0 Steaming Bach to London . S.S. “BUCCANEER.” MONDAY, SEPT. 8th, 1902 (4th DAY OUT) — Contd. Ind. = 1047 revs. = 3 n.m. D.S. type laid from after tank. Ship’s engines 26 revs. Up to cable buoy “H” ind. = 1361 revs. = 3*9 n.m. of D.S. laid from after tank, ship’s engines being worked as required. Lowered cable boat. Shackled on drum rope. Knocked up tumbler, put stoppers on cable, picked up cable buoy “ H,” took turns of D.S, type off drum. Ind. = 1360 revs. =^3-9 n.m. Paid out -070 n.m. main cable 8512 through stoppers. Original length 6-000 n.m. Remaining in after tank 2*030 ,, Total paid out 3-970 „ Commenced to heave up moorings. Mushroom at bows, unshackled and secured on deck. Waterville end on drum, put on stoppers. End banded over to electrician. Fresh wind and sea, fine. Bar. 30-07. Tber. 71° E. Cut cable from after tank. Total D.S. paid out from splice, 3"970 n.m. Distance overground, 3‘8 n.m. Slack 4-5%* Opened ends out for testing. Tests “ O.K.” Commenced joint between Havre — Waterville ends. Joint finished and commenced final splice. Final splice completed. Set about slipping bight. Sounded in 63 fms. Bottom temp. 50°. Sea surface 63° F. Lat. 49° 43'*3 N. Lon. 7° 31' -9 W. Position sounding No. 5 Slipped final splice. Set on to pick up mark buoy “ P,” N 47|° E. Distance 2-7 n.m. STEAMING BACK TO LONDON. Moderate gale and rising sea. Bar. 30 08. Ther. 70° F. Picked up mark buoy “ P.” 24 Steaming Bach to London. S.S. “BUCCANEER.” HOUR. P.M. 1.25 4.0 6.30 8.0 MID. A.M. 2.50 4.0 8.0 11.0 NOON. P.M. 4.0 MONDAY, SEPT. 8th, 1902 (4th DAY OUT) — Contd. Mushroom up. All clear. Set on for Gravesend. Cable- hands clearing up and stowing away gear. Moderate gale and high sea. Ship taking heavy seas forward. Bar. 30-00. Ther. 75° E. Commenced to turn over picked up cable from fore tank to after tank, to get at faulty place. Amount of cable transferred from fore to after tank = 3-41 n.m., then cut ; 10 fms. being cut out at flattened place, therefore leaving 0*38 n.m. in fore tank. Strong wind and high sea, ship pitching heavily and taking water aboard forward. Bar. 29-83. Ther. 76° E. Wind and sea moderating, dull cloudy weather. Bar. 29-75. Ther. 76° E. TUESDAY, SEPTEMBER 9th, 1902 (5th DAY OUT). Lizard’s light abeam. Moderate gale and high sea. Bar, 29-73. Ther. 70° E. Strong wind and overcast with high head sea. Bar. 29-70. Ther. 75° E. Slowed ship off Prawle Point, hoisted number and enquired if any orders. Reply received : “No.” Moderate breeze and hazy weather. Bar. 29-70. Ther. 75° E. Start Point N 61° W, dist. 7-75 n.m. Cable-hands spliced up remaining 0-380 n.m. of No. 8512 in fore tank and transferred it to after tank. ( 2-030 n.m. Length of piece in after tank \ 3-398 ,, ( 0-304 „ Total 5*732 n.m. Similar weather. Bar. 29*70. Ther. 73° E. 25 Moored off Silvertoivn. S.S. “BUCCANEER.” HOUR. P.M. 8.0 9.0 MID. A.M. 2.5 4.0 5.0 6.45 8.0 11.25 NOON. P.M. 0.55 2.30 TUESDAY, SEPT. 9th, 1902 (5th DAY OUT) — Contd. Similar weather, overcast with rain. Bar. 29-75. Ther. 75° E. St. Catherine’s abeam, dist, 4-3 n.m. Light breeze, fine and clear. Bar. 29-87. Ther. 76° F. WEDNESDAY, SEPTEMBER 10th, 1902 (6th DAY OUT). Beachy Head abeam, dist. 5 n.m. Light breeze, fine and clear. Bar. 29-90. Ther. 80° F. Stopped off Dungeness and picked up Pilot (Mr. Howgego). Signalled off Dover. Light breeze, fine but hazy weather. Bar. 29-90. Ther. 76° F. Signalled off Southend. Light breeze, fine and clear. Bar. 29-82. Ther. 71° F. Stopped off Gravesend. Sea Pilot left and river Pilot (Twist) boarded. Moored to buoys off Silvertown and finished with engines. Cable-hands during first part of the day stowing gear and clearing up. Note. — Ship’s Company was paid off at Tidal Basin Shipping Office at noon, September 11th, 1902. 26 COMMERCIAL CABLE COMPANY. HAVRE— WATERVILLE REPAIR, SEPTEMBER, 1902. S.S. “BUCCANEER.” ELECTRICAL REPORT. 27 R " INDEX. PAGE Havre — Waterville Repair (Sept. 1902) 31 Factory Electrical Values at 75° Fahr. after Repair, Sept. 8th, 1902 ... 39 Types and Lengths of Cable Sections after Repair^ Sept. 8th, 1902 ... 40 Tests from Ship towards Waterville and Havre, Sept. 7th, 1902 41 Capacity Test from Ship on Havre side, Sept. 8th, 1902 42 Test from Ship towards Waterville (before making Final Splice) ... 43 Test from Ship towards Havre (before making Final Splice) 43 Factory Electrical Values of Cable on board S.S. “ Buccaneer ” on leaving the Thames, Sept. 5th, 1902 45 Expenditure Table ... 46 Factory Electrical Values of Cable on board S.S. “ Buccaneer ” after completion of Repair, Sept. 10th, 1902 ... 47 K 2 29 ELECTRICAL REPORT. F. W. Robinson, Esq., Engineer in Charge, S.S. *' Buccaneer.” September , 1902. Deae Sie, A fault haying developed in the above cable on the 31st ult., which rendered “duplex” working impracticable, though the section was working well by “simplex,” the “Buccaneer” was chartered the following day by the Commercial Cable Company to effect the repair. On the 3rd inst. a length of 6 - 000 n.m. of Cable Type 8512 Core 70/75 was barged across from Messrs. Siemens Bros.’ Works and transhipped to the “ Buccaneer’s ” after tank. Electrical particulars of the same will be found in the loading table in Appendix. At 2.20 p.m., 5th inst. — Mr. J. Gott, Electrician in Chief to the Commercial Cable Company, Mr. Hensman, Navigating Officer s.s- “ Mackay Bennett,” and Staff having joined ship off Silvertown — the “ Buccaneer ” cast off moorings and proceeded down river. During the run down Channel, Mr. Gott handed me a number of S.G.’s relating to tests taken from Havre and Waterville respectively to localise position of fault. Although taken by different methods — Blavier, Overlap and Kennedy — the results from both ends agreed very closely and from these I placed fault at a little over 315 miles (cable) from BHville, Havre and 195 miles from Waterville. The Channel passage was uneventful, fine weather being experi- enced throughout, and at 7.15 p.m., September 6th, stopped ship to take temperature sounding. 31 Electrical Report. Depth, 41 fathoms. Bottom temp. 58f° F. Surface temp. 59° F. Position [Lat. 49° 45'-0 N. (Lon. 3° 55' -5 W. At 11.5 p.m. same evening, sounded again in 48 fathoms. Bottom temp. 56J° F. Surface temp. 59J° F. Position (Lat. 49° 30'-3 N. (Lon. 4° 45'-0 W. At 10.5 a.m. the next morning (7th inst.), the ship having arrived on cable ground, a mark buoy “P” was lowered in 66 fathoms, and at 10.37 ajn. paid out grapnel for Drag 1, raising same again at 11.30 and ran back to mark buoy to verify position by noon sights. A sounding was taken again at mark buoy. Depth, 64 fathoms. Bottom temp. 50° F. Position (Lat. 49° 42'-l N. (Lon. 7° 28'-8 W. Opportunity was now taken to test the top piece of cable in after tank (L = 6-000 n.m. received from Siemens Bros., 3/9/02), 180 volts being used for D.B. Following are results : ft ft D.R. total 1st* min. — Zinc and Carbon = 479-2 = 2875 per n.m. at sea temp. The grapnel was lowered again at 0.30 p.m. for Drag 2, and at 1.50 p.m. cable was hooked, the Havre end being brought on board and in Testing Room at 2.50 p.m. Havre was called and ship received immediate reply. Signals failing slightly. The end being U) free at Havre a D.R. test taken from ship gave only 2277 total. Having ascertained the electrical conditions of cable on Havre side, the end was handed over to Engineer to veer away in order to pick up on Waterville side, which cable was handed to Testing Room at 3.50 p.m., when ship called shore and received immediate answer. 32 Electrical Report. Tests were taken with the following results : ft ft D.R. total, 1st min., Zinc (30 volts) = 19*9 = 3888 per n.m. at sea temperature. C.R. total (mean Z. and C.), corrected = 3222*94. Length in circuit = 195*158 n.m. (For full tests see Appendix.) Note. — Position agreed upon for “ Buccaneer’s ” cut in (by C.R., etc.) : From Waterville = 195*158 n.m. ,, Havre =315*316 n.m. Length of Section = 510*474 n.m. The tests on Waterville end being satisfactory, the following S.G. was despatched 4.17 p.m. : “ Gott to G.M., V.P., and M.E. Cut in Havre 2 p.m., Sunday. Now buoy Waterville end, and pick up to fault on Havre side. Weather fine.” N.B.— Before sealing and buoying, the cable was put to “ Earth’’ on board, for Waterville to take C.R. 0 } Waterville C.R. to ship (corrected) = 3222. At 5.20 p.m. (7th) buoyed Waterville end (end sealed), and shortly after started picking up on Havre cable towards fault, coiling down in fore tank. At 5.48 spoke Havre, who “free’d” end for ship to test, but on calling again after the interval, five minutes* ship was unable to get shore — continuity having failed. Tests were taken to locate position of fault, which placed same between 50 to 55 from ship, very many tests giving practically the same results. A control test (1 Leclanch6 cell) was applied to cable during the whole time ship was engaged in picking up, and although strict watch was 33 Electrical Beport. kept, no indication whatever — either by change of resistance or unsteadiness — was observed to lead one to suppose that fault had passed inboard. When 3*8 n.m. had been picked up it was decided to cut and test. On this being done the fault was found to be in cable recovered and coiled down in tank, and the cable outboard — towards Havre — O.K. A loop test placed fault at 0*380 n.m. from bottom end in tank, and the fault was subsequently found at this position at a crushed place which had evidently been caused by a steam trawler. From 9.40 to 10.5 p.m. tests were taken from ship on Havre end with the following results : Mean total C.E. (Z. and C.) corrected = 5214. ft ft D.E. (30 volts) 1st min., Zinc, total = 8*928 = 2800 per n.m. at sea temperature. Tests taken O.K. to Havre, the end was given out for splicing on to cable in after tank, the joint and splice being finished at 2 a.m. the following morning — 8th inst.) — joint and all bare core being brass taped and splice compounded over all. The night being extremely dark, it was decided to await daylight before paying out cable to Waterville buoyed end. A D.E. test taken on Havre side after splicing up to cable in . after tank gave : ft ft Total D.E. (30 volts) 1st min., Zinc = 8*928 = 2834 per n.m. at sea temperature. At 5.20 a.m. (8th inst.) ship started paying out cable to buoy on Waterville end, a control test (30 volts) being maintained throughout, and at 6.20 the buoyed end was reached, 3*97 n.m. of Type 8512 being laid between buoys, the end being on board at 7.25 a.m., when Waterville was called and instructed to “free” end for seven minutes, and a D.E. test was taken from ship. 34 Electrical Report. D.R. test towards Wateryille before making final splice : Length in circuit = 195*158 n.m. ft ft D.R. total, 1st min., Z. (30 volts) = 20*565 = 4013 per n.m. at sea temperature. (For full test see Appendix.) Tests having shown cable to be electrically O.K., the following S.G.’s were sent, via Waterville, 8.20 a.m. : “Gott to G.M., Y.P., and M.E. Monday, 8 a.m. Have taken out fault in Havre cable, now about to make final splice — blowing.” 8.27 a.m. “ Robinson to ‘ Silvergray, London.’ Now making final splice, 10 a.m. Monday. Expect to arrive London Wednesday forenoon. All well.” Waterville was now instructed to call Havre at 10.30 a.m., and at 8.30 the end was given out to prepare for final splice. Attention was then given to Havre end and a short insulation test taken from ship gave the following : ft ft D.R. (30 volts) total 1st min. . Zinc = 8*173 = 2546 per n.m. at sea temp (For full test see Appendix.) Everything being satisfactory, ship advised Havre: “We now make final splice — blowing. Call Waterville at 10.30 this morning. G.B.” And at 8.45 a.m. the end was given out to prepare for final splice. Note. — Owing to a strong breeze blowing and sea increasing rapidly, it was deemed advisable to economise time as much as possible, consequently only a short insulation test was taken on each side to ascertain if the D.R. was satisfactory before making the final splice. During the process of making the final splice a temperature sounding was taken. Depth 63 fms. Bottom temperature 50° F. Lat. 49° 40' *3 N. Position Lon. 7° 31'*9 W, 35 Electrical B export. At 11.45 a.m. (8th inst.) the splice was finished — the joint and all bare core being brass taped and the splice compounded ; and at 11.53 a.m. the final splice was slipped and ship set on to pick up mark buoy, which, owing to the bad weather prevailing, was not accomplished until 1.20 p.m., when the “Buccaneer” proceeded to London. During the evening of the same day 3-410 n.m. — length determined by Capacity ( see Appendix ) — of the cable picked up during repairs to this section and coiled in fore tank, were transferred to after tank. The cable was then cut at a flattened place and a length of 10 fms. was also cut off, leaving 0-380 n.m. p.u. cable type 8512 in fore tank. Character of Fault . — Cable flattened for some little distance, evidently the work of a trawler. Of the core stripped on board 20 feet was very badly strained and indented, and in one place the conductor was slightly exposed. The above length (3-410 n.m.) was then tested for D.R. with 180 Q volts and gave a Dielectric Resistance of 2614 per n.m. (1st min. zinc) at tank temp. 63° F. 1 The next day (9th inst.) a splice was made between the top end of cable remaining in after tank, type 8512 (shipped o/b “ Buccaneer.” from Siemens Bros. 3/9/02) (L = 6-000 - 3-970 = 2-030 n.m.) and the bottom end of picked up cable L = 3T40 n.m. transferred on the 8th inst. from the fore tank, 6 fms. being cut off p.u. cable for splice. See Expenditure List. The piece of p.u. cable type 8512 remaining in fore tank having tested O.K. was turned over and spliced up to cable in after tank, a length of 76 fms. being cut off the bottom end, it being too screwy to pay out again. 6 fms. were cut off the 3 mile piece for the splice. See Expenditure List. On arrival at Gravesend about noon on the 10th inst, Mr. Gott received telegraphic advice from the Superintendent at Waterville re 36 Electrical Report. tests on Havre-r- Waterville Cable after repairs, tests being taken at Waterville. The following are the figures received : i) T i (Zinc =3795 0 Insulation | Oarbon=3486 per n.m. aft. ? mins. The “Buccaneer” arrived off Silvertown at 2 p.m. same day, where Messrs. J. Gott and Hensman disembarked. In the Appendix will be found the following tables, etc. : Revised Lengths and Factory Values at 75° F. of the Havre — Waterville Section. Types and Lengths of Cable Sections after repair of the Havre — Waterville Section. Tests from Ship towards Havre and Waterville on recovering cable. Tests from Ship towards Havre and Waterville before making final splice. Distribution of Cable in tanks o/b “ Buccaneer ” and 75° F, values before repairs. Distribution of Cable in tanks o/b “ Buccaneer ” and 75° F. values after repairs. Expenditure Table of new and picked-up cable. I am, dear Sir, Yours faithfully, HERBERT E. CANN, Electrician. 37 Electrical Report. HAVRE— WATERVILLE (1885) CABLE. FACTORY ELECTRICAL VALUES AT 75° FAHR. After Repair by S.S. “Buccaneer,” September 8th, 1902. C.R, at 75° P. Induction Length. N.M. Total. Capacity. Total. Remarks. u mfds. Bleville. 20-682 359-2 6-376 2-892 26-89 1-012 9-228 160-7 2-861 0-407 373 0133 3411 5938 1-054 12*813 223-00 3-970 0-845 7-76 0-276 1-290 21-44 0-460 9-222 1605 2-847 2-406 2209 0-787 7-449 129-67 2-302 “Mirror’s” Splice. 5-000 2-154 86-94 37-05 1-546 0-767 (S.S. “ Buccaneer,” ' j 5.2.02. 41-267 717-58 12-757 3-251 30-12 1-095 13-994 245-3 4-215 1-593 16-47 0-471 4-189 38-88 1-483 3321 57-28 1-026 20-239 354-9 6-095 0445 7-67 0-138 8-545 147-4 2-649 0-260 2-38 0-121 36-875 636-00 11-455 0-770 8-68 . 0-231 6307 108-8 1-959 2-787 46-32 0-995 33-835 586-8 10-515 48-889 855-36 15-783 7-190 3 970 125-47 67-57 2-196 1-318 ! S.S. “Buccaneer,” j 8.9.02. 32-623 569-30 9-964 _ 48-788 , 844-60 1516 1-258 21-77 0-391 2-409 41-77 0-748 2-822 32-72 0926 1-673 1529 0-560 13-080 226-45 4-065 67-201 1177-17 20-347 Watery ill e. 25-294 439-52 7-678 510-624 8719-92 158-732 Underground at Waterv ille. 0-221 3536 00701 39 Electrical Report. HAVRE— WATERVILLE (1885) CABLE. TYPES AND LENGTHS OF CABLE SECTIONS After Eepair by S.S. “ Buccaneer,” September 8th, 1902. Type. Length of Section. N.M. Total Length. N.M. Remarks. Bleville C.H. 8512 0-110 o-iio Beach 0-050 0-160 8517 1-000 1-160 8516 6-000 7-160 5 9 000 16-160 4 4-472 20-632 E.T.C. B 2-892 23-524 “Amber.” 8514 9-228 32-752 ’E.T.C. B 8514 0-407 3411 33T59 36-570 | “ Mirror,” April, ’98. . 8514 12-813 49383 E.T.C. B 0-845 50-228 j “Mirror.” ) 8514 1-290 51-518 8514 9222 60-740 E.T.C. B 2-406 63-146 >“ Mirror,” May, ’98. 8514 7-449 70-595 8514 8514 5-000 2154 75-595 77-749 | “ Buccaneer,” 5.2.02. 8514 41-267 119-016 E.T.C. B 3251 122-267 “ Amber.” 8518 A 13994 136-261 E.T.C. B 1-593 137-854 ) E.T.C. B 4*189 142-043 V“ Chiltern.” 8513 A 3-321 145-364 J 8513 A 20-239 165-603 8513 A 0-445 166-048 ) 8513 A 8 545 174-593 >“Electra.” E.T.C-. B 0-260 174-853 J 8513 A 36-875 211728 8147 0-770 212-498 “ Bittern.” 8513 A 6-307 218-805 8514 8513 A 2-787 0-724 221- 592 222- 316 j- “ Marmion.” 8513 - 82-000 304-316 8512 7-190 311-506 4 8512 3-970 315-476 V“ Buccaneer, 5 ' 8.9.02. 8512 ' 32-623 348-099 8512 48-788 396-887 8512 1-258 398-145 Y 8512 2-409 . 400-554 >“ Mirror.” E.T.C. B 2-822 403376 E.T.C. D 1-673 405-049 ) 8512 8T525 486-574 8513 2-000 488-574 8514 4-000 492-574 8515 9000 501-574 8516 8-000 509-574 8517 rooo 510-574 WATERVILLE Beach 0-050 510-624 Office. Undergrouhd 0-221 510-845 40 Electrical Beport. Tests from Ship toivards Waterville ( 7 / 9 / 02 ). Position: “Buccaneer’s” cut in. (Cable Free at Waterville.) 8.55 to 4.15 p.m. Length in Circuit=195*158 n.m. Dielectric Resistance (30 volts). Mins. Zinc. Lead=nil S.R. 10000. 1 = 32 S.R. 10000 m.p.==l. 2 = 28 ft 3 = 25 1st min. D.R. Total =19‘9. 4 = 24 ft 5 = 23 1st min. D.R. per n.m.= 3888 at sea temperature. ft Constant 20 cells (30 volts) through 10 5 =255 S.R. 400=637‘5 through 1. (Cable Earthed at Waterville.) Conductor Resistance 18 cells=(27 volts). Zinc. Carbon. Leads=0’66. w (i) 3240 3193 Ratio=1000 : 1000. 3237 3198 3232 3199 Temperature Bridge Coils=76° F. 3233 3205 Correct at 60° F. (Platinoid). 3226 3205 3234 3202 w Mean C.R. total corrected for temperature B.C., leads, etc.=3222 94. Note. — The cable being earthed on board, a C.R. test taken from Waterville made 0 ) the resistence=3222 (corrected). Tests from Ship towards Havre (after cutting out fault , 7/9/02). (Cable Free at Havre.) 9.43 to 10.5 p.m. Length in Circuit=311-516 n.m. Dielectric Resistance (30 volts). Aft Mins. Zinc. Lead=nil S.R. 10000. 1 = 70 S.R. 10000 m.p.=l. 2 = 65 ft 3 = 60 1st min. D.R. Total =8'928. 4 = 58 ft 5 = 55 1st min. D.R. per n.m.= 2800 at sea temperature. ft Constant 20 cells through 10 5 =250 S.R. 400=625/0 through 1. 41 Electrical Report. (Cable Earthed at Havre.) Conductor Resistance 18 cells=(27 volts). Zinc. Carbon. Leads=0*66. (i) O) 5473 4960 Ratio=1000 : 1000. 5482 4915 5489 4960 Temperature Bridge Coils=76° F. 5495 4935 Correct at 60° F. (Platinoid). C 0 Mean C.R. total corrected and leads deducted=5214. Capacity Test from Ship on Havre side {after splicing up to Gable in After Tank, 8 / 9 / 02 ). (End Free at Harve.) 1 a.m. Length=317*509 n.m. Kelvin's “Null” Method (20 cells) using K. & V.’s Slides. Standard Condensers=39*205 mfds. (K.). Slide Reading S.R. =7204. Total Capacity of Cable in Circuit= 101*01 mfds. Note.— This includes the Capacity of 6*000 n.m. of Type 8512 spliced up in after tank, which equals 1*992 mfds. Therefore 101*01—1*992=99*018 mfds., which, on comparing this Capacity with the 75° Values, represents a length of 316 236 n.m. in circuit between Ship and Havre, as agaiust 317 509 n.m. (length agreed upon by C.R. Values and taken as correct), a difference of only T273 N.M. Test from Ship on Havre End of Cable {after splicing to Cable in After Tank — 6*000 n.m. Type No. 8512 — and before paying -out to Waterville Buoy, 8 / 9 / 02 ). (End Free at Havre.) Length in Circuit=311*516 n.m. + 6'000 n.m.— 0*007 n.m. (spliced)=317*509 n.m. Dielectric Resistance (30 volts). . Mins. Zinc. Lead=nil S.R. 10000. 1 = 70 S.R. 10000 m.p.=l. 2 = 66 ft 3 = 63 1st min. D.R. Total = =8*928. 4 = 62 ft 5 = 59 1st min. D.R. per N.M.= =2834 at sea temperature. ft Constant 30 volts through 10 5 =250 S.R. 400=625 through 1. 42 Electrical Report. Test from Ship towards Waterville ( before making Final Splice). (End Free at Waterville.) Dielectric Resistance (30 volts). Length in Circuit=195-158 n.m. Mins. Zinc. Lead=nil S.R. 10000. 1 = 31 S.R. 10000 m.p.=l. 2 = 28 O 3 = 25 1st min. D.R. Total =20‘565 4 =?= 25 ft 5 = 23 1st min. D.R. per n.m.= 4013 at sea temperature. ft Constant 20 cells through 10 5 =255 S.R. 400=637*5 through 1. Test from Ship towards Havre ( before making Final Splice). (End Free at Havre.) Dielectric Resistance (30 volts). Length in Circuit=31T506 n.m. Mins. Zinc. Lead=nil S.R. 10000. 1 = 78 S.R. 10000 m.p.=l. 2 = 74 ft 3 = 72 1st min. D.R. Total =8"173. 4 =' 71 ft 5 = 69 1st min. D.R. per n.m.= 2546 at sea temperature. ft Constant 20 cells through 10 5 =255 S.R. 400=637’5 through 1. Test on picked up Gable Type 8512, transferred from Fore to After Tank (8/9/02). Length=3*41 n.m. (by capacity). Capacity by Kelvin’s Null Method (30 volts) using K. & V.’s Slides. Standard Condenser=0*9624 mfds. Slide Reading =5176. 5176 X=0-9624 10000—5176=1-0326 mfds. Total Capacity. Note. — The I.C. per n.m. of this section by 75 values=0‘3031 mfds., therefore 10326 -f- 0-3031=3-41 n.m. length of piece transferred. Dielectric Resistance 120 cells=(180 volts). Mins. Zinc. Lead=nil S.R. 10000. 1 = 5 to 6 S.R.=10000. Readings approximate only, ship plunging heavily. 2 = 4 to 5 ft ft 3 = 4 D.R. Total (1st min. Z.)=766 7=2614 per N.M. at tank temperature 63° F. Constant 120 cells through 10 5 =230 S.R. 60. 43 s ' COMMERCIAL CABLL COMPANY’S CHARTED. Havre — Waterville 1885 Repairs. FACTORY ELECTRICAL VALUES AT 75° FAHR. OF CABLE ON BOARD S.S. “BUCCANEER,” On Leaving the Thames, September 5th, 1902. No. Length in N.M. O.R. at 75° F. Capacity. D.R. at 76° F. Type. of Remarks. Wire. Cable. Core. Total per N.M. Total per N.M. Total per N.M. CJ mf ds. ft Single Core AFTER TANK. 70/75 8512 6-000 102-12 17-02 1-992 0-332 96'67 580 Received from Siemens Bros., 3.9.02. 8514 0-915 15-738 17-2 0-3257 0-356 417-5 382 1 • 2-992 49-667 16-6 1-0711 0-358 100-9 302 1 t 3 907 66-405 16-74 1-3968 0-3575 81-26 317 ' FORE TANK. * Twin No. 1 14-720 13T3 0-3704 03304 2132 2390 Core 8553 1-1085 1-1210 No. 2 14-730 13T4 0-3689 0-3291 2618 2935 Plain 0-718 13-29 0-0162 0-2993 1 0-053 0-054 8552 Rib 0-716 1326 0-0159 0-2950 _ Piece 3 2 Plain 1 3-265 13-29 0-0735 0-2993 — — - “ Buccaneer,” 30.7.02. A 0243 0-2457 Piece 2 Rib 3-258 13-26 0-0725 0-2950 _ 2 Plain 36-389 13-29 0-3196 0-2993 — — “ Buccaneer,” 30.7.02. 2-708 2-738 Piece 1 Rib 2 36-305 13-26 0-8078 0-2950 - ' - ; Plain 0-6645 13-29 0-0151 0-2993 _ “ Buccaneer,” >• 31.7.02. 0050 0-0103 Piece 4 Rib 0-6710 13-26 0-0149 0-2950 _ 2 Above Plain 41-037 13-29 0-9244 0-2993 4 pieces spliced 3-054 3-089 up Rib 40-950 13-26 0-9111 0-2950 45 Electrical Report. EXPENDITURE TABLE. New Cable. Siemens’ 8512. Received from Messrs. Siemens Bros, off Telegraph Works, Silvertown, 8.9.02 N.M. 6-000 Laid in Havre — Water ville Section, 8.9.02 Remaining on board in “Buccaneer’s” After Tank after completion of repairs Total == 6-000 Cable Recovered during Repairs. Total Cable picked up, Type 8512 Transferred to After Tank and spliced up 3‘410 — 0'012 (2 splices) Transferred to After Tank and spliced up Cut off, flattened place, position of fault *Cut off first end picked up— screwy Cut off Splice, etc. Total = 3-800 Cable cut out of Havre — Waterville Section during Repairs. N.M. Picked up and coiled in Fore Tank ... = 3"800 Cut off for splices and damaged places ... = 0"020 Total = 3-820 * This Cable was stripped on the 24th inst. and the core forwarded to Mr. Gott. 46 COMMERCIAL CABLE COMPANY’S CHARTER. FACTORY ELECTRICAL VALUES AT 75° FAHR. OF CABLE ON BOARD S.S. “BUCCANEER,” On heb Retubn to Silvertown Works, Septembeb 10th, 1902, after Completion of Havre — Wateeville Repairs. Length in N.M. C.R. at 75° P. Capacity. D.R. at 75° F.- No. of Remarks. Wire. Cable. Core. Total per N.M. Total per N.M. Total per N.M. Single Core 70/75 AFTER TANK. 8512 * 0-304 5-305 17-451 0-0929 •3051 — — Picked up during Repairs, 8.9.02. „ * 3-398 59-298 17-451 1-0380 •3054 _ “ Buccaneer,” 10.9.02. ” 2-030 34-551 17-02 0-6740 •332 235-7 580 “ Buccaneer,” 9.9.02. 5-732 99-154 17-30 1-8049 •3149 285-7 580 8514 0-915 15-738 17-2 0-3257 0-356 417-5 382 f Siemens’ Splice. ” 2-992 49-667 16.6 1-0711 0-358 100-9 302 ) 3-907 65-405 16-74 1-3968 0-3575 81-2 317-5 FORE TANK. Twin Core 8553 No. 1 1-1085 1-1210 14-720 13-13 0-3704 •3304 2132 2390 No. 2 14-730 13-14 0-3689 •3291 2618 2935 Pin in 0-718 13-29 0-0162 •2993 1 0-053 0-054 8552 Rib 0-716 13-26 0-0159 •2950 Piece 3 2 [ “(Buccaneer,” Plain 3-265 13-29 0-0735 •2993 — — r 30.7.02. 1 0-243 0-2457 Piece 2 Rib 2 3-258 13-26 0-0725 •2950 - — \ Plain 36-389 13-29 0-8196 •2993 L “Buccaneer,” 1 2-708 2-738 30.7.02. Piece 1 Rib 2 36-305 13-26 0-8078 •2950 — — J Plain 0-6645 13-29 0-0151 •2993 1 0-050 0-0506 . “Buccaneer,” Piece 4 Rib 1 0-6710 13-26 0-0149 •2950 — — 31.7.02. 2 * The above 4 pieces (3, 2, 1, 4 of Type 8552) as spliced up. 8552 Twin Plain 3-054 3-089 41-037 13-29 0-9244 •2993 - - Core Rib 40-950 13-26 0.9111 •2950 — — * Picked up during Repairs to Weston — Waterville (1885) Cable, 25th and 26th July, 1902. 47 V \ Ibavre— WatervtUe Cable AND Watennlle— Canso (1884) Cable IRepalrs j£ypebltlcm. JR- ZED 3? .A. I JR S TO THE Ibavre— Watervtlle Cable (Western ant> Eastern), AND TOatervflle— Canso (1884) Cable. S.S. “BUCCANEER,” JULY, 1903. 3 T GENERAL INDEX. Ibavre— Waterville Cable (Western anb Eastern) anb Waterville— Canso (1884) Cable IRepatrs Espebltton, Julp, 1903. S.S. “ BUCCANEER.’ PAGE GENERAL REPORT 9 List of Staff, Officers, Cable Hands and Crew ... ... ... ... 17 Mechanical Description of Cable ... ... ... ... ... ... 21 Distribution of Cable on Leaving Silvertown 24 Distribution of Weight in Ship on Leaving Gravesend ... ... ... 25 Drum Co-Efficients 26 Steaming Down River from Silvertown 29 On Cableground 31 Grappling, etc 33 Finished Splice ... 40 At Waterville 41 Expenditure Table 42 Diagram Showing Operations of Havre — Waterville Western Repair ... 43 Table Showing Cable in Ship after Havre — Waterville Western Repair ... 44 Steaming to Valencia ... ... ... ... ... ... ... ... 45 Table Showing Cable in Ship on Leaving Valencia for Waterville — Canso (1884) Repair 49 Steaming to and on Cableground 50 Grappling, etc ... ... 53 Returned to Valencia ... ... ... ... ... ... ... ... 58 Set on for Cableground 60 Grappling, etc 61 Finished Final Splice : 64 Cable Picked Up and Expended ... ... ... ... ... ... 65 Diagram Showing Operations of Waterville — Canso (1884) Repair ... 66 Table Showing Cable in Ship after Waterville — Canso (1884) Repair ... 67 Steaming to Portland 68 Steaming to Cableground off Barfleur 73 Table Showing Cable in Ship on Leaving Portland for Havre — Waterville Eastern Repair 74 On Cableground, Grappling, etc. 75 Finished Final Splice 79 Steaming to London ... ... ... ... ... ... ... ... 80 Cable Picked Up and Expended ... ... ... ... ... ... 81 Diagram Showing Operations of Havre — Waterville Eastern Repair ... 82 At London ... ... ... ... ... ... ... 83 Distribution of Cable and Weight in Ship on Arrival off Works ... 84 Index to Electrical Reports ... ... ... ... ... ... ... 87 ELECTRICAL REPORTS 91 5 GENERAL REPORT. GENERAL REPORT. M. H. Gray, Esq., Silvertown. July 31s£, 1903. Dear Sir, We left Silvertown on Wednesday, July 1st, 8 p.m., Mr. Gott, representing the Commercial Cable Company, having joined the ship there. There being two faults in the Harve-Waterville section, Mr. Gott instructed us to take out the Western fault first — about 60 n.m, west of Scilly. We arrived in position on Friday, 3rd inst., and on the second drag lifted the cable, which was very taut, and parted at a strain of 50 — 60 cwts. On the Saturday and Sunday we got both ends and put through Monday morning, the Final Splice being in Lat. 49° 47'-4 N, Lon. 7° 59'-2 W— 68 fms. f.s. The fault was evidently caused by damage by trawler, and while we were on the cable ground there were several working around us. The original intention was, after taking out this fault, to go to the second fault, off Cape Barfleur, but Mr. Gott received information that there was a fault in the ’84 Northern Canso Cable, about 50 n.m. from Waterville, and instructed us to proceed there at once. We arrived at Waterville on the morning of the 7th, and took in some provisions there. As the South American Cable, No. 2147 A and 2147, which we were to use on this repair, was at the bottom of after tank and we were unable to get a barge at Waterville to facilitate the turning over, we proceeded to Valencia, and obtaining a hulk there, finished the transferring on the Thursday and left for cable ground about 4 p.m. 9 General Report. The position of fault was given as Lat. 51° 41'*3 N, Lon. 11° 28'*2 W, about 2| n.m. south of ’74 Anglo Cable and 2J n.m. north of ’94 C. C. Co. Cable and 3J n.m. from where the ’84 cable crosses the Anglo. On 10th and llth inst. the weather being thick and foggy we were unable to obtain sights to verify position. On the 12th and 13th, thirteen drags were made without success, and on the morning of the 14th as strong S.W. gale and rising sea rendered it unfit for work, we ran into Valencia. Here we heard that the ’84 cable, on which we were working, had parted at 10.18 a.m. on Monday, this led us to believe that we had run through it on Drag No. 7 — the westermost one. While in Valencia we took out the faults in the C. C. Co. cable No. 8514. On Thursday, 16th inst., as weather was moderating, we proceeded to Cable Ground, leaving Valencia at 9.20 a.m., and getting both ends in successive drags, put the cable through by 7 p.m. on Friday, 17th, in Lat. 51° 42 r *5 N, Lon. 11° 34'*9 W, 219 fms. The fault, which so far has not been exactly located, as it sealed up on coming inboard, is in a 1178 n.m. piece, now on board “ Buccaneer,” and is apparently not a mechanical one. The nature of the bottom was hard, no specimen obtained from soundings, but large flint pebbles were brought up jammed in prongs of grapnel and on mushroom. 3*673 n.m. S.A. No. 2174 A was expended on this repair. I may mention that I heard from the Anglo Co. at Valencia that the “Britannia” last April reported trawlers working in the vicinity of this repair, in 150 — 200 fms., but we did not see any. After landing Pilot O’Neill off Waterville we set on for Portland, and taking in there 100 tons of coal and provisions, left on Monday, 20th, for the Eastern Repair of Havre — Waterville Cable, about 10 n.m. north of Cape Barfleur, arriving on the ground the same evening, and completed and put through at 1.15 p.m. on Wednes- day, 22nd inst, in Lat. 49° 52'*9 N, Lon. 1° 21'*9 W — 40 fms. The 10 General Report. fault proved to be in the original cable on the eastward side of “ John Pender’s” splice 16.2.02. The old cable was in very bad condition, badly corroded, core exposed in parts, and the broken end brought in had only been holding by four wires, the rest being corroded to needle points. The nature of the bottom here was hard, pieces of broken granite being brought up jammed in grapnel prongs. The S.S. “Buccaneer” arrived off Works, all well, at 10 a.m. on Thursday, 23rd, and hands were paid off on Friday noon. I will hand you the Engineering Log and Electrical Log in the course of a few days. % Yours faithfully, F. C. CRAWFORD. 11 u HAVRE— WATERVILLE CABLE WESTERN REPAIR. S.S. “BUCCANEER.” JULY, 1903. 13 u 2 . \ ' LIST OF STAFF, OFFICERS, CABLE HANDS AND CREW. S.S. “BUCCANEER.” 15 S.S. “BUCCANEER.” LIST OF STAFF, OFFICERS, CABLE HANDS AND Mr. F. C. Crawford ,, H. E. Cann ... ,, S. E. Marsham „ E. H. Walker 1 . Mr. B. C. Combe 2. » ,, J. S. Roberts 3. ,, Y. Jones 4. „ A. Clunie 5. W. Mackenzie 6. J. Kelly 7. C. Collins 11. 4 Quartermasters. 17. 6 Able Seamen. 18. Mr. A. White 19. ,, W. Macfarlane 20. ,, J. W. Cadman 21. „ R. Hall 22. J. Maguire 23. A. Gooch ... 29. 6 Firemen. 33. 4 Trimmers. 34. Mr. A. Patrick ... 35. B. Dold 36. W. Parsons 37. A. Golding 38. J. Rouan ... 40. 2 Assistant Stewards. 41. Engineers’ Steward. 42. 1 Scullion. 43. 2nd and 3rd Class Cater CREW. Engineer in Charge. Electrician. Assistant Electrician. Accountant. Captain. Chief Officer. 2nd „ Aux. 2nd ,, Carpenter. Boatswain. Boatswain’s Mate. Chief Engineer. 2nd 3rd 4th Donkeyman. Greaser and Electric Light Driver. Chief Steward. 2nd Steward and Storekeeper. Chief Cook and Baker. 2nd Cook and Butcher. Pantryman. 17 S.S. “ BUCCANEER.” CABLE HANDS. 1. W. Tillyer Foreman. 2. B. Butcher Leading Hand. 3. C. Cakebread Cable Hand. 4. R. Duncan • • • 99 99 5. A. Smith ... • • • 99 99 6. H. Marshall • • • 99 9 9 7. A. Harris ... • • 9 9 9 9 8.' W. Mack • • • 9 9 99 9. H. Livingstone Fitter. * 10. A. E. Newton Fitter’s Mate. 11. W. Billington Jointer. Representative of the Commercial Cable Company : Mr. J. Gott. SUMMARY. Staff . 4 Cable Hands ... ... ... ... ... 11 Officers and Crew ... ... ... ... 43 Visitor ... ... ... ... ... ••• 1 Total on board leaving London ... ... 59 18 MECHANICAL DESCRIPTION OF CABLE. S.S. “BUCCANEER.” 19 S.S. “ BUCCANEER.” MECHANICAL DESCRIPTION OF CABLE. Siemens’ Main Cable, their Factory No. 8512 (Single Core). Conductor : — Strand of 7 copper wires each "-023 dia., weighing 70 lbs. per n.m. Dielectric: — Gutta percha one coat to "-205 dia., weighing 75 lbs. per n.m. Serving : — Tanned jute yarn. Sheathing : — 10 B.B.G.I. wires "T43 dia. Outer Serving : — Two coats prepared jute yarn alternating with three coats of compound. Ex. diameter = 2"-875. Weight in air, dry = 2-138 tons per n.m. „ ,, wet = 2*175 „ „ ,, in sea water = 1*433 ,, ,, Siemens’ L.I. Cable, their Factory No. 8553 (Twin Core). Conductor : — Solid plain copper wire, weighing 90 lbs. per n.m. Dielectric : — Gutta percha, weighing 85 lbs. per n.m. Two Cores as above, one marked with “Bib,” the other “ Plain,” laid up, wormed and served with tanned jute yarn. Sheathing : — 15 G. Homo, wires, No. 9 L.S.G. = "T44 dia. when galvanized. Outer Serving: — Two coats jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = 1"* 103. Weight in air, dry = 3*293 tons per n.m. ,, ,, wet = 3*420 ,, ,, ,, in sea water = 2*241 ,, ,, 21 S.S. “ BUCCANEER.” Siemens’ L.I. Cable, their Factory No. 8513 (Single Core). Conductor : — Strand of 7 copper wires each "-023 dia., weighing 70 lbs. per n.m. Dielectric : — Gutta percha to "*205 dia., weighing 75 lbs. per n.m. Serving : — Tanned jute yarn. Sheathing : — 10 B.B.G.I. wires "-180 dia. when galvanized. Outer Serving : — Two coats jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = 1"-160. Weight in air, dry — 3’4 tons per n.m. Siemens’ E.I. Cable, their Factory No. 8514 (Single Core). Core and serving same as in No. 8513. Sheathing : — 10 B.B.G.I. wires "‘238 dia. when galvanized. Outer Serving : — Two coats jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = l"-393. Weight in air, dry = 5’437 tons per n.m. ,, ,, wet=5’526 ,, ,, „ in sea water = 3*873 ,, ,, Siemens’ Main Cable, their Factory No. 8552 (Twin Core). Conductor : — Solid plain copper wire, weighing 90 lbs. per n.m. Dielectric : — Gutta percha, weighing 85 lbs. per n.m. Two Cores as above, one marked with “Rib,” the other “ Plain, ” laid up, wormed and served with tanned jute yarn. Sheathing : — 17 G. Homo, wires "• 124 dia. when galvanized. Outer Serving : — Two coats jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = l"-078. Weight in air, dry = 2-838 tons per n.m. ,, ,, wet = 2*900 ,, ,, ,, in sea water = 1-798 ,, ,, 22 S.S. “BUCCANEER. Light Deep Sea Cable, No. 2147. Conductor : — Strand of 7 copper wires each "*0415 dia., weighing 225 lbs. per n.m. Dielectric : — Gutta percha three coats to "*355 dia., weighing 225 lbs. per n.m. Serving ; — Tanned jute yarn. Sheathing : — 16 galvanized steel wires "’0918 dia. when gal- vanized. Outer Serving : — 20 hemp cords prepared in compound, alter- nating with two coats of compound. Ex. diameter = 1"*039. Weight in air, dry = 2T45 tons per n.m. ,, wet = 2T6 ,, in sea water = 1-12 ,, ,, Light Deep Sea Cable, No. 2147a. Same as the above, with cords stripped off and two com- pounds and tape on instead. Intermediate Cable, No. 02664. Conductor : — Strand of 7 copper wires each "*032 dia., weighing 130 lbs. per n.m. Dielectric : — Gutta percha three coats to "*355 dia., weighing 130 lbs per n.m. Core brass taped. Serving : — Tanned jute yarn. Sheathing : — 10 B.B.G.T. wires "*203 dia. when galvanized. Wires pickled in compound. Outer Serving : — Two laps of tape alternating with two coats of compound. Ex. diameter = 1"*039. Weight in air, dry = 3*83 tons per n.m. 23 HAVRE— WATERVILLE CABLE WESTERN REPAIR. S.S. “BUCCANEER,” JULY, 1903. co o h-q p 1-5 !zr & o EH P3 S h— I m £ t—i o o 00 eo C- I-H C5 O i> j> (old)... 4-250 346-590 2-5398169 2-927 L.I. 8558 twin core 3-465 347-886 2-5414375 2-916 Int. 8552 „ 3-387 348016 2-5415988 2-915 L.I. 8518 single core 3-650 347-580 2-5410551 2-919 L.D.S. 2147A „ 2-953 348-737 2-5424979 2-909 „ 2147 „ 3-280 348-193 2-5418204 2-913 Int. 02664 „ 3-264 348-220 2-5418535 2-912 26 HAVRE— WATERVILLE CABLE WESTERN REPAIR. STEAMING DOWN RIVER FROM SILVERTOWN. S.S. “BUCCANEER,’ 27 v STEAMING DOWN RIVER FROM SILVERTOWN. S.S. “ BUCCANEER.” HOUR. P.M. 6.30 6.35 6.50 7.25 8.8 9.28 11.0 11.35 MID. WEDNESDAY, JULY 1st (1st DAY OUT). Mr. Gott, of Commercial Cable Company, came on board with Mr. Crawford. Mr. M. H. Gray came on board. Commenced unmooring ship. Mr. M. H. Gray left ship. Cast off moorings and proceeded down river. Pilot Twist in charge. Slowed ship off Gravesend. Pilot Twist left and Pilot Lygo boarded. Set on full speed ahead. Passed Nore Light Vessel. ,, Mouse „ Light SE breeze. Fine weather. Hazy horizon. Bar. 30-10. Ther. 75° F. A M. 0.30 1.15 2.15 3.10 3.12 1.0 5.15 5.17 6.0 THURSDAY,' JULY 2nd (2nd DAY OUT). Black Deep Light Ship abeam. Tongue Elbow Buoy abeam. Gull Light Ship „ Half speed. Adjusting compasses. South Goodwin Light Ship abeam. Light ESE breeze. Smooth sea. Fine and clear. Bar. 30-20. Ther. 71° F. Pilot Lygo left ship off Dover. Full speed ahead. Dungeness Light abeam. 29 v 2 Steaming to Cableground off Scilly Islands. S.S. “BUCCANEER.” HOUR. A.M. 8.0 9.20 10.0 NCON P.M. 3.30 4.0 8.0 10.20 MID. A.M. 0.8 2.40 4.0 6.23 THURSDAY, JULY 2nd (2nd DAY OUT) — Contd. Light ESE breeze. Eine weather. Hazy horizon. Bar. 30*29. Ther. 64° F. Royal Sovereign Light Vessel abeam. Beachy Head Lighthouse abeam. Light variable breeze. Eine weather. Hazy horizon. Bar. 30*24. Ther. 67° E. Distance run from Gravesend = 140 n.m. STEAMING TO CABLEGROUND OFF SCILLY ISLANDS. St. Catherine’s Point abeam. Light ESE breeze and smooth sea. Hazy. Bar. 30*02. Wind hauling to westward. Overcast and fine. Bar. 30*02. Observed Start Point Light. Fresh WNW breeze. Clear weather. Bar. 30*13. Ther. 70° F. Note. — Mr. Gott informed Mr. Crawford to-day that the first fault in the Havre — Waterville cable was approx- imately 19 n.m. west from “ Buccaneer’s ” final splice on FRIDAY, JULY 3rd (3rd DAY OUT). Start Light abeam. Eddy stone ,, Fresh W breeze. Fine and clear. Moderate W’ly swell. Bar. 30*25. Ther. 62° F. Observed Lizard Lights. 30 On Cableground. S.S. “BUCCANEER.” H0UK. A.M. 8.0 10.15- 11.18 NOON P.M. 4.0 5.0 5.5 5.20 5.30 5.40 5.55 FRIDAY, JULY 3rd (3rd DAY OUT). — Contd. Moderate WNW breeze, and fine, with head swell. Bar. 30-30. Ther. 66° F. St. Agnes abeam. Bishop’s Rock Lighthouse abeam. Fresh WNW breeze. Fine weather. Head swell Bar. 30-30. Ther. 66° F. Distance run since noon yesterday = 255 n.m. Position Lat. 49° 49' N. Lon. 6° 39' W. Moderate WNW breeze. Fine and clear. Bar. 30‘05. Ther. 63° F. Stopped ship and sounded No. 1. 70 fms. Fine sand. •p . , , o Pi ^ , =° ^ d cS O Hi Hi *80 L'f P«*>1-ooh ^sa^g fcO to a o-h a ^ o o Ol ©oo s o ..2 ®6a c^fcaQ £\^ o'« -« Q o © © 3 pP£o a Sz5 ~ CO O ^ CO o o 05 CO t- CO O *a ° r. a O P^PmCLiH 43 w HAVRE — WATERVILLE CABLE WESTERN REPAIR. S.S. “BUCCANEER,” July, 1903. M Ph P-1 tf PP Eh Ph <3 Ph w CQ £5 t-H £ o W C Cl PP i-P PP <1 EH P3 <1 P ai N.M. TONS.* After Tank = 25-598=58-980 Anchored off Water mile and Valencia. S.S. “ BUCCANEER.” HOUR. A.M. 8.45 8.45 10.5 11.25 11.55 NOON P.M. 0.50 1.40 2.35 4.0 4.30 6.45 8.0 8.10 9.30 MID. A.M. 2. 30 ANCHORED OFF WATERYILLE AND VALENCIA. TUESDAY, JULY 7th (7th DAY OUT)— Contd. Messrs. Gott and Cann left for shore. Opened out ends of L.D.S., No. 2147 A , S.A., 3-673 n.m., and No. 2147, S.A., 10-978 n.m., for splice in after tank. Commenced joint, cut 9 fms. off 10-978, piece thus reducing this length to 10-969 n.m. Finished joint. Commenced splice. Light variable breeze. Overcast and misty. Bar. 30-30. Ther. 66° F. Temp. 70° F. dry, 61° F. wet. Messrs. Gott and Cann remained ashore to test and will join ship at Valencia this afternoon. Hove up anchor and set on for Valencia. Finished splice. Mod. W’ly breeze. Misty. Bar. 30-44. Ther. 64° F. Temp. 66° F. dry, 64° F. wet. Anchored off Valencia. Messrs. Gott, Wilmot (Supt. at Waterville), and Cann came on board. Similar wind and weather. Bar. 30-42. Ther. 64° F. Temp. 65° F. dry, 63° F. wet. Hulk “Dannebrog” came alongside for receiving cable on board temporarily. Commenced transferring cable from after tank to hulk in order to get the S.A. cable on top, 10 labourers from shore assisting cable hands to do this. Light airs overcast. Drizzling rain. Bar. 30-40. Ther. 64° F. Temp. 64° F. dry, 63° F. wet. WEDNESDAY, JULY 8th (8th DAY OUT). Finished transferring Commercial Cable Co.’s cable from after tank to hulk. w 2 45 Anchored off Watervillc and Valencia. S.S. “BUCCANEER.” HOUR. A.M'. ! 4.0 5.0 8.0 NOON P.M. 2.0 4.0 5.15 5.45 6.50 8.0 MID. A.M. 4.0 8.0 j WEDNESDAY, JULY 8th (8th DAY OUT) — Contd. Light NW breeze. Overcast. Fine rain. Bar. 30 38. Ther. 64° F. Temp. 60° F. dry, 59° F. wet. Commenced transferring S.A. cable in after tank to fore tank. Note . — At 10.45 a.m. the picking up gear was put in use for transferring. Light variable breeze. Thick mist. Bar. 30-50. Ther. 65° F. Temp. 62° F. dry, 60° F. wet. Light NW breeze. Misty weather. Bright intervals. Bar. 30-54. Ther. 65° F. Temp. 63° F. dry, 61° F. wet. Messrs. Gott, Wilmot and Crawford left for shore. Light NW breeze, with passing mist. Bar. 30 51. Ther. 68° F. Temp. 62° F. dry, 62° F. wet. All S.A. cable coiled in fore tank. Commenced transferring Commercial Cable Co.’s cable back from hulk to after tank. Messrs. Gott and Crawford returned to ship. Light variable breeze. Overcast, misty weather. Bar. 30-50. Ther. 67° F. Temp. 63° F. dry, 60° F. wet. Similar wind and weather. Bar. 30 50. Ther. 66° F. Temp. 62° F. dry, 60° F. wet. Finished transferring Commercial Cable Co.’s cable back into after tank, and commenced turning back S.A. cable from fore to after tank. THURSDAY, JULY 9th (9th DAY OUT). Light SE breeze. Overcast and misty. Bar. 30-43. Ther. 62° F. Temp. 62° F. dry, 59° F. wet. Similar wind and weather. Bar. 30 40. Ther. 62° F. Temp. 62° F. dry, 59° F. wet. Similar wind and weather. Bar. 30*45. Ther. 63° F. Temp. 62° F. dry, 59° F. wet. 46 NOON WATERVILLE— CANSO (1884) CABLE. S.S. “BUCCANEER.” ... . WATERVILLE — CAN SO REPAIR. S.S. “BUCCANEER,” JULY, 1903. tf hH <1 PH S W EH P3 O PH o 53 s <1 h— I <1 PQ hQ £ o PH i— i W CQ 5zi S PQ <1 o O 53 i— i £ O W CQ PQ PQ <1 EH 49 . o -h tfi 00 Id i5 O N 2 oo iH H lO (N »■ CS )) >> In position to grapple. Lowered as before. Drag No. 12. Ind. = 100 revs. = 300 fms. of rope paid out. Commenced drag. Engines used as required. No strain. No strain. Commenced picking up. Grapnel at bows, no cable. Lowered centipede with usual chain and rope. 57 On Cableground. S.S. “BUCCANEER/’ HOUR P.M. 11.50 , MID. A.M. 2.0 4.0 5.20 I 5.40 | 6.0 8.0 9.40 j NOON | P.M. 2.20 4.0 I 5.40 8.0 MID. A.M. 4.0 MONDAY, JULY 13th (13th DAY OUT) — Contcl. Drag No. 13. Ind. = 100 revs. = 300 fms. of rope paid out. Commenced drag. Engines used as required. No strain. Eresh SW wind. Increasing sea. TUESDAY, JULY 14th (14th DAY OUT). No strain. Bar. 30T2. Ther. 66° E. Temp. 72° E. dry, 61° F. wet No strain. Strong SW wind and sea increasing. No Strain. Commenced to pick up. Grapnel at bows. Weather too bad to continue grappling. Mod. SW gale. High sea. Thick. Raining. Bar. 29 91. Ther. 63° F. Temp. 60° E. dry, 57° F. wet. Set on for Valencia. Wind and sea increasing. Similar conditions. Bar. 29-88. Ther. 65° E. Temp. 69° F. dry, 59° F. wet. Anchored in Valencia Harbour. Strong SW wind and raining. Bar. 29-84. Ther. 67° F. Temp. 70° F. dry, 60° F. wet. Mr. Crawford went ashore to go to the Anglo-American Telegraph Co.’s Station. Mr. Crawford returned to ship. Similar wind and weather. Bar. 29*82. Ther. 67° F. Temp. 70° F. dry, 60° F. wet. Mr. T. Wilmot left ship for Waterville, his home. Strong SW breeze, and squally, heavy rain at times. Bar. 29-70. Ther. 67° F. Temp. 72° F. dry, 62° F. wet. WEDNESDAY, JULY 15th (15th DAY OUT). Mod. SW gale, with hard squalls of wind and rain. Bar. 29 - 70. Ther. 66° F. Temp. 68° F. dry, 60° F. wet. 58 Order of Cable now in Fore Tank and Hold . S.S. “ BUCCANEER.” HOUR. A.M. 5.0 8.0 NOON. P.M. 3.0 4.0 5.0 7.0 8.0 MID. WEDNESDAY, JULY 15th (15th DAY OUT) — Contd. Commenced turning over cable from fore tank to fore hold in order to cut out a fault in the spliced-up section 1*100 n.m. from the top. Similar wind and weather. Bar. 29*72. Ther. 67° F. Temp. 64° F. dry, 60° F. wet. Strong SW wind and squally, overcast with fine rain. Bar. 29*76. Ther. 67° F. Temp. 71° F. dry, 61° F. wet. Capt. Combe and Mr. Crawford left for shore. Strong SSE wind and squally, with heavy rain. Bar. 29*72. Ther. 66° F. Temp. 69° F. dry, 61° F. wet. Stopped turning over cable and cut 10 fms. out with fault. This fault was at the splice between H.I. 8514 single core 0*380 n.m. and 0*901 n.m., the latter length now being 0*891 n.m. Commenced turning back the cable from fore hold into fore tank. Finished turning back cable for the day. Mod. WNW breeze, cloudy and overcast. Bar. 29*72. Ther. 69° F. Temp. 65° F. dry, 62° F. wet. Similar wind and weather. Bar. 29*72. Ther. 69° F. Temp. 65° F. dry, 62° F. wet. ORDER OF CABLE NOW IN FORE TANK AND HOLD. Fore Hold. Top, Piece “C,” No. 8512, 1 core = 0*894 n.m. Havre — Waterville, 5.7.03. Bot., Piece “B,” No. 8512, 1 core = 0*200 n.m. Havre — Waterville, 5.7.03. Fore Tank. Top, H.I., No. 02664, 1 core = 2*000 n.m. 8514, „ =0*500 „ ) 8513, „ =0*220 „ [ Spliced up. 8514, „ =0*380 „ j Fault cut out here=0‘009 N.M. ;; ;; =1-638 ;; ( s P lioedu p- 59 H.I., L.I., H.I., H.I., H.I., x On Cableground. S.S. “BUCCANEER.” HOUR. A.M. 4.0 7.45 8.0 9.0 9.20 11.10 NOON. P.M. 2.20 2.30 2.35 2.40 x 2.50 2.55 3.15 3.20 THURSDAY, JULY 16th (16th DAY OUT). Calm, cloudy and fine. Resumed turning back cable to fore tank. Bar. 29-60. Ther. 62° F. Temp. 65° F. dry, 62° F. wet. Mr. Marsham left ship and will proceed to London (over- land), acting on instructions received from Mr. M. H. Gray yesterday. Similar wind and weather. Finished turning back cable. Bar, 29-65. Ther. 70° F. Temp. 70° F. dry, 66° F. wet. Capt. Combe and Mr. Crawford returned to ship. Hove up anchor and set on for cableground. Skelligs Lt. Ho. abeam, dist. 1*3 n.m., set course S 81° W. Mod. SW wind, fine and clear. Bar. 29*65. Ther. 70° F. Temp. 71° F. dry, 60° F. wet. Observed Mark Buoy “ K ” with flagstaff and lamps gone, and thought to be out of position. Up to buoy, sent boat to dismantle it. Knocked up tumbler and commenced picking up moorings. Hoisted buoy and boat. ON CABLEGROUND. End of rope (buoy’s moorings) came on board, having broken at kink, thus losing 50 fms. 4x6 rope, 30 fms. £" chain, mushroom 4 cwt. 1 qr. 5 lb. ; also flag “ K,” staff and 2 Dioptric buoy lamps lost off buoy. Set on for Mark Buoy “T.” Observed the lamp was ruined. Up to buoy. Sent boat to put fresh lamp on same. Sounded No. 26 — 162 fms., n. sn. Boat returned and was hoisted up. Set on to place another Mark Buoy in place of Mark Buoy “ K.” Light SW. Cloudy, but clear. Bar. 29-60. Ther. 70° F. Temp. 68° F. dry, 60° F. wet. 60 4.0 On Cabieground. S.S. “BUCCANEER” HOUR. P.M. 4.4 '• 4.20 4.25 4.35 5.20 5.23 5.30 5.50 6.15 6.35 6.45 6.57 7.9 7.15 THURSDAY, JULY 16th (16th DAY OUT). — Contd. Sounded No. 27 — 153 fms., h. n. sn. In position to place Mark Buoy. Commenced paying out moorings. All moorings paid out. Streamed buoy, and let go forward. Buoy's Moorings . — Buoy No. 47, Flag Blue “ B,” 2 Dioptric lamps and hangers, 20 fms. f" chain, 90 fms, 3x4 and 100 fms 4x4 rope, 15 fms. f" chain. Mushroom 4 cwt. Sent boat to put lamps on buoy. Boat returned and was hoisted up. Set on to run distance between buoys. In position to grapple. Lowered centipede with 10 fms. -f" chain and 2-| fms. trail chain, and commenced paying out 4x4 rope. Drag No. 14. Ind. = 100 revs. = 300 fms. of rope paid out. Put rounding on and commenced drag. Engines used as required. Strain rose steadily to 18 cwt. Commenced to pick up. 200 fms. of rope out. Strain = 22 cwt. 100 „ „ „ „ „ -20 „ Grapnel at bows with cable (17 wires and taped). Got drum ropes along and secured to each side of cable. - Cut cable. Hove in enough cable on Waterville (short) end for testing. Commenced testing. Tests showed this to be a short piece. Veered away on short end towards Waterville and picked up on Canso end for testing. Similar wind ahd weather. Bar. 29*57. Ther. 70° F. Temp. 67° F. dry, 61° F. wet. 61 x 2 8.0 On Cableground. S.S. “ BUCCANEER.” HOUR. P.M. 8.5 8.20 8.37 10.37 11.30 MID. A.M. 0.20 1.25 1.30 2.10 2.45 2.50 3.0 3.52 THURSDAY, JULY 16th (16th DAY OUT). — Contd. Took Canso end off drum and took short piece to drum and commenced heaving on board. End off drum. Set indicator = Zero. End of short piece passed off drum. Ind. = 55 revs. = 0157 n.m. —Piece “ G." Note. — Piece “ G ” has several broken wires, which are worn to needle points. Put turns of Canso end on drum and commenced picking up to fault. Ind. = 411 revs. = 1*178 n.m. Picked up cut cable and made fresh tests. ’ Fault supposed to be inboard. Fault found still to be outboard. Resumed picking up to fault. Note. — The above 1*178 n.m. piece has three broken wires, and was not relaid — Piece “ H.” Light SW wind. Overcast. Bar. 29*57. Ther. 70° F. Temp. 70° F. dry, 60° F. wet. FRIDAY, JULY 17th (17th DAY OUT). Ind. = 596 revs. = 1*708 n.m. Picked up on Canso end. Stopped picking up, and made fresh tests. These tests proved cable to be “ O.K.” to Canso. Preparing to pay out again on Canso end to last cut. Commenced paying out to last cut = 0*503 n.m. All cable to cut paid out. Commenced paying out buoy’s moorings attached to end of cable. All moorings paid out. Streamed buoy and let go forward. Buoy's Moorings. — Buoy No. 42, Flag “ N,” 1 lamp and hanger, f" bridle, 20 fms. f" chain, 200 fms. 3x4 rope, 30 fms. f" chain. Mushroom 3 cwt. 1 qr. 7 lb. Sent boat away to put lamp on buoy. Boat returned to ship. Set on for position to grapple Waterville end. In position, lowered as in Drag No. 14. 62 On Cableground. S.S. “BUCCANEER.” HOUR. A.M. 4.0 4.5 4.30 4.48 5.0 5.10 5.21 6.40 8.0 8.30 9.20 10.2 10.30 11.0 11.45 11.55 NOON. FRIDAY, JULY 17th (17th DAY OUT). — Contd. Drag No. 15. Calm and clear. Bar. 29-56. Ther. 69° F. Temp. 65° F. dry, 61° F. wet. Ind. = 100 revs. = 300 fms. of rope paid out. Put rounding on and commenced drag. Engines used as required. Strain rose steadily to 18 cwt. Commenced picking up. Grapnel at bows with cable. Got drum ropes along and secured to both sides of cable. Cut cable. Hove enough Waterville end abaft drum for testing. Commenced testing. Got Waterville “ O.K.” Got up end of S.A. 2147 A cable from after tank for splice with Waterville end, and commenced opening out same. Finished testing to Waterville. Gave ends out. Commenced opening out same. Similar wind and weather. Bar. 29-58. Ther. 71° F. Temp. 68° F. dry, 64° F. wet. Commenced joint. Hove in short piece towards Canso = Piece “ K” = 0 083 n.m. Sounded No. 27 — 156 fms., h. n. sn. Bottom temperature 50° -6 F. Finished joint. Lat. 51° 40' -7 N. Lon. 11° 30' 6 W. 156 fms. Commenced splice. Finished splice. Put engine out of gear. Commenced paying out S.A. cable from after tank to Canso buoyed end. Splice passed off drum. Ind. = Zero. Light variable breeze, fine and clear. Bar. 28-55. Ther. 72° F. Temp. 70° F. dry, 64° F. wet. S3 On Cableground. S.S. “BUCCANEER.” HOUR. P.M. 0.10 0.30 0.45 0.55 1.0 1.8 1.15 1.20 2.5 2.18 2.45 3.32 4.0 5.50 6.0 6.5 7.0 7,10 FRIDAY, JULY 17th (17th DAY OUT). — Gontd. Ind. = 348 revs. = LOO n.m. of rope paid out. No strain. „ 696 „ 200 „ „ 1044 „ 3-00 „ Approaching Canso buoyed end. Lowered boat and sent her with drum rope to dismantle buoy. Put engine in gear. Knocked up tumbler and commenced picking up buoy’s moorings by winch. Hoisted buoy and boat. Ind. = 1184 revs. = 3*394 n.m. of rope paid out. Put stoppers on and took turns of cable off drum. Took buoy’s moorings on Canso end to drum, and resumed picking up on same. Strain rose to 40 cwt. Commenced veering away on Water ville (tank) end accordingly. Canso end abaft drum. Amount of tank end veered away = 0*279 n.m. Commenced testing to Canso. Finished testing to Canso = “ O.K.” Gave out end for opening out for splice. Cut Waterville (tank) end. Gave out Waterville (tank) end, for splice and commenced opening out same for final splice. Commenced joint. Similar wind and weather. Bar. 29*63. Ther. 74° F. Temp. 73° F. dry, 63° F. wet. Finished joint. Commenced splice. Sounded No. 28 — 219 fms., h. n. sn. Bot. temp. 50° F. Finished splice 3 ^.^ yy 1 219 fms. Final splice Commenced veering away on banging ropes. 64 On Cablcground. S.S. “BUCCANEER.” HOUB. P.M. 7.14 FRIDAY, JULY 17th (17th DAY OUT). — Contd. Cut hanging ropes and let go final splice, thus completing the repair to the Waterville — Canso Northern Cable. Set on to pick up Mark Buoys “ B ” and “ T.” No. 8502. 0T57 n.m. 1-178 0083 0008 Cable Picked Up. Piece “G” — Loose end, Drag 14, wires. after getting Canso has several broken “ II ” — Picked up to fault in Canso end, has 3 places with broken wires. “K” — Loose end after getting Water- ville Drag 15. Cut off for splice Waterville end for splice with cable in after tank. 1*426 n.m. = Total cut out of section and in fore tank. Cable Expended, No. 2147a. 3*394 n.m. Paid out by indicator. 0*271 ,, Veered away while picking up Canso end. 0*008 ,, Cut off tank end for splice with Canso end. 3*673 n.m. — Total cable expended on repair from after tank. Note . — The expended cable was cut at a splice between the L.D.S 2147a S.A. 3*672 and „ 2147 „ 10*969. The amount of cable No. 8502 abandoned, as agreed with Mr. Gott, being 1*774 n.m. approximate. 65 WATERVILLE — GAN SO NORTHERN (1884) CABLE REPAIR. CO o 05 rd t- pH ►4. P P P P P < o o p pq w. w. «o ©eo ;L>> PS OO t-* » h3 J ° £ Z-i Ph ^ H E-i . o g (N — ^ Sco ^00 QO 8^0 O*- o • T3 a © £ fl 55 o S ° ^ J O 1-3 . o & . £o a ,*T o,?^ o — t'- 72 rH — I *< r- " . «^ 2 Is 3 Y r PS 66 Cable No. 2147A paid out=3'665 n.m. WATERVILLE— CANSO REPAIR. S.S. il BUCCANEER,” JULY, 1903 cc A O H O r-4 GO F-l © O >0 CO 05 p cc A II II b- •>+1 © II & CD «4-l O Picked-Up Cable in Fore Hold.— Piece “0,” No. 8512, Single Core=0-894 N.M.=r944 tons; and Piece “B,” No. 8512, Single Core=0200 x.H.=0*435 tons. On Cableground and Steaming to Portland. S.S. “BUCCANEER.” HOUR. P.M. 7.35 7.38 7.40 7.55 8.0 8.16 8.20 8.25 8.35 MID. A.M. 4.0 5.0 5.10 8.0 10.0 10.30 NOON. ON CABLEGROUND AND STEAMING TO PORTLAND. FRIDAY, JULY 17th (17th DAY OUT). — Contd. Up to Mark Buoy “ T.” Lowered and sent away boat to dismantle it. Knocked up tumbler, and commenced picking up moorings. Hoisted buoy and boat. All moorings on board. Set on for Mark Buoy “ B.” Light NE breeze. Fine and clear. Bar. 29-63. Ther. 72° F. Temp. 70° F. dry, 66° F. wet. Up to Mark Buoy “ B.” Lowered and sent boat to dismantle it. Knocked up tumbler, and commenced to pick up moorings. Hoisted buoy and boat. All moorings aboard. Set on to land Pilot O’Neill at Horse Island. Light NNE breeze. Fine and clear. Bar. 29-86. Ther. 72° F. Temp. 72° F. dry, 63° F. wet. SATURDAY, JULY 18th (18th DAY OUT). Light NW wind and fine. Bar. 29-65. Ther. 68° F. Temp. 70° F. dry, 61° F. wet. Stopped off Horse Island and landed Pilot O’Neill. Set on full ahead for Portland. Light wind, and fine but cloudy. Smooth sea. Bar. 29-73. Ther. 69° F. Temp. 68° F. dry, 63° F. wet. Slowed for fog. Fog cleared. Full speed. Light wind. Fine and clear. (Lat. 51° 9' 3 N. Position Lon. 9°7'-8W. Bar. 29-80. Ther. 70° F. Temp. 74° F, dry, 64° F. wet, Steaming to Portland. S.S. “BUCCANEER.” HOUR, P.M. 4.0 5.0 MID. A.M. 3.30 4.0 5.43 8.0 9.35 11.25 NOON. P.M. 2.38 4.0 4.12 4.55 5.25 6.0 SATURDAY, JULY 18fch (18th DAY OUT). — Contd. Light WSW breeze. Fine and clear. Smooth sea. Bar. 29*82. Ther. 69° F. Temp. 74° F. dry, 65° F. wet. During the afternoon cable hands transferred Pieces “ G ” and “ K ” to fore hold and Piece “ H ” to after tank ; also the 2-00 n.m. piece of Int. 02664 was transferred to after tank on top of Piece “ H.” Light WSW wind. Fine and clear. Bar. 29-93. Ther. 71° F. Temp. 70° F. dry, 60° F. wet. SUNDAY, JULY 19th (19th DAY OUT). “Wolf” abeam. Light NW wind. Fine weather. Bar. 29-91. Ther. 68° F. Temp. 71° F. dry, 62° F. wet. Signalled number to Lloyd’s Station, Lizard Point. Similar wind and weather. Bar. 29-98. Ther. 66° F. Temp. 67° F. dry, 63° F. wet. Eddystone Lighthouse abeam. Start Point Lighthouse abeam. Similar wind and weather. Bar. 29-99. Ther. 72° F. Temp. 72° F. dry, 72° F. wet. Position Lat. 50° 16' N. Lon. 3° 24'-5 W. Observed Portland Bill. Light SW breeze. Cloudy and overcast. Bar. 29-90. Ther. 67° F. Temp. 64° F. dry, 57° F. wet. Rounded Shambles. Entered harbour. Alongside coal hulk. -n u* • , ( Fore = 10' 8" Draught on arrival | Aft==12 , g „ Messrs. Gott and Crawford, with Capt. Combe, left for shore. 69 Arrived at Portland Harbour. S.S. “ BUCCANEEB.” HOUR. P.M. 8.0 9.0 11.50 MID. SUNDAY, JULY 19fch (19th DAY OUT). — Gontd. Light variable wind. Fine and clear. Bar. 30-00. Ther. 70° F. Temp. 70° F. dry, 62° F. wet. Began coaling into bunkers. Shore party returned to ship. Similar wind and weather. Bar. 30-00. Ther. 70° F. Temp. 70° F. dry, 63° F. wet. 70 HAVRE- WATERVILLE CABLE EASTERN REPAIR. S.S. “BUCCANEER.” I s - I . ' HOUR. A.M. 2.45 4.0 6.0 6.15 8.0 9.0 11.50 NOON. P.M. 2.0 2.25 2.35 2.47 3.27 4.0 5.0 Steaming to Cableground off Barfieur. S.S. “ BUCCANEER. ” MONDAY, JULY 20fch (20th DAY OUT). Finished coaling. Amount shipped = 100 tons. Light WNW breeze. Fine and clear. Bar. 30 03. Ther. 64° F. Temp. 70° F. dry, 60° F. wet. Cast off moorings from hulk and left for anchorage. Let go anchor. Similar wind and weather. Bar. 30-05. Ther. 67° F. Temp. 70° F. dry, 60° F. wet. Messrs. Gott and Crawford left for shore. Messrs. Gott and Crawford returned to ship with visitors. Similar wind and weather. Bar. 30 06. Ther. 70° F. Temp. 72° F. dry, 62° F. wet. Visitors left ship. Hove up anchor and set on for cable ground off Barfieur. Passed breakwater. Discharged pilot. Full speed ahead. Passed Shambles Light Ship. Light W breeze. Overcast. Bar. 30-20. Ther. 78° F. Temp. 73° F. dry, 64° F. wet. During the day the cable hands transferred from fore to after tank the 1-100 n.m. spliced up piece and the 1 1638 n m spliced piece. In this second piece the splice was cut out and the fault removed. All the short pieces were afterwards spliced up and turned into the after tank. 73 HAVRE— WATERYILLE EASTERN REPAIR. S.S. “BUCCANEER,” JULY. 1903. « hH <1 Ph h « w w EH « O pq ft £ hP EH tf O P-t o {z; HH > <1 H £ O Cn HH w m m A PQ < o o £ I— I £ o M GQ w £ 74 Piece “K,” No. 8502, Single Core=0-083 N.M.=0-197,tons; and Piece “0," No. 8502, Single Core=0-157 n.M.= 0-372 tons. Picked- Up Cable in Fore Hold .— Piece “0," No. 8512, Single Core=0-894 N.M—1'944 tons; and Piece •• B,” No. 8512, Single 0ore=0*200 n.m.= 0-435 tons. HOUR. P.M. 8.0 11.35 MID. A.M. 0.20 0.46 1.5 2.20 2.25 4.0 4.40 4.45 4.47 5.0 On Cableground. S.S. “BUCCANEER.” MONDAY, JULY 20th (20th DAY OUT) — Contd. Light W. wind. Fine and clear. Bar. 30-22. Ther. 74 d F. Temp. 69° F. dry, 61° F. wet. In position to place Mark Buoy. Paid out moorings and slipped buoy. Buoy's Moorings . — Buoy No. 47, Flag blue “ B,” 2 lamps and hanger, ■§" bridle, 30 fms. J chain, also 30 fms. -f" and 2J fms. j' chain, 2 mushrooms 4 cwt. 1 qr. 16 lb. and 3 cwt. n i/i ik t> • i • ( Lat. 49° 53 f, 8 N ) QQ , 0 qr. 14 lb. Position | Lon p 23 ,. g w J 38 fms. Similar wind and weather. Bar. 30-22. Ther. 72° F. Temp. 69° F. dry, 60° F. wet. TUESDAY, JULY 21st (21st DAY OUT). Sounded No. 21 — 38 fms. h. n. sn. Bottom temperature 61-5° F. Sounded No. 29 — 37 fms. h. n. sn. Bottom temperature 58-7° F. Set on for position to grapple. Lowered centipede with 2-|- fms. trail chain and 20 fms. f" chain, and commenced paying out 4x4 rope. Drag No. 1. Ind. = 33 revs. = 100 fms. of rope paid out. Commenced drag. Engines used as required. Light N wind and overcast. Bar. 30-22. Ther. 70° F. Temp. 67° F. dry, 61° F. wet. Strain rose (for the first time), to 18 cwt. steadily. Com- menced picking up. Strain rose to 60 cwt. Paid out a few fms. Strain fell. Resumed picking up. Grapnel at bows, with cable. Strain, 70 — 80 cwt. Got drum ropes along and made fast to each side of cable. Cut cable. 5.25 75 Y On Cableground. S.S. “BUCCANEER.” HOUR. A.M. 5.30 6.1 6.26 6.30 6.45 8.0 10.50 11.5 11.45 11.53 11.55 NOON. P.M. 0.57 1.5 1.15 1.30 TUESDAY, JULY 21sf (21st DAY OUT) — Contd. Took grapnel inboard and took starboard drum rope to drum (Waterville end), and commenced picking up for testing. End to Waterville abaft drum. Commenced testing. Finished testing — “ O.K.” Prepared to buoy end., Sealed Waterville end. Veered away on Waterville end and picked up on Havre end for testing. Similar wind. Fine and clear. Bar. 30-30. Ther. 69° F. Temp. 65° F. dry, 61° F. wet. Paid away on Havre end, in order to pick up on Water- ville end and buoy same. Picked up on Waterville end and attached buoy’s moorings. Paid out buoy’s moorings with Waterville end attached. All moorings paid out. -p, ... ( Lat. 49° 52' Position Let go buoy. ■9 N. . Lon. 1° 2P-9 W. Buoy's Moorings. — Buoy No. 55, Flag “ S,” Lamp hangers, f" bridle, 5 fms. J" chain, 15 fms. 4x4 rope, 40 fms. chain, 15 fms. 4x4 rope. Mushrooms 2 — 3 cwt. Commenced picking up to fault in Havre end. End of cable off drum. Set lnd. Zero, coiling cable in after tank. Similar wind and weather. Bar. 30-33. Ther. 73° F. Temp. 73° F, dry, 63° F. wet. Ind. = 423 revs = 1-220 n.m. Splice passed inboard = Piece “L.” Resumed picking up, cable now coming in, in bad condition. Ind. = 436 revs. =1-257 n.m. Broken end passed inboard. From the above splice to the end = 0-037 n.m. the cable was in very bad condition, and only holding together by the core in places. This piece was thrown overboard. Set on to grapple for Havre end again. Lowered centipede as in previous drag. 76 On Cableground. S.S. “BUCCANEER.” HOUR. P.M. 1.35 1.55 2.0 2.30 2.42 3.10 3.35 3.45 4.0 5.15 6.10 6.15 6.50 7.20 7.30 7.33 TUESDAY, JULY 21st (21st DAY OUT) — Contd. Drag No. 2. Ind. = 33 revs. = 100 fms. of 4x4 rope paid out. Com- menced drag. Engines used as required. Strain rose to 25 cwt. steadily. Commenced picking up. Grapnel at bows with cable. Got drum rope and secured to bight of cable. Took grapnel inboard and took drum rope to drum. Hove bight of cable inboard and secured drum ropes to each side of bight, and cut cable. Commenced testing to Havre — “ O.K.” Decided to pick up on Havre end for 0-5 n.m. to ascertain condition of cable. Condition of cable fair, wires badly corroded. Stopped picking up. Ind. =65 revs. =0T87 n.m. Cut cable. Piece “M” ready for splice with top end of Piece “L” in after tank and commenced opening out same. Short piece coiled in fore tank. Got up top end of Piece “ L ” from after tank and opened it out for splice with Havre end. Mod. W breeze. Overcast and cloudy. Bar. 3021j Temp. 79° E. dry, 69° E. wet. Opened out bottom end of Piece “L” and top end of spliced-up section. Commenced joint between Havre end and top end Piece “ L.” Gut 5 fms. off Havre end. Finished joint. Commenced splice. Finished splice. Commenced joint between bottom end of Piece “ L ” and top end of spliced-up Section H. I 8514 in after tank. Cut 5 fms. off spliced-up section for splice. Hove in short Piece “ N ” towards Waterville = 0T32 n.m. Put turns of tank (Havre) end on drum. 77 y 2 On Cableground. S.S. “ BUCCANEER. 5 ’ HOUR. P.M. 7.40 8.10 8.15 8.20 8.45 9.0 9.50 MID. A.M. 2.5 4.0 6.50 6.55 7.0 7.20 7.27 7.37 TUESDAY, JULY 21st (21st DAY OUT) — Contd. Set on “slow” ahead, paying out Piece “ L ” from after tank. Splice passed off drum. Ind. set Zero. Ind. = 353 revs. = 1-018 n.m. of rope paid out. Stopped ship, put brakes down and took turns of cable off drum. Finished joint between Piece “ L ” and spliced-up section. Commenced paying out moorings to moor ship for night. Veered away on cable accordingly. Ship’s Moorings all paid out. Put stoppers on and took 4x4 rope off drum and took cable to drum again. Put rounding on both to await daylight to resume paying out. Note. — No lamps were put on the buoy on Waterville end, which necessitates waiting till daylight. Commenced splice between Piece “L” and spliced-up section. Finished splice between Piece “L” and spliced-up section. Similar wind and weather. Bar. 30-22. Ther. 69° F. Temp. 67° F. dry, 66° F. wet. WEDNESDAY, JULY 22nd (22nd DAY OUT). Picked up 0-288 n.m. of cable, and paid out on grappling rope. Ship swinging to tide. Moderate WSW wind. Cloudy. Bar. 30-13. Ther. 69° F. Temp. 72° F. dry, 63° F. wet. Picked up ship’s moorings. Put turns of cable on drum and set Ind. = Zero. Commenced paying out cable from after tank to Water- ville buoyed end. Put engine out of gear. Engines used as required. Ind. = 124 revs. Splice between Piece “L” and spliced up section in after tank passed off drum. 0-50 n.m. paid out from splice. Strain = 18 cwt. L00 „ „ „ „ 19 „ On Cableground. S.S. “BUCCANEER.” HOUR. A.M. 7.50 7.55 8.0 8.7 8.15 8.30 8.40 10.0 10.50 10.55 11.15 11.55 NOON. P.M. 0.20 1.0 1.5 1.10 WEDNESDAY, JULY 22nd (22nd DAY OUT) — Contcl. Splice H.I. 8514 — H.I. 8514 passed off drum. This is the top piece of the spliced up section = 1-623 n.m. Approaching Waterville buoyed end. Lowered and sent boat away with drum rope to dismantle it. Similar wind and weather. Bar. 30-16. Ther. 73° F. Temp. 74° F. dry, 63° F. wet. Knocked up tumbler and hove in slack of buoy’s moorings by winch. Put engine in gear. Hove up buoy and boat. Ind. 768 — 124 = 664 revs. = 1-915 n.m. of rope paid out. Took turns off drum. Took buoy’s moorings to drum and resumed picking up on same. Veered away 57 fms. of cable. All buoy’s moorings on board and Waterville end abaft drum. Commenced testing to Waterville. Finished testing to Waterville. Gave out end for joint. Finished testing to Havre. Gave out end for joint. Cut Havre end and commenced opening out both ends for joint. Commenced joint. Cut 5 fms. off Havre (tank) end. Sounded No. 31 T — 40 fms. Temp, of bottom = 59°-9 F. Finished joint. Light WSW wind. Cloudy and overcast. Bar. 30-16. Ther. 73° F. Temp. 74° F. dry, 63° F. wet. Commenced splice. Finished splice. Started veering away on hanging ropes. Bent slip stopper on to bight of cable and cut hanging 79 Steaming to London . S.S. “BUCCANEER.” HOUE. P.M. 1.17 1.30 1.37. 1.50 2.7 4.0 7.50 8.0 11.15 11.40 MID. WEDNESDAY, JULY 22nd (22nd DAY OUT) — Contd. Slipped final splice. Position 2p-cfwj ^ ^ ms Set on to pick up Mark Buoy. Up to Mark Buoy. Lowered boat and sent her away to dismantle it. Knocked up tumbler and commenced picking up moorings Hoisted buoy and boat. All buoy’s moorings on board. Set on full speed for London. Light WSW breeze. Cloudy and overcast. Bar. 30-08. Ther. 72° E. Temp. 74° E. dry, 63° F. wet. Observed Beachy Head Lighthouse. Light SSW breeze. Cloudy and overcast. Bar. 30-01. Ther. 74° F. Temp. 63° F. dry, 61° F. wet'. Dungeness Light abeam. Stopped and took Pilot and proceeded. Light SSW wind. Fine and clear. 80 Fac. No. 8514. S.S. “ BUCCANEER.” Cable Picked Up and Abandoned. 1*220 n.m. Piece “ L,” picked up to fault after buoying Waterville end =“ O.K.” Type B 12, No. 6, 130/130. 0*037 n.m. Part Piece “ L.” Bad, and thrown overboard. 0*187 n.m. Piece “ M.” Picked up to ascertain condition of cable ; broke while picking up on Havre end. - 0*132 n.m. Piece “N.” Short piece picked up to break after Drag 2, Havre end=“ O.K.” 0*005 n.m. Cut off Havre end for splice yvith Piece “ L,” which was relaid. 1*581 N.M. Total picked up. 1*369 n.m. Abandoned length, as agreed with Mr. Gott. 2*950 N.M.=Total. Cable Relaid and Expended. 1*220 n.m. Type B. Piece “ L ” relaid. 1*618 N.M. H.I. No. 8514, top piece. Splice Piece “ L ” and H.I. No. 8514, cut off latter. Paid out by Ind. H.I. No. 8514. 0*057 N.M. 0*005 N.M. Final splice cut off tank end. 3*175 N.M. 1*220 n.m. Piece “ L” picked up and relaid. 1*955 N.M.=Total new cable expended. 81 HAVBE— ' WATER VELLE EASTERN w © * W CO o CT> TS 3 cq cq cq kH P Pf (-H <1 Ph Ph 'SOTTZ ‘Svxa Z o^j pa^ooH Ph m p p o g*is g ^ .^ H nO > 1^1 ■'•§§ a -S w ^3 pq ^ d d *158 ‘ 0 JsT — 9/ST a soxidg 'i ^ ii ii 3 O «* - o d B 'S JM « •§* H 53 M „ >2; ~ O rH CSJ zo cs CO II II II ffl fc 82 HOUR. A.M. 1.30 2.15 3.50 4.0 6.40 7.40 8.0 9.0 NOON. I Steaming to London. S.S. “ BUCCANEER.” STEAMING TO LONDON. THURSDAY, JULY 23rd (23rd DAY OUT). Off South Foreland. Gull Lightship abeam. Tongue Lightship abeam Light WSW breeze, and clear. Bar. 29-92. Ther. 69° F. Temp. 72° F. dry, 64°. F wet. Chapman Lightship abeam. Off Gravesend. Pilot Anderson left ship, Pilot Twist boarded. Similar wind and weather. Bar. 29-91. Ther. 69° F. Temp. 72° F. dry, 64° F. wet. Off Silvertown and moored inshore of “ Dacia.” FRIDAY, JULY 24th, Paid all crew off at Tidal Basin Shipping Office. 83 COMMERCIAL CABLE COMPANY’S CHARTER. S.S. “ BUCCANEER,” JULY, 1903. m W o £ P P O P <1 > i— i pq P <1 55 o P hH w zn Eh P O i— i P £ ft 55 <1 P P PP <1 o P o 55 O t-q H P P (—1 P EH ZD y A rH I! 11 II s ^ 2 H H M | S g 'f-j O' o < ^ q 84 SUMMARY. HAVRE— WATERVILLE CABLE REPAIRS. S.S. “BUCCANEER.” ELECTRICAL REPORTS. INDEX TO ELECTRICAL REPORTS. Havre — Waterville Western Repair Report Havre — Waterville Eastern Repair Report Distribution .of Cable in Tanks on board S.S. “ Buccaneer ” on Leaving Silvertown ... Factory Electrical Values of Cable on board S.S. “Buccaneer,” July 1st, 1908 Expenditure Table Diagram Showing Cable Operations during Western Repair Distribution of Cable in Tanks, etc., on board S.S. “ Buccaneer,” on Leaving Portland for Eastern Repair Expenditure Table Diagram Showing Cable Operations during Eastern Repair Sheet Totals and Tests Sheet A Sheet B Sheet C Sheet D Distribution of Cable in Tanks on board S.S. “ Buccaneer,” on Return to Silvertown ... Factory Electrical Values of Cable on board S.S. “Buccaneer” on Return to Silvertown, July 23rd, 1803 PAGE 91 99 107 108 109 111 112 113 114 115 116 117 118 119 120 121 Waterville— Canso (1884) Repair Report Factory Electrical Values after Repair by S.S. “ Buccaneer, ” July 17th, 127 1903 134 Diagram Showing Cable Operations during Repair Distribution of Cable in Tanks on board S.S. “ Buccaneer,” on Leaving 135 Valencia for Repair Factory Electrical Values of Cable on board S.S. “ Buccaneer ’ ’ on Leaving 136 Valencia, July 9th, 1903 137 Expenditure Table ... 138 87 ' ELECTRICAL REPORT. (WESTERN REPAIR, JULY 1st— 6th, 1903.) 89 ELECTRICAL REPORT. (WESTERN REPAIR, JULY 1st— 6th, 1903.) F. C. Crawford, Esq., Engineer in Charge. S.S. “ Buccaneer .” Dear Sir, Two partial earth faults having developed in the above section, the “Buccaneer” was chartered by the Commercial Cable Company to remove the same, and left the Silvertown Works at 8 p.m., July 1st (Mr. J. Gott having previously joined ship), and pro- ceeded to position of Western fault, which had been localised at 60 miles approximate West of Scilly Isles. On July 3rd, 5.30 p.m., arrived on cable ground, streamed Mark Buoy, and took a series of soundings (see Appendix), and then started dragging for cable, which was hooked at second drag, but parted at bows. Grappling was resumed, and at the seventh drag the cable was caught. At 5.32 p.m. (July 4th), Waterville end was handed to testing room, but on testing it was found to be a “short end.” Havre end was now dealt with, the ship being in communication with that station from 6.22 p.m. A preliminary test taken with 5 cells gave a total D.R. of CO 7365 falling. From 6.50 to 9 p.m., a series of tests were taken from ship and Havre to locate position of Eastern fault, but owing to its very variable resistance, polarization changes being frequent and rapid, the results obtained were only very approximate, and therefore mis- leading. At 9.5 p.m. the lowest resistance (zinc 20 cells), obtained CO by H.R. being 6400 (end earthed on board). Lowest resistance at any CO CO time obtained by H.R. = 5600. Carbon to line from ship = 20000. (End earthed in all cases mentioned.) a 91 Electrical Report. Ships results by Blavier’s formula and Anderson and Kennedy’s 03 03 earth overlap varied to an extraordinary degree, i.e. from 2320 to 4703. At 9.8 p.m. sent S. G. — Gott to V. P., G. M. and M. E., “ Saturday cable broke on picking up. 6 a.m., spoke H. R. 6.20 : Fault on Havre side cannot be localised at present ; now buoy and go for Waterville end; weatfher getting squally and unpromising.” 9.11 p.m. Gott to S. H. R., “ We seal your end and buoy. Try and seal the fault with carbon 20 or 30 cells and get a capacity ; wire results to Waterville.” Havre end was buoyed at 9.45 p.m., and loose piece of cable towards Waterville picked up. Length recovered = 0*708 n.m., Piece “A,” type No. 8512. Cruised round cable and Mark Buoys all night. The following morning, July 5th, was unfavourable for cable work, so the opportunity was taken of splicing up Piece “A” to Piece 5 in the Fore tank, which, tested after splicing, gave a D.R. per n.m.= ft 617* at 59J° F. (200 volts). Weather becoming finer, the grapnel was lowered again — Drag 8 — and at 2.40 p.m. cable was at bows, the end being handed to testing room at 3.22 p.m. Waterville was called and replied immediately, signals being very jerky and failing. Waterville was instructed to “free,” and ship tested, and with 1 03 L6clanche cell obtained a total D.R. of 73. H. E. C.’s triple test 03 was then taken and the fault on Waterville side located at 16 = 0*969 n.m. approximate from ship. At 4 p.m. started picking up on Waterville end to fault and loose end at same time., the latter coming on board at 4.30 p.m. Length p.u. =0*200 n.m., Piece “ B.” During the process of picking up on Waterville end a control was kept on cable by means of observing the natural current from fault — 230 S.R. 200 — and at 4.52 p.m. a great change was observed, the deflection falling to 100, until at 5.5 p.m., bad kink passed over drum, deflection fell to zero and then rose slowly to 80. Fault inboard. The cable was cut at kink which was found to be the fault. Nature of fault ; — Kink, damage caused by trawler. When the 92 Electrical Beport, kink was opened out the conductor was found to be exposed in two places. Length picked up on Waterville end to fault = 0-894 n.m., Piece “C.” After cutting out the kink, Waterville end was tested from ship, results showing that the fault had been removed from cable. ft ft D.R. (20 cells), 1st min. Z. total = 31-111 = 5510* per n.m. at sea temp. (See Appendix.) ft Conductor resistance mean Z. and C. total corrected = 2907*5. Length in circuit = 177- 13 n.m. At 5.40 p.m. the following S. G.’s were received on board. To Gott, “ Fourth fault of 20000 ohms, resistance appeared in Northern yesterday, our tests useless. Canso makes 614 added to loop = 100 ohms, from here.” S. W. V. to Gott. — “ Canso’s test to-day loop 14370 added to Northern 614.” 5.50p.m. V. P. to Gott. — “Can ‘Buccaneer’ proceed after repairing H.R. to take out fault in Northern. Have you cable on board?” S. W. R. to Gott. — “After being on for ten hours carbon makes resistance go up only to 30000 ohms. No Capacity test possible.” 5.53 — 6 p.m. Waterville took C.R. from Waterville to ship. Total, a; 2908. Ship then took capacity test (Null Method), obtaining a total capacity in circuit between ship and shore = 54-150 mfds. (See Appendix.) Note. — By comparison with the 75° values this capacity represents a length in circuit of 176-517 n.m. from Waterville C.H. to ship, from which must be deducted 0-221 n.m. = Waterville land line. Therefore 176-517 — 0-221 = 176-296 n.m. to Waterville from ship. z2 93 Electrical Beport. At 7.10 p.m. the joint was commenced between cable in after tank and Waterville end, and at 9.45 the splice was completed. From 8.15 to 8.41 several S.G.’s were sent to Waterville, the follow- ing — bearing on the Northern repair — being the most important. Gott to Y. P. — “ Sunday, 8.0 p.m. Taken out fault, spliced on and will soon pay out to Havre end. Another fault between ship and Havre partial continuity. If they can work, propose go Water- ville. ‘ Buccaneer ’ has sixteen miles suitable cable for Northern on board. Fault in Northern appears to be about fifty miles from Waterville. Must locate fault in Havre from shore, and may do so at Waterville. Please reply. If I hear nothing further shall proceed direct to Waterville and wire from there.” At 8.42 p.m. Waterville reported: “Working very well on Northern simplex.” At 9.35 p.m. took temperature sounding at position of “Buc- caneer’s” Western splice. Lat. 49° 48'*0 N ) Lon. 8° 2'-0 W 1 Depth 54 fms ' Bot ' temp ' 50 ° At 10.10 p.m. started paying out cable towards Waterville, a control test with 20 cells being maintained, and at 11.10 Havre cable buoy was reached. At 0.15 a.m., July 6th, received S.G. — S. H. R. to Gott. 10.30 p.m. — “ Lowest now, 1320 zinc.” Havre end was on board at 0.20 a.m. v , and from 0.53 to 1.10 ship tested Havre end — “earthed” and “free” alternately. Cable free at Havre (20 cells) 5990, 6190, to false zero. Zinc. W 10 „ earthed ,, ,, 5040, 5150 ,, ,, OJ L taken as 5560. free earth w By Blavier’s formula, 1st pair, 5990, 5040 x = 4337 from ship to fault. „ „ 2nd „ 6190, 5150 x = 4497 0 > Resistance of line when perfect, Havre to Waterville = 8455. 94 Electrical Report. Resistance of cable (by ship) from ship to W.V = 2939 Resistance of cable (by ship) Ct ) from ship to fault = 7 27 b 2nd pair, 2939 + 4497 = 7436 w Mean of the two = 989 from Bleville to fault. Note. — Result approximate only, the battery not being adjusted so as to give the same C.S. through fault when testing cable either “ free ” or “ earthed.’’ 8455—7276 = 1179—110 L.L. and E. w = 1069 dist. to fault from B16ville. 8455-7436 = 1019—110 L.L. and E. = 909 dist. to fault from Bleville. From 1.15 to 1.25 a.m., Waterville and Havre ends were put through on board in order to exchange signals with each other. At conclusion of time both Havre and Waterville reported signals very good, and at 1.33 — 1.36 sent S.G. : Crawford to Silvergray. — “About to make final splice 60 miles west of Scillys, then proceed to Waterville to repair Northern cable. All well. 1.30 a.m., Monday.” Gott to S. W. V. — “We are going to make Final Splice. Get earth overlap test with Havre. Do not apply copper to line. I shall be at Waterville Tuesday morning. Let Canso repeat loop test and give resistance of fault in Northern at time loop taken.” Cable was now cut at tank end. Total cable expended = 2-171 n.m. Ship tested (2.5 — 2.20 a.m.) Waterville end before making final splice, obtaining highly satisfactory results, viz : Total C.R. corrected (mean Z. and C.) = 2939-4. ft ft Total D.R. 1' zinc = 28-00 = 5020 per n.m. at sea temp. Length in circuit = 179-289 n.m. At 2.25 a.m., gave out Waterville end after instructing him to call Havre at 4.0 o’clock. At 2.40 a.m., gave out Havre end after instructing him to call Waterville at 4.0 o’clock. | See j Appendix. 95 Electrical Report. July 6th, at 4.10 a.m. the joint was finished, and at 5.15 the splice completed, the Final Splice being slipped at 5.25 a.m. D ... , -nr 7 c 7 . ) Lat. 49° 47'*4 N Position of Final Splice. J Lcxn 7° 59 f, 2 W Depth 68 fms. After waiting for the sea to moderate, the mark buoy and moorings were got on board at 10.15 a.m., and at 10.35 ship set on full speed for Waterville, Co. Kerry, Ireland, to repair Commercial Cable Co.’s Northern section. This repair will be the subject of a separate report, and we will now deal with the Eastern repair to the Havre — Waterville Cable. 96 ELECTRICAL REPORT. (EASTERN REPAIR, JULY 18th— 23rd, 1903.) 97 ELECTRICAL REPORT. (EASTERN REPAIR, JULY 18th— 23rd, 1903.) Note. — The S.S. “Buccaneer” arrived off Waterville on the morning of the 7th July, and at 8.45 a.m. Messrs. Gott and Cann went ashore to Cable Station to localise the faults in the Havre — Waterville and Waterville — Canso Cables. From a number of tests taken on the Havre — Waterville Sec. by Anderson & Kennedy’s Earth overlap— free overlap — etc., a selection was made from those which most closely checked each other, and which placed the fault at from 990 to 993 from B15ville. Assuming the mean bot. temp, to be 65° F., then this resistance = ... ... 6P9 from B16ville app. Assuming the mean bot. temp, to be 63° F., then this resistance = ... ... 62-78 ,, „ „ Mean 62-34 ,, ,, ,, The S.S. “Buccaneer” having finished the Repair to the Canso — Waterville Northern (1884) Cable at 8.35 p.m., July 17th, discharged her Pilot (O’Neill) off Horse Island, Ballinskelligs Bay, the following morning — 18th — at 5 a.m., and proceeded for Portland, there to take in coal and provisions. During the passage and subsequently opportunity was taken to transfer Pieces “G” and “K” (p.u. Canso — Waterville repair) from Fore tank to Hold, and Piece “H” (Canso — Waterville) to After tank, Intermediate Sec. 4, (L = 2000) was also transferred from Fore to After tank. The fault in the 2-5396 n.m. piece of H.I. No. 8514 was also broken down by the application of 560 volts for many hours, a loop test taken and the fault located in the splice 0-9011 — 1-6385. This cable was transferred 99 Electrical Report. from Fore to After tank and the splice between above pieces cut out, the fault proving to be a defective joint. The separate lengths of H.I. No. 8514 (brought away in “Buccaneer’’) were now spliced up, making a total length of 3-615 n.m. of No. 8514, the type required for Eastern repair. This section was tested after splicing, and gave ft highly satisfactory results, viz., D.R. with 200 volts = 1434 per n.m. at 61i° F. The “ Buccaneer ” arrived at Portland at 4.55 p.m., July 19th, and after coaling and taking in fresh provisions, left again for cable ground off Cape Barfleur at 2.25 p.m., July 20th, arriving off that place late on the same night, and at 11.55 p.m. streamed Mark Buoy, “BB,” took two soundings, 28 T , 28 fms., hot. temp. 61^° F., and 29 T , 37 fms., hot. temp. 58°*7 F. ; at 2.25 a.m., July 21st, lowered grapnel for Drag 1, hooked cable and had it at bows at 5 a m. Called Waterville and got him immediately, and at 5.32 ship tested Waterville end with the following result — Length in circuit = 449*2 n,m. ft ft D.R. 20 cells 1' Zinc total = 15*8 = 7297 per n.m. at sea temp. C.R. ,, Mean total Z. & C. (corrected) = 7363. to Waterville obtaining a C.R. to ship = 7370. At 6.26 a.m. gave out Waterville end for buoying, and had end sealed for testing. Picking up was then commenced on Havre end, which was handed to testing-room at 7.7 a.m. Havre was called and answered immediately, and ship taking a D.R. test with 5 cells, to obtained a resistance of 2709 only. Havre shortly afterwards to getting a C.R. = 1115, end being to earth on board. From 7.40 to 10 a.m. ship and shore testing for locating fault. Very varying results were obtained, the fault being most unsteady. The following were the only workable results obtained from all the series, viz. : to 1st measurement — By Blavier’s formula = 270 from ship. w 2nd. ,, Earth overlap (Anderson & Kennedy's) = 7 to 8 from ship. 100 Electrical Beport. July 21st, 3rd measurement. Earth overlap (Anderson and Kennedy’s) = 42*5 from ship. to 4th measurement. Earth overlap (Anderson and Kennedy’s) =8 very unsteady, approximate only. w At 9.19 a.m., Havre obtained a resistance = 1117 — “good result.” End earthed on board, ship earthing direct, and at 10.0 a.m. shore attempted Kennedy series, “ end free on board,” but reported, “ No reliable Kennedy could be taken, readings varying by 1000 ohms, in same second.” Shortly after the following S.G. was received from Waterville via Havre to ship: — “Tests to buoyed end 10th minute, zinc 6570, carbon 6500 megs, per n.m. Capacity = 142 6 mfds.” 10.25 to 10.27, sent two S.G.’s — Gott to S. H. R. and Y. P. M. E. Veered away on Havre end at 10.45 a.m. Ready to buoy Waterville end, which was let go at 11.45, and ship then started picking up towards fault on Havre side, Havre at this time taking C.R. end to to earth on board and getting a resistance = 1117. Ship now instructed Havre re details of fad of potential test which it was decided to take, and at 0.56 p.m. commenced test, when cable parted close to ship, A minute later splice passed off drum between Type B “ Mirror ” and Type No. 8514 original. Length picked up = 1 -223 n.m. Piece “L.” This splice was cut out and 37 fms. of very badly damaged and corroded cable, which came in subsequently, were cut off and thrown overboard. The broken end came in at 1.5 p.m. In three places the core only was holding and ad sheathing wires were very badly corroded. Down grapnel again at 1.35 p.m., the cable being hooked and handed to testing room at 2.41, when Havre was called and answered immediately. Ship took D.R. test on Havre side after removal of fault. 101 Electrical Beport. Length in circuit = 59-1 97 n.m. 12 12 20 cells V Zinc total = 24-5 = 1451 per n.m. at sea temperature. Note. — This value, although low, is no lower than that obtained from about the same position during recent repairs by “ Mirror,” “ Buccaneer,” etc. Resumed picking up on Havre side to ascertain if cable was in good mechanical condition, it being the intention to examine the cable for about -J-mile, and if found to be in good condition to relay the same. Tested Piece “ L ” (L = 1-220 n.m.), Type B, picked up this morning. 12 D.R. with 200 volts 1' Z. total = 3700 approx. “O.K.” At 3.35 p.m.,, stopped picking up and cut cable when 0-187 n.m. had been recovered (Piece “M’’). This piece is mechanically bad, the sheathing wires being much worn by abrasion and corrosion. A C.R. test taken from ship after cutting gave (end to earth at i a Havre) mean Z. and C. total (corrected) = 1071. Length in circuit = 59*015 n.m. The following S.G was. sent vik Havre at 4.15 p.m. : “ Gott to V.P. and M.E., 4.0 p.m. Have cut out fault in Havre. There are three splices to make. Hope to get through to-night. Weather fine.” And then gave out Havre cable for splicing on to Piece “ L,” Type B, (L = 1.220 n.m.) coiled in after tank. Joint finished about 6.0 p.m., the splice also at 7.0 p.m. Position of 11 Buccaneer's” First Splice. July 21st, 1903. Lat. 49° 5P-8 N Lon. 1° 17'*8 W 36 fms. Cape Barfleur Lighthouse S. 6° E. 5.50 — 6 p.m. at Havre). Ship tested Havre side for D.R. and I.C. (end free 12 12 D.R. 1' Z. total = 21-55 = 1298 per n.m. at sea temperature. 102 Electrical Report. Capacity total (Null method) = 20-03 mfds. (See Appendix.) The loose end towards Waterville was now picked up, break coming inboard at 7.30 p.m., sheathing wires worn to needle points and end perfectly sealed by the G.P. being drawn down over con- ductor. Length picked up = 0T32 n.m., Piece “N.” At 7.40 p.m. commenced paying out cable towards Waterville buoy and stopped paying out when eight turns of Piece “L” remained in tank, and anchored ship for the night with mushroom and buoy-rope. After this operation the splice between bottom end of Piece “ L ” and top end of H.I. (L = 3-610 n.m.) was completed and work suspended for the night. Two separate C.R. measurements taken from ship at 10.15 and c o fi 12 10.39 p.m. gave 1140*3, and the D.R. total = 16-333 = 1043 per n.m. The following morning, July 22nd, Havre was called up at 6.45 a.m., and ship testing obtained the following results on cable — O ft D.R. total 1st min. Zinc = 22 0 = 1405 per n.m. at sea temp. ft Havre also took a check D.R. test, getting a total of 22-5 mean of 4 mins, zinc and 4 mins, copper. At 6.58 a.m. started paying out cable towards Waterville buoy, which was reached at 7.55. At 9.5 Waterville end was in testing room and ship called, receiving immediate reply. Ship tested for C.R. and D.R. before making Pinal Splice. 0 } Conductor Resistance total mean Z. and C. =7377 ft ft Dielectric ,, 1' Zinc total = 17*133 = 7696 per n.m. at sea temp. Length in circuit = 449*2 n.m. The following S.G.’s were sent and received during 9.41 — 9.52 a.m. S.W. Y. to Gott. — “C.R. loop 14275 added 324. Insulation Northern, tenth min. Zinc and Carbon = 37320 megs, per n.m.” 103 Electrical Report. Gott to Y. P, and M. E. — “Wednesday, 10 a.m., about to make Final Splice, weather fine, fault due to corrosion. ‘ Buccaneer’ pro- ceeds to London, should arrive Thursday morning.” Gott to S. W. Y. — “Please wire tests Havre, care Twist, Trinity Pilot, Gravesend.” Crawford to “ Silvergray,” re final splice and ship’s movements. — “At 10 a.m. ship instructed Havre to take C.B., who obtained a total C.R. to ship 7370* ohms.” Waterville was notified (10.13 a.m.), “About to make Final Splice, call Havre at noon,” and dismissed, arid the tank end of cable was cut. Total paid out between Havre end and Waterville = 3 T655 n.m. At 10.30 a.m. Havre was informed, “ We now make Final Splice, call Waterville at noon,” and also dismissed. The joint between Waterville and Havre ends was finished at noon, and at 1 p.m. the splice was completed and slipped at 1.15 p.m., thus completing the repair. Position of “ Buccaneer's Final Splice .” July 22nd , 1903. Lat. 49 52'-9 N \ 40 fms. Lon. 1 21'*9 W j Bottom temperature = 59 0, 9 F. Cape Barfleur Lighthouse, S. 19° E. Cape Levi, S. 21f° W. Gatterville Church Tower, S. 15° E. Distance overground = 2*95 n.m. July 22nd. After picking up Mark Buoy, the “Buccaneer ” pro- ceeded for London, arriving off Gravesend at 7.40 a.m. the following morning, July 23rd, where Mr. Gott received following telegram from the superintendent at Waterville, “ Havre tests Z. 4602, C. U) 4985 megs, per knot tenth min. C.R. 8483 — Wilmot.” The “ Buccaneer ” proceeded up river and made fast off Silvertown Works, inside “ Dacia,” the same morning. In the Appendix will be found the following tables, etc. 104 Electrical Report. Revised length and 75° F. values after Western and Eastern repairs, Havre — Waterville cable. Tests from ship towards Havre and Waterville on picking up ends. ,, ,, ,, ,, before making Final Splice. Distribution of cable in tanks and 75° values of same before repairs a )> n >> >> >> after , Expenditure tables of new and picked up cable. Diagram of operations, etc., Western and Eastern repairs, etc I am, Dear Sir, Yours faithfully, HERBERT E. CANN. Electrician . DISTRIBUTION ' OF . CABLE IN TANKS ON BOARD S.S. “BUCCANEER” ON LEAVING CO O 05 CO kH P P 1-5 0Q‘ W p o £ £ O P P P P CQ p w Eh 107 AA Factory Electrical Values at 75° F. of Cable on Board S.S. “Buccaneer,” July 1st, 1903. No. Length in N.M. C.R. at 75° F. Capacity. D.R. at 75° F. Type. of Remarks. Wire. Cable. Core. Total Per N.M. Total Per N.M. Total Per N.M. Int. Sec. 4 FORE TANK. Top. 02664 2-0000 18-456 9-228 0-7186 •3593 247 494 H.I. 8514 0-5000 8-515 17-03 0-1780 0-356 764 382 ] L.I. 0-0783 1 V 8513 0-2200 3-747 1736-4 H.I. } 8514 0-3804 6-478 0-1354 1004-2 H.I. } 8514 0-9011 15-346 0 3208 423-9 H.I. \ 8514 1-6385 27-904 0-5833 99 233-14 / Bottom. 3-6400 61-990 17-03 1-2958 0-356 104-9 382 Single AFTER TANK. Top. 8512 Top 2066 36-054 17-451 0-6311 •3054 Bot. 0-624 10-620 17-02 0-2072 •3320 Piece 5. 2-690 46-674 17-35 0-8383 •3116 Top 0-304 5-305 17-451 0-0929 •3054 Bot. 1-332 23-245 » 0-4068 » Piece 6. 1-636 28-550 17-451 0-4997 •3054 Twin 0-994 16-91 17-02 0-3300 •3320 583 580 Piece 4. Oore 8553 v No. 1 1T085 1-1210 14-720 13-13 0-3704 •3304 2132 2390 No. 2 14-730 13-14 0-3689 •3291 2618 2935 Piece 3 Plain 8552 1 0053 0-054 0-718 13*29 00162 •2993 Piece 2 8552 Rib 2 Plain 1 0-716 13-26 0-0159 •2950 1 “ Buccaneer,” 0-243 0-2457 3-265 13-29 0-0735 •2993 j 30.7.02. Piece 1 8552 Rib 2 Plain 1 3-258 13-26 0-0725 •2950 ) “ Buccaneer,” 2-708 2-738 36-389 13-29 0-8196 •2993 j 30.7.02. Piece 4 Rib 2 Plain 36-305 13-26 0-8078 •2950 ) “Buccaneer,” f 30.7.02. 8552 1 0050 0-0506 0-6645 13-29 0-0151 •2993 Rib 2 0-6710 13-26 0-0149 •2950 The a bove pie< 3es of Type ! No. 855: 2 as splic :ed up. Twin Core Plain 8552 1 3-054 3-089 41-037 13-29 0-9244 •2993 D.S. 10 pt. B Rib 2 40-950 13-26 0-9111 •2950 3673 19-570 5-328 1-3267 •3612 226-25 831 pt. 3 2147 a DS, 10 pt. B 2147 D.S. 10 pt. B 10-978 58-458 5-325 3-9268 •3577 67-86 745 2147 3-000 15-987 5-329 1-0996 •3665 277-7 833 108 Electrical Eeport, HAVRE— WATERVILLE (1884) CABLE. WESTERN REPAIR, JULY 6th, 1903. EXPENDITURE TABLE. Cable recovered during Repair, Type No. 8512. Relaid in Section, part Piece “ A ” Cut off Piece “ A ” — screwv 99 99 55 55 lUJiXliagCU. Splice to Waterville end Original length, Piece A ' Cut off damaged, Piece “ C ” ,, „ Havre end for Final Splice Piece “ B,” coiled in Fore Tank ... « c ” ‘ 99 v - y ? 99 ' 9 9 99 *9 Total N.M. = 0-636 = 0-066 = 0-020 = 0-006 = 0-728 = o-oio - 0-006 = 0-200 = 0-894 = 1-838 Piece 5, Tpye No. 8512, in After Tank. Original length Laid in Havre — Waterville Section, 6.7.03 Remaining in After Tank ... N.M. = 2-690 = 1-529 = 1-161 Laid in Section as above. N.M. Part Piece “A” ... — 0-636 t Waterville splice „ „ 5 = 1-529 1 Havre Type No. 851 Total... 2165 AA 109 ‘2 Electrical Report. HAVRE— WATERVILLE (1884) CABLE. WESTERN REPAIR, JULY 6th, 1903. Amount of Cable cut out of Section. N.M. July 4th. — Cut off Havre end — damaged = 0020 Picked up towards Waterville, 4.7.03, Piece “A” = 0*708 „ 5th. — Cut off Water ville end — damaged ... ... = 0*010 Picked up loose end towards Havre, Piece “ B ” = 0*200 „ „ Waterville end, Piece “ C ” = 0*894 ,. 6th. — Cut off Havre end for Final Splice = 0*006 Total cut off = 1*838 Cable laid in Waterville and Havre Buoys. N.M. Piece “ A,” picked up 4.7.03, 0*642 — 0*006 ... == 0*636 Part Piece 5 = 1*529 Total laid in Section = 2*165 Splice cut off tank end (to Waterville Cable) ... = 0 006 Total expended = 2*171 110 DIAGRAM SHOWING CABLE OPERATIONS DURING WESTERN REPAIR BY S.S. “BUCCANEER.” JULY 4th to 6th, 1903. miAHaiYM. ^ i « O fl P.,2 02 3 s° S3 « p. 3 - % PS 5 c5 5 H •g oOe ‘diuaj -jog *scaj iwdaa •gO’i’fi < 30f[d r j iuojsd.w ” s,joaiiBoong „ IBUjSlJO ’SOTS ‘’ra’d ZZ'Z ‘aniA.xa^'B^v 95[ods ‘aiq«o paj[oojj •Z 'om Stu a ’SO 'Lf ‘’nra 9 ‘sAvoq jb 3>|o.iq ‘ajqpo pajjoojj m L -o n 3ej a 1 •SO 'Lf ‘’nrd gg-9 ‘8JA13H a^ods ‘aiq-GQ pa^oon fl’f l, ra-d Sf6 pa^oi g •g ohQ ‘draai *iog II -sui.4 89 qjdag o *S0T9 ‘99(ldS 5 retug „ s.jaauflbong „ .5 n in IS aaAYH Tests from Ship on Waterville end before making Final Splice. Length in Circuit= 179*3 N.M. to Mean Total C.R. (Z. and 0.) corrected =2939*4. P 53 I— I > <1 P 53 C P P P <1 O P P P i— i 5 > P P EH < £ > <1 PP P P P <1 o o p p ZD m p P i—i C P P P P P P H zn <1 P O P h-t P P P zn P O i— i EH <1 P P P O P P P < o co o . ^ 8 O 2 ^ •png n33[oja ci O 2 ■5 JZ* 2 ! •puft iiajfojg V > Tl?8 ’o\t pni3 9,'si u fl„ aoilds J M a 3 3 £ « < 1 > o S CL . -51 CO 05 O CO OO rH rH O r|( 'tH W5 i O) 05 05 OS H Ci| N . EH P3 pq eh <1 134 WATERVILLE— CANSO (1884) NORTHERN REPAIR. « m H 55 <3 O o p « CQ CQ cq « Hi < P « P 55 HH « P Q CQ 55 O HH <1 P3 E3 P O P P « <1 O P 55 Hi £ o W CQ <1 « P < 02 I as 2 * SgS Eh “3 «g«33 II » II ^ o ^ , ■ 1 ■ dSft fi- ll ft? S 3 « a Si e$d c "ca cs M 9. 0 oe 'draax -sraj ggx 'SO'Z'il ‘*nrB OVOI ‘a:>IldS W 'SI '°K Si3ad * 'SOTH SVf pa^ooH So » PS „ C3 «§ 03 II » C3 ? II In ^ a la ii ■gN co . — S Sq H G« a In © £ ^ m Ph s ft fi to r* C O a «§ S CO ii 2 a ° a CD O £ .. ’g In 63 m H w fi „HJ 8 SO! R □ _yy AA YY AA aiiiAaaiTAi. to : •a I S3 CQ P 5 o «s Sg « 02 rfi X > H 3% If Pm £ to fi .9 Ifl Eh £ OT <2 o.© 3 M «© fi — © o S£ P3d S* § cs$. ® f* 3 § a S fe I t d P3N 8 o Q rt ^ ^ M .S «j ■a a 2 □ •-X d 0 «NTO 135 DISTRIBUTION OE CABLE IN TANKS ON BOARD S.S. “BUCCANEER” ON LEAVING VALENCIA CO O K H 05 V* 0 0 i-o A w <1 o £ Ph H tn o HH <1 Ph h P 3 O EH M £ H tf H H cc •4-3 a © s 8 M *3 - e +3 a. o I I I I S 3 '£ EH CN r*H i a co CO “ Buc,” 7.7.03. 2147 10-969 58-410 5-325 3-9237 •3577 67-92 745 ) L.D.S. 10 Pt. B 14-642 77-980 5-326 5-2504 •3587 52-23 765 3-000 15-987 5-329 1-0996 •3665 277-7 833 2147 Main Pt.Pce. 5 8512 Top 0-537 9-371 17-451 0T640 •3054 Bot. 0-624 10-620 17-020 0-2072 •3320 Main Piece 6 1-161 19-991 17-219 0-3712 •3197 Top 0-304 5-305 17-451 0-0929 •3054 . 8512 Bot. 1-332 23-245 99 0-4068 Main Piece 4 8512 1-636 28-550 17-451 0-4997 •3054 0-994 16-91 17-02 0-3300 •3320 583 580 Twin Core 8553 No. 1 1-1085 1-1210 14-720 13T3 0-3704 •3304 2132 2390 No. 2 14-730 , 13-14 0-3689 •3291 2618 2935 Twin Core Piece 3 8552 Plain 1 0-053 0-054 0-718 13-29 0-0162 2993 Piece 2 8552 Rib 2 0-716 13-26 , 0-0159 •2950 ( “Buc.” 30.7.02. Plain 1 0-243 0-2457 3-265 13-29 00735 2993 ) Piece 1 8552 Rib 2 3-258 13-26 0-0725 •2950 1 „ „ Plain 1 2-708 2-738 36-389 13-29 0-8196 •2993 ) Piece 4 8552 Rib 2 36-305 13-26 0-8078 •2950 ] „ . Plain 1 0-050 0-0506 0-6645 13-29 0-0151 •2993 J Rib 2 0-6710 13-26 0-0149 •2950 The £ ibove piec :es of Ty] pe No. 851 52 as split jed up. Twin Core 8552 Plain 1 3-054 1 3-089 1 41-037 13-29 1 0-9244 | -2993 Rib 2 | 40-950 13-26 0-9111 •2950 Bottom. 137 cc Electrical Report. WATEKVILLE— CANSO (1884) NORTHERN. REPAIRS BY S.S. “BUCCANEER,” JULY, 1903. CABLE CUT OUT OF SECTION. Type. Picked up. Piece “ G.” 8502 “ H ” .55 55 5? ■ LA * 55 K ” 55 55 55 55 Abandoned „ Cut off Waterville end for Splice. Core. N.M. Sheathing. 450/ 270 = 0*157 17 /2 === 1*178 59 0*083 95 === 1*774 = 0*008 Total = 3*200 EXPENDITURE OF CABLE. Core. n.m. SA. No. 2147 A 225 /225 16 /l3 cwt. = 3*673 Cut off for Splice to Canso end = 0*008 Total laid in between buoys = 3*665 N.M. Laid in Section = 3*665 Cut out of Section = 3*200 Increase in length = 0*465 Former length of Waterville — Canso Section Increase by “ Buccaneer ” Present length N.M. = 2370*880 = 0*465 = 2371*345 138 Electrical Report. WATERVILLE— CANSO (1884) NORTHERN. REPAIRS BY S.S. “BUCCANEER,” JULY, 1903. CABLE CUT OUT OF SECTION. Type. Picked up. Piece “ Gr.” 8502 55 !) » AA * II 55 55 55 -**-• 55 Abandoned „ Cut off Waterville end for Splice. EXPENDITURE Core. SA. No. 2147 A 225 /225 Cut off for Splice to Canso end Core. N.M. Sheathing. 450/270 = 0-157 17 /2 = 1-178 ?? = 0-083 = 1-774 = 0-008 Total = 3-200 OF CABLE. « N.M. l ^/l3 cwt. = 3-673 = 0-008 Total laid in between buoys == 3 '665 Laid in Section Cut out of Section ... N.M. = 3-665 = 3-200 Increase in length = 0-465 Former length of Waterville — Canso Section ... Increase by “ Buccaneer ” Present length N.M. = 2370-880 = 0*465 = 2371-345 138 WESTON — WATERVILLE No. 1 CABLE REPAIR EXPEDITION. DECEMBER, 1903. l JrC' J±J IP _A_ I IRv TO THE Weston— Watenulle Bo. X Cable. S.S. “BUCCANEER.” DECEMBER, 1903. 3 GENERAL INDEX. Meston— MatervUle Bo. 1 Cable Repair Bjpebttion, December, 1903. S.S. “BUCCANEER.” PAGE GENERAL REPORT 9 List of Staff, Officers, Cable Hands and Crew 15 Mechanical Description of Cable 19 Drum Co- Efficients 22 Distribution of Cable in Ship on Leaving the Thames 23 Distribution of Weight in Ship on Leaving the Thames 24 Note previous to Leaving Silvertown 27 Leaving the Thames and Steaming down Channel 27 Anchored in Falmouth Harbour 30 Steaming to Waterville 31 On Cableground, Grappling, etc 33 Anchored in Valencia 37 Returned to Cableground 39 Testing, Splicing, etc 40 Slipped Final Splice 43 Steaming to London 44 Arrival in Victoria Dock 46 Distribution of Cable in Ship on Arrival in London ... ... ... 47 Distribution of Weight in Ship on Arrival in London ... ... ... 48 Index to Electrical Report 51 ELECTRICAL REPORT 53 5 GENERAL REPORT. WESTON— WATERVILLE No. 1 CABLE BEPAIB. GENERAL REPORT. S.S. “ Buccaneer,” January 1st , 1904. M. H. Gray, Esq., Silvertown. Dear Sir, On December 9th, the S.S. “ Buccaneer ” was chartered by the Commercial Cable Company to repair the above Cable, the position of fault being given as 1-5 n.m. from Waterville. The ship left Silvertown at 7.45 a.m., December 12th, after taking on board 1-660 n.m. S.E. Cable, No. 8556, and 0-115 n.m. S.E. Cable, No. 8567, barged from Messrs. Siemens’, in addition to the Commercial Cable Company’s Cable already on board. On the passage out we encountered strong SE to SW gale, having to take shelter in St. Helen’s Bay on the 13th, and to put back from the Lizard to Falmouth on the 15th, being unable to keep our course after rounding the Lizard. On December 18th we arrived off Waterville and took Pilot O’Neill on board, and, as the weather was unfavourable for working in the Bay, proceeded to Valencia. While there, I went over to Waterville and saw Mr. Wilmot, arranging with him that we should have daily weather reports from Waterville. On December 19th, as weather was improving, we proceeded to Waterville and put down mark-buoy. Beyond this, work was impossible, as the weather set in thick and obscured the land, so we anchored for the night. On the 20th we made six drags, picking up and slipping twice what we took to be the Havre Cable, and also once the Southern 1884 Cable. I may mention that where we were working there are seven cables within the mile. On the sixth drag 9 dd 2 General Report. we got the Weston No. 1 Cable, which was recognised by its having three reverse lay strands in outer sheathing. As dark was setting in, and blowing from SSE, we were unable to continue work, so after buoying both ends, anchored for the night. As the weather increased during the night, and as our anchorage was not good holding ground, we ran for Valencia at daylight. On December 24th we picked up Weston and spoke. Tests to Weston “ O.K.” Waterville end gave dead earth close to ship, and on picking up 0T50 n.m. a bad chafe came in, extending about three feet. Of the outer sheathing only two strands and one wire were standing, and of the inner only seven wires. The cores were scarfed with the chafe, Waterville end being about £" and Weston y with conductor exposed in both cases. The cable on both sides of the 0T50 n.m. cut out was in good condition and no signs of chafe or corrosion. As tests to Waterville were now “O.K.” and shoreward cable appeared in good condition, the No. 8567, plus 8556 in after tank, was spliced on, and the final bight slipped at 4.17 a.m., December 25th, in 12J fathoms. The total cable picked up was 0-154 n.m., and put in 0*226 n.m., increasing the length of section by 0*072 n.m. In the No. 8567 put in there were no “reverse lay” strands in outer sheathing as in original cable, whikh has three strands reverse lay, and in the No. 8556 both cores were plain. At daylight Mr. Cann and myself landed at Waterville, and on hearing from Mr. Wilmot that the final tests were satisfactory and that there were no further instructions for us, the “ Buccaneer ” left for London at 0.35 p.m., arrived off Gravesend Monday morning, December 28th, and made fast alongside the “ Silvertown,” Victoria Docks, the same afternoon. Herewith I enclose copy of Engineer’s Log and Electrical Report for the Expedition. I am, dear Sir, Yours faithfully, F. C. CRAWFORD. 10 WESTON- WAT ERVILLE No. 1 CABLE REPAIR. S.S. “BUCCANEER.” DECEMBER, 1903. LIST OF STAFF, OFFICERS, CABLE HANDS AND CREW. S.S. “BUCCANEER.” 13 S.S. “BUCCANEER.” LIST OF STAFF, OFFICERS, CABLE HANDS AND CREW. Mr. F. C. Crawford ,, P. Bates ,, H. E. Cann ... „ E. H. Walker Mr. B. C. Combe ,, J. S. Roberts ,, Y. Jones „ H. D. Emery W. Mackenzie J. Kelly ... C. Collins... 1 Lamp Trimmer 4 Quartermasters 6 Able Seamen. Mr. A. White „ W. Macfarlane ,, J. W. Cadman ,, 0. Reed J. Maguire A. Gooch ... 6 Firemen. 4 Trimmers. Mr. A. Patrick ... T. Brackett T. Williams C. Praerman D. Pratt ... 2 Assistant Stewards. 1 Scullion. 1 2nd and 3rd Class Caterer. 1 Engineers’ Steward. Engineer in Charge. Assistant Engineer. Electrician. Accountant. Captain. Chief Officer. 2nd 3rd ,, Carpenter. Boatswain. Boatswain’s Mate. Chief Engineer. 2nd 3rd 4th ,, Donkeyman. Electric Light Driver. Chief Steward. 2nd Steward and Storekeeper. Chief Cook and Baker. 2nd Cook and Butcher. Pantryman. 15 S.S. “BUCCANEER.” CABLE HANDS. W. Tillyer ... C. Buckmaster R. Schwartz A. Smith ... D. Archard W. Mack ... H. Marshall A. Harris ... H. Livingstone A. Newton R. Malt Foreman. Leading Hand. Cable Hand. »> >> >> ft ft it Fitter. Fitter’s Mate. Jointer. \ SUMMARY. Staff 4 Cable Hands ... ... ... ... ... 11 Officers and Crew ... ... ... ... 46 Total on board leaving London 61 MECHANICAL DESCRIPTION OF CABLE. S.S. “BUCCANEER.” 17 S.S. “BUCCANEER.” MECHANICAL DESCRIPTION OF CABLE. Siemens’ Main Cable, their Factory No. 8512 (Single Core). Conductor : — Strand of 7 copper wires, "023, weighing 70 lbs. per n.m. Dielectric : — Gutta percha, one coat to "*205, weighing 75 lbs. per n.m. Serving : — Tanned jute yarn. Sheathing : — 10 B.B.G.I. wires, "143 dia. Outer Serving : — Two coats of prepared jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = 2"*875. Weight in air, dry = 2*138 tons per n.m. „ „ wet = 2*173 „ ,, in sea water =1*433 ,, ,, Siemens’ H.I. Cable, their Factory No. 8514 (Single Core). Conductor : — Strand of 7 copper wires, "*023, weighing 70 lbs. per n.m. Dielectric: — Gutta percha, "*205, weighing 75 lbs. per n.m. Serving : — Tanned jute yarn. Sheathing : — 10 B.B.G.I. wires, "*238 dia. when galvanized. Outer Serving : — Two coats jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = 1"*393. Weight in air, dry = 5*437 tons per n.m. „ „ wet = 5*526 „ „ „ in sea water =3*873 „ ,, 19 S.S. “ BUCCANEER.” Siemens’ L.I. Cable, their Factory No. 8553 (Twin Core). Conductor : — Plain copper wire, weighing 90 lbs. per n.m. Dielectric : — Gutta percha, weighing 85 lbs. per n.m. Two Cores as above, one marked with “ Rib,” the other “ Plain,” laid np, wormed and served with tanned jute yarn. Sheathing : — 15 G. Homo, wires, No. 9 L.S.G.="*144 dia. when galvanized. Serving : — Two coats jute yarn prepared in compound, alter- nating with three coats of compound. Ex. diameter = 1"* 103. Weight in air, dry = 3*293 tons per n.m. ,, ,, wet = 3*420 ,, ,, in sea water = 2*241 ,, ,, Siemens’ Main Cable, their Factory No. 8552 (Twin Core). Conductor : — Solid plain copper wire, weighing 90 lbs. per n.m. Dielectric : — Gutta percha, weighing 85 lbs. per n.m. Two Cores as above, one marked with “ Rib,” the other “ Plain,” laid up, wormed and served with tanned jute yarn. Sheathing : — 17 G. Homo, wires "*124 dia. when galvanized. Serving : — Two coats jute yarn prepared in compound, alter- nating with three coats of compound. Ex. diameter = 1"*078. Weight in air, dry = 2*838 tons per n.m. ,, ,, wet = 2*900 ,, „ ,, in sea water = 1*798 ,, ,, Siemens’ S.E. Cable, their Factory No. 8556 (Twin Core). Conductor : — Plain copper wire, weighing 90 lbs. per n.m. Dielectric : — Gutta percha, weighing 85 lbs. per n.m. Two Cores as above, both “ Plain,” laid up, wormed and served with tanned jute yarn. 20 S.S. “ BUCCANEER.’ Inner Sheathing : — 20 B.B.G.I. wires, "'100 dia. Serving : — Jute and compound. Outer Sheathing : — 12 B.B.G.I. wires, "'300 dia. Outer Serving : — Two coats jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = 1"-916. Weight in air, dry = 11*65 tons per n.m. „ in sea water= 8'85 ,, ,, Siemens’ S.E.- Cable, their Factory No. 8567 (Twin Core). Conductor : — Plain copper wire, weighing 90 lbs. per n.m. Dielectric : — Gutta percha, weighing 85 lbs per n.m. Two Cores as above, one marked with “Rib,” the other “ Plain,” laid up, wormed and served with tanned jute yarn. Inner Sheathing : — 20 B.B.G.I. wires, "TOO dia. Serving : — Jute and compound. Outer Sheathing : — 12 strands of 3 B.B.G.I. wires, each "-220 dia. Outer Serving : — Two coats jute yarn prepared in compound, alternating with three coats of compound. Ex. diameter = 2"-895. Weight in air, dry = 18-7 tons per n.m. ,, in sea water = 13'55 ,, ,, 21 S.S. “BUCCANEER” COMMERCIAL CABLE COMPANY’S REPAIRS. S.S. “BUCCANEER,” DECEMBER, 1903. DRUM COEFFICIENTS. Circumference of Drum = 17' 2J" Type. Circ. in inches. Revs. per N.M. Log. Fms. per Rev. Main, 8512 (1 Core) 2*875 348*867 2*5426596 2*908 H.I., 8514 „ new... 4*375 346*385 2*5395594 2*929 „ old ... 4*250 346*590 2*5398169 2*927 L.I. 8558 (2 Core) 3*465 347*886 2*5414375 2*916 Main, 8552 3*387 348*016 2*5415988 2*915 S.E. 8567 9*093 338*805 2*5299498 2*994 „ 8556 6*020 343*704 2*5361847 2*952 Rope 4x6 4*646 345*940 2*5390016 2*932 „ 4X4 3*860 347*233 2*5406213 2*922 „ 3x3 2*700 349*159 2*5430228 2*905 22 COMMEBCIAL CABLE COMPANY’S BEPAIBS. S.S. “BUCCANEEB,” DECEMBEB, 1903. CQ s a w eh s w Eh 55 HH 5> ft P 55 O W m § « < o abfl m in b- ^ oo jO iG 00 0O 00 00 a :: ^ >< ◄ a a & m 23 EE After Tank ... 8-361 N.M. = 41*85 TONS. Fore Tank ... 4114 n.m. == 12*71 TONS. S.S. “BUCCANEER." DISTRIBUTION OF WEIGHT IN SHIP ON LEAVING THE THAMES. Cable in fore tank Ballast in ,, ,, Cable in after tank Ballast in ,, ,, Coal in bunkers Fresh water in after fresh water tank ,, ,, ,, fore cone ,, „ „ side tanks Water in ballast tanks forward , , , . . . aft Boatswain’s stores Cable stores and buoys Engine-room stores Water in main boilers... Steward’s stores Extra chain cable Spare anchors, ropes, etc. ,, propeller ... Deck machinery TONS. 12*71 41*85 200*00 13*00 8*00 4*50 70-00 *75 1200 2*50 30-00 7-00 1-00 , 200 3*00 10-00 Total = 418*31 tons Draught Forward 11' 9" Aft 14' 3" Mean 13' 0" 24 WESTON— WATERVILLE No. 1 CABLE REPAIR. LEAVING THE THAMES. S.S. “BUCCANEER,” 25 EE 2 S.S. “BUCCANEER.” NOTE PREVIOUS TO LEAVING SIVERTOWN. On Thursday, December 10th, 1903, a barge from Messrs. Siemens Bros. & Co. arrived alongside the “Buccaneer” with 1*660 n.m. of S.E. No. 8556 and 0*115 n.m. of S.E. No. 8567 Cable, belonging to the Commercial Cable Company, which was shipped the same day for the Commercial Cable Company’s Repair to the Waterville — Weston No. 1 Section. HOUE. A.M. 7.45 8.0 8.55 9.30 11.55 NOON. P.M. 0.10 1.30 1.36 2.5 3.6 4.0 5.55 6.11 LEAVING THE THAMES. SATURDAY, DECEMBER 12th (1st DAY OUT). Unmoored ship from S.S. “Dacia,” and proceeded down river, Pilot Twist in charge. Light SE wind and overcast. Arrived off Greenhithe. Made ship fast to buoy. Proceeded to swing ship, assisted by tug “ Undaunted.” Light SE breeze. Eine and overcast. Bar. 29*59. Ther. 50° E. Messrs. Crawford and Cann, with cable hands, joined ship. Finished adjusting compass. Cast off from buoy and proceeded down river. Off Gravesend, eased down. Pilot Twist left ship and Pilot Letten boarded. Passed the Mucking. Strong SE breeze and cloudy. Bar. 29*52. Ther. 50° F. Eased engines. Brought up off Nore Light Vessel in 11 fms, 27 Steaming down Channel. S.S. “BUCCANEER.” HOUR, P.M. 8.0 MID. A.M. 4.0 8.0 8.22 9.4 9.48 11.33 NOON. P.M. 0.45 2.0 4.0 4.47 5.45 8.0 9.48 11.2 SATURDAY, DEC. 12th (1st DAY OUT) — Contd. Strong SE wind and overcast. Bar. 29*50. Ther. 50° E. Mod. to Fresh SE gale. Overcast and raining. Bar. 29-45. Ther. 50° F. SUNDAY, DECEMBER 13th (2nd DAY OUT). Mod. SSW breeze. Raining. Bar. 29-45. Ther. 51° F. Hove up and proceeded. Similar wind and weather. Bar. 29*45. Ther. 51° F. Passed Prince’s Channel Light Vessel. Passed Margate NE buoy. North Foreland Lighthouse abeam. South ,, ,, ,, Mod. SSW wind and fine. Ship pitching heavily to high sea. Bar. 29-45. Ther. 50° F. STEAMING DOWN CHANNEL. Varne Light Vessel abeam. Dungeness, N 40° W, 2 n.m. Strong S breeze, and considerable sea, ship plunging heavily. Cloudy but fine. Bar. 29-42. Ther. 51° F. Royal Sovereign Light Vessel abeam. Beachy Head Light, distant 3 n.m. Similar wind and weather, shipping water to port. Bar. 29-45. Ther. 51° F. Passed Owers Light. Eased engines. 28 Steaming to Falmouth. S.S. “BUCCANEER.” HOUR. P.M. 11.35 MID. A.M. 4.0 6.30 8.0 8.26 9.30 11.27 NOON. P.M. 0M 4.0 5.5 8.0 9.56 MID. A.M. 0.40 2.56 SUNDAY, DEC. 13th (2nd DAY OUT) — Contd. Let go anchor in St. Helen’s Bay. Moderate to fresh SSW gale, cloudy, some rain. Bar. 29-56. Ther. 50° F. MONDAY, DECEMBER 14th (3rd DAY OUT). Light SW breeze and fine. Bar. 29-60. Ther. 52° F. Hove up anchor and set on for Ventnor to land Pilot Letten. Moderate SW breeze, and fine. Bar. 29-62. Ther. 52° 'F. Off Yentnor Pilot Letten left ship, ship proceeded down Channel. Needles abeam. Observed Portland Lighthouse. Similar wind, fine and cloudy. Portland Lighthouse abeam. Strong SE breeze, cloudy, moderate sea and swell. Bar. 29-63. Ther. 59° F. Eddystone Lighthouse abeam. Strong SSE breeze, squally, with rain ; heavy sea from starboard. Observed Lizard Light. Strong SSE breeze, squally with rain. Ship plunging heavily to high sea. Bar. 29-53. Ther. 57° F. STEAMING TO FALMOUTH. TUESDAY, DECEMBER 15th (4th DAY OUT). Lizard Lighthouse abeam, distant 8 n.m. Heavy SW swell and high S’ly sea. Ship unable to keep course. Rounded to and slowed engines. 29 Anchored in Falmouth Harbour. HOUE. A.M. 4.0 7.15 8.0 8.15 10.50 11.8 11.16 11.54 NOON. P.M. 4.0 6.30 8.0 MID. A.M. 4.0 8.0 9.30 NOON S.S. “BUCCANEER.” TUESDAY, DEC. 15th (4th DAY OUT) — Contd. Strong SSE gale. Cloudy, with rain at times. Similar weather. Keeping Lizard Light in sight. Turned ship, directed course to Lizard Light. Similar wind and weather, with high confused sea. Bar. 29-49. Ther. 52° E. Observed Lizard Lighthouse. Manacles abeam. Eased engines and took Falmouth Pilot Vincent on board. Proceeded towards anchorage. Moored ship in Falmouth Harbour. Similar wind and weather. Cloudy and raining. Bar. 29-56. Ther. 52° F. ANCHORED IN FALMOUTH HARBOUR. Moderate SE breeze, overcast and raining. Bar. 29-55. Ther. 60° F. Pumped up fore and after cable tanks. Strong SE wind and gloomy, overcast, with rain at times. Bar. 29-60. Ther. 68° F. Strong SSE breeze, squally, with rain. WEDNESDAY, DECEMBER 16th (5th DAY OUT). Strong SE breeze and occasional fine rain. Bar. 29-47. Ther. 60° F. Strong E wind and overcast, with rain at times. Bar. 29-55. Ther. 60° F. Mr. Crawford, Captain Combe, and Mr. V. Jones left ship for the Meteorological Office to get weather reports and compare barometers, also to get weather reports from Waterville and the Lizard. Fresh ESE breeze with heavy rain. Bar. 29-50. Ther. 58° F. 30 Steaming to Waterville. S.S. “BUCCANEER.” HOUR. P.M. 4.0 7.0 8.0 10.35 MID. A.M. 4.0 6.0 6.45 7.41 8.0 8.5 8.37 9.0 9.46 11.36 NOON. WEDNESDAY, DEC. 16th (5th DAY OUT) — Contd. Similar wind and weather. Bar. 29-55. Ther. 56° F. Pumped up forward cable tank. Moderate ESE breeze, squally, with rain. Bar. 29-58. Ther. 56° F. Mr. Crawford, Captain Combe, and Mr. Y. Jones returned to ship. Moderate ESE breeze, squally, with heavy rain. Bar. 29-61. Ther. 55° F. During the day Mr. Cann tested cable in fore and aft tanks. STEAMING TO WATERVILLE. THURSDAY, DECEMBER 17th (6th DAY OUT). Mod. NTy breeze and misty. Bar. 29-17. Ther. 52° F. Pumped up after cable tank. Hove short. Pumped up after ballast tank. Hove up anchor and proceeded out of harbour, Pilot Fittock in charge. Light NNW breeze. Cloudy and overcast. Bar. 29-75. Ther. 53° F. Pilot left ship. Manacles abeam. Black Head abeam. Lizard Lighthouse abeam. Longships ,, ,, Light N’ly breeze and fine. Bar. 29-82. Ther. 56° F. Distance run from Falmouth = 46 n.m. -p . f Lat. 50° 6' N. Position | Lon go 51 ,. 5 w _ 31 HOUR. P.M. O. 43 4.0 8.0 MID. A.M. 3.18 4.0 6.3 8.0 9.0 10.47 NOON P. M. 1.0 4.0 8.0 MID. Steaming to Waterville. S.S. “BUCCANEER.” THURSDAY, DEC. 17th (6th DAY OUT) — Gontd. Seven Stones Light Vessel abeam. Light SE breeze and fine. Moderate SW swell. Bar. 29-78. Ther. 60° F. Similar wind and weather. Smooth sea. Bar. 29-76. Ther. 59° F. Mod. E’lv breeze and fine. Passing clouds. Bar. 29-63. Ther. 58° F. FRIDAY, DECEMBER 18th (7th DAY OUT). Fastnet Light abeam. Strong ESE breeze and following sea. SW swell. Bar. 29-45. Ther. 68° F. Bull Rock Light abeam. Similar wind and weather. Heavy sea and swell. Bar. 29-43. Ther. 61° F. Off Horse Island. Stopped ship and took Pilot O’Neill on board. Decided to proceed to Valencia Harbour on account of weather. Passed Valencia Lighthouse. Strong ESE breeze. Overcast, with fine rain. Bar. 29-48. Ther. 53° F. Pumped up after cable tank. Messrs. Crawford, Cann and Captain Combe left for shore to go to Waterville Cable Station. Mod. ESE breeze and raining. Bar. 29-57. Ther. 54° F. Fresh ESE breeze. Overcast, rain at times. Bar. 29-65. Ther. 54° F. Similar wind and'weather. Bar. 29-68. Ther. 55° F. 32 On Cableground. S.S. “BUCCANEER.” HOUR. A.M. 4.0 8.0 10.0 10.25 11.25 NOON. P.M. 0.42 2.0 3.0 4.0 4.15 8.0 MID. A.M. 4.0 7.15 SATURDAY, DECEMBER 19th (8th DAY OUT). Light SSE breeze and fine. Bar. 29*75. Ther. 59° F. Similar wind and weather. Bar. 29*75. Ther. 54° F. Messrs. Crawford and Cann, with Captain Combe, came on board. Hove up anchor and proceeded to Waterville. Bray Head Tower abeam. Light SSE wind, with fine rain at times. Heavy W’ly swell. Bar. 29*86. Ther. 60° F. Reduced speed in Ballinskellig Bay. Dodging around taking angles. Slipped Mark Buoy, No. 72, blue flag. Mark Buoy 0*05 n.m. N of ship. Lohar R.C. Church Old Watch Tower < Western Pig Rock Horizontal Angles ° 00 ' 30 ' Light NNW wind. Misty, and fine rain at times. Bar. 29*87. Ther. 61° F. Anchored in 8 fms. with port anchor. Veered to 45 fms. chain. Light N’ly breeze, with rain at times. Bar. 29*87. Ther. 62° F. Light NNE breeze. Fine, with passing clouds. Bar. 29*92. Ther. 56° F. ON CABLEGROUND. SUNDAY, DECEMBER 20th (9th DAY OUT). Light NE’ly airs and fine. Slight mists. Bar. 29*94. Ther. 49° F. Hove up anchor and set on for grappling position. 33 On Cab'leground. S.S. “ BUCCANEER.” HOUR. A.M. 8.40 SUNDAY, DEC. 20th (9th DAY OUT). — Contd. In position. Lowered short toe ordinary grapnel with centipede trailing, and 10 fms. J" chain, and commenced paying out 4x4 grappling rope. 8.45 9.0 9.5 9.8 9.30 9.42 9.45 10.0 10.5 10.7 10.10 10.17 Drag No. 1. Paid out to 30 fms. of rope. No strain. Bottom rocky. Strain rose. Commenced picking up. Grapnel at bows with cable, 12 wires "*350 dia. This taken to be the Waterville — Havre Section. Cable in good state, one broken wire showing. ( Lohar R.C. Church l ggo q* Old Watch Tower < Western Pig Rock} 47 45 Slipped Waterville — Havre Section with balloon buoy attached, and set on for new position to drag nearer shore. Lowered grapnels as in Drag No. 1. Drag No. 2. Paid out to 30 fms. of rope. Strain rose to 60 cwt. and fell to nil. Rocky bottom. Over line of cable. Commenced picking up. Decided to resume drag a little further. Paid out again. Strain rose. Commenced to pick up. Cable at bows. This has every appearance of being the same cable as hooked in Drag No. 1. Decided to slip this. ( Lohar R.C. Church 1 ggo 45 1 Position \ Old Watch Tower j (Western Pig Rock j 44 4& Slipped cable. Set on to drag again. In position. Lowered grapnels as in Drag No, 2. 34 10.25 10,30 On Cableground. S.S. “BUCCANEER.” HOUR. A.M. 10.32 10.35 10.38 10.42 11.15 11.17 11.30 11.40 11.45 NOON P.M. 0.9 0.11 0.45 0.50 1.0 1.15 SUNDAY, DEC. 20th (9th DAY OUT) — Contd. Drag No. 3. Paid out to 30 fms. of 4 x 4 rope. Grapnel continually hanging. Strain rising and falling. Strain steadily rose to 80 cwt. Commenced picking up. 13 fms. of rope out. Strain suddenly fell to nil. Grapnel up. No cable. In position. Lowered grapnels as in Drag No. 3. Drag No. 4. \ Paid out to 30 fms. of 4 x 4 rope. Over line of cable. Commenced picking up. Grapnels up. No cable. No strain during this drag. Observed boat put off from Waterville Beach, set on towards boat. Boat came alongside. Mr. Wilmot, Superintendent at Waterville, came on board. Mod. SSE breeze. Fine. Passing clouds. Bar. 30 05. Tber. 54° F. In position. Lowered grapnels as in Drag No. 4. Drag No. 5. Paid out to 30 fms. of 4 x 4 rope. Strain rose to 80 cwt. and fell to nil. Commenced picking up. Strain whilst picking up = 70 — 80 cwt. Picking up very slowly. Strain = 100 cwt. >> 140 cwt. Grapnel at bows with cable (one toe gone from ordinary, two toes from centipede). Strain = 140 cwt. Cable very taut. Position Lobar R.C. Church leeo onr ■ Old Watch Tower ] , Western Pig Rock | ^0 30 Sounding = 13 fms. 35 On Gableground. S.S. “BUCCANEER.” HOUR. P.M. 1.17 1.30 1.40 2.10 2.12 2.20 2.35 2.37 2.43 2.45 2.55 3.26 3.45 3.51 4.0 4.15 4.20 SUNDAY, DEC. 20th (9th DAY OUT) — Contd. Decided to slip this cable, believing it to be the Southern Section (12/"-350, 2 tapes). Cable in good state. No chafe. Slipped cable. Changed ordinary and centipede grapnels for one short toe ordinary grapnel. In position. Lowered short toe ordinary grapnel with 10 fms. f" chain, and commenced paying out 4x4 rope. Drag No. 6., Paid out to 30 fms. 4x4 rope. Strain rose steadily to 60 cwt. Commenced picking up. 20 fms. of rope out. Strain fell to nil. Paid out again to 30 fms. and resumed drag. Strain rose to 80 cwt. Commenced picking up. 20 fms. outboard. Strain fell to nil. Grapnel at bows. Lowered away again and resumed drag. Strain steadily rose 30—40 cwt. Commenced picking up. Grapnel at bows with stranded cable (Weston — Water- ville No. 1). Got drum ropes along and made fast to each side of cable. Took grapnel in board. Commenced cutting cable. Cut cable. Hove end towards Waterville on board for testing. Commenced testing. Mod. SSE breeze. Clear, cloudy weather and fine. Bar. 29'92. Ther. 52° E. Finished testing to Waterville. Tests gave earth close to ship. Prepared to buoy end. Attached moorings to Waterville end. 36 Anchored at Valencia. S.S. “ BUCCANEER.” HOUR. P.M. 4.30 4.35 4.42 4.50 4.56 5.10 7.45 8.0 MID. A.M. 4.0 8.0 SUNDAY, DEC. 20th (9th DAY OUT). — Contd. Let go buoy on Waterville end. Position Lokar R.C. Church 1 590 45 r 38° 30' Soundings 13 fms. Old Watch Tower ^Western Pig Rock Moorings . — Buoy No. 71, red flag. 10 fms. of §" chain, 10 fms. of J" chain. Mushroom = 2 cwt. 1 qr. 10 lbs. Hove in Weston end for testing. Commenced calling Weston. Preparing to buoy this end, as dark setting in and sea increasing. Finished with Weston. Attached moorings to Weston end. Could not read Weston, owing to their employing too strong battery. Let go buoy on Weston end. Set on for anchorage. Darkness coming on, making angles unobtainable. (Lohar R.C. Church jgQo ^ Position] Old Watch Tower < Sounding = 13 fms. (Western Pig Rock j **9 ^0 Moorings . — Buoy No. 63, “N” flag. J" bridle, 20 fms. |-" chain, 10 fms. §" chain, 2J fms. f" chain. Mushroom = 2 cwt. 0 qrs. 15 lbs. Let go port anchor in 13 fms. Veered to 45 fms. chain. Veered to 60 fms. chain. Mod. to fresh SE breeze. Overcast and fine. Bar. 29*96. Ther. 58° F. Fresh SSE wind. Overcast, with hard squalls. Bar. 29-89. Ther. 58° F. ANCHORED AT VALENCIA. MONDAY, DECEMBER 21st (10th DAY OUT). Strong gale, SE, with fierce squalls of wind and rain. Bar. 29-92. Ther. 52° F. Similar wind and weather. Bar. 29-88. Ther. 56° F. Decided to proceed to Valencia for shelter on account of weather, 37 HOUR. A.M. 9.10 9.25 10.45 11.25 11.35 NOON. P.M. 3.30 4.0 8.0 MID. A.M. 4.0 8.0 NOON. P.M. 4.0 8.0 MID. Anchored at Valencia. S.S. “ BUCCANEER.” MONDAY, DEC. 21st (10th DAY OUT) — Gontd. Hove up anchor and proceeded. Hog Head abeam. Bray Head abeam. Passed Valencia Lighthouse. Let go port anchor in Valencia Harbour. Veered to 45 fms. chain. Strong SW wind. Heavy squalls, with rain. Bar. 29-82. Ther. 58° F. Mr. Wilmot left ship to proceed to Waterville. Similar wind and weather. Bar. 29-72. Ther. 55° F. Strong SE breeze. Heavy squalls, with rain. Bar. 29-80. Ther. 56° F. Strong SWS breeze and similar weather. Bar, 29-83. Ther. 57° F. TUESDAY, DECEMBER 22nd (11th DAY OUT). Strong SW breeze to gale. Raining and overcast. Bar. 29-77. Ther. 56° F. Similar wind and weather. Bar. 29-76. Ther. 60° F. Strong SSW wind. Fine, cloudy and squally. Bar. 29-78. Ther. 56° F. Strong WSW breeze. Cloudy and squally. Bar. 29-77. Ther. 55° F. Similar wind and weather. Bar. 29-77. Ther. 55° F. Mod. NW wind, with passing rain squalls. Bar. 29-94. Ther. 54° F. 38 On Gableground. S.S. “BUCCANEER.” HOUR. A.M. 3.30 4.0 8.0 10.0 NOON. P.M. 4.0 8.0 MID. A.M. 4.0 8.0 8.3 10.20 10.25 10.33 WEDNESDAY, DECEMBER 23rd (12th DAY OUT) Hail squall. Fresh NW breeze and fine. Bar. 29-98. Ther. 51° F. Light variable airs and fine. Bar. 30-06. Ther. 48° F. Getting ready for sea, but on advice from Waterville that heavy sea was running there, decided to remain. Mr. Crawford, and Captain Combe and Mr. Cann went ashore at Beginnis Island to observe weather outside. Found heavy sea running in from westward. Light variable airs and fine. Bar. 30-04. Ther. 47° F. Calms and fine weather. Heavy surf breaking outside. Light variable airs and fine weather. Bar. 30 09. Ther. 51° F. Similar wind and weather. Bar. 30-06. Ther. 51° F. ON CABLEGROUND. THURSDAY, DECEMBER 24th (13th DAY OUT). Calms and light airs. Fine. Bar. 30*08. Ther. 48° F. Light variable airs and fine. Bar. 30-12. Ther. 48° F. Hove up anchor and proceeded to Waterville (Cable- ground). Arrived in Waterville Bay, and up to Buoy “N ” on. Weston end of cable. Lowered boat and sent her away with drum rope to dismantle buoy. Freed buoy from mooring and commenced picking up same. Weston end on board. 39 FF On Cableground. S.S. “ BUCCANEER.” HOUR. A.M. 10.37 11.40 11.26 11.30 11.33 11.45 11.50 11.51 11.55 NOON. P.M. 0.15 0.40 0.50 1.33 1.55 2.0 2.30 THURSDAY, DEC. 24th (13th DAY OUT). — Contd. Commenced testing to Weston. Captain Combe went away in boat to take soundings and put down mark (oil drum) for ship’s depth limit. Finished testing to Weston. Sealed end and prepared to buoy same. Cable to Weston “ O.K.” Captain Combe returned to ship. Sounded No. 1 T — 11J fms. Bot. Temp., 48J°F. Air, 53° F. S.S. 55° F. Ther. No. 134463. Commenced paying out moorings on Weston end. All moorings paid out. Let go Buoy “ Y ” flag on Weston end. Moorings . — Buoy No. 63, flag “ V.” J" bridle, 30 fms. £" chain, 2J fms. f" chain. Mushroom = 2 cwt. 0 qrs. 15 lbs. Set on for buoy on Waterville end. Up to buoy. Sent boat with drum rope to dismantle buoy. Calm. Fine, clear weather. Bar. 30-15. Ther. 52° F. Freed buoy from moorings and commenced picking up on Waterville end. Waterville end on board, off drum. Set indicator to zero and resumed picking up to fault. Ind. = 26 revs. = -078 n.m. Badly chafed. ,, 40 ,, -120 ,, Splice and broken strand. ,, 50 ,, -150 ,, Very bad place. Coreexposed. Cut cable at bad place and made fresh tests to Waterville. This bad place proved to be the fault. Finished testing to Waterville. Cable “ O.K.” Commenced opening out Waterville end for splice with S.E. Cable, No. 8567, on top in after tank. Took Waterville end off drum. Got up end of above S.E. from after tank, and commenced opening out same for splice with Waterville end. 40 S.S. “ BUCCANEER” HOUR. P.M. 3.20 3.26 3.30 3.42 4.0 5.30 7.10 7.25 7.35 7.40 7.44 8.0 8.7 8.10 8.30 THURSDAY, DEC. 24th (13th DAY OUT) — Gontd. Both ends ready for joint and splice. Commenced joints. Sent boat away to light up buoy on Weston end. Boat returned to ship. Calm and fine. Bar. 30-21. Ther. 53° F. Finished joints and started splice. ,, splice, and prepared to pay out through stoppers. Commenced paying out S.E. Cable, No. 8567, from after tank towards Weston buoyed end. Position of Splice Lohar R.C. Church J 540 45 > Old Watch Tower < ^Western Pig Rock j ^ By horizontal angles. Sounding = 10 fms. Splice S.E. 8567 and H.I. 8556 passed out board. Up to buoy on Weston end. Lowered boat, and sent her with drum rope to dismantle buoy. Freed buoy from moorings, and commenced picking up Weston end. Light airs and calms, with fine weather and heavy dew. Bar. 30-17. Ther. 55° F. Enough Weston end inboard for splice. Put hanging ropes and stoppers on cable, and took turns off drum. „ Sent S.G. : “Crawford to Wilmot.” “ After slipping final will proceed to sea for night, returning to pick up buoys at daylight, and if weather favourable will land ; otherwise proceed to Valencia and drive over for tests. Weston end now on board. Please send to-day’s weather report.” Commenced testing to Weston. pf 2 41 On Cableground. S.S. “BUCCANEER.” HOUR. P.M. 8.35 10.0 10.7 11.35 11.35 MID. A.M. 0.30 2.30 2.40 3.15 4.0 4.5 THURSDAY, DEC. 24th (13th DAY OUT) — Contd. Received S.G. : “ Here is the forecast : ‘ Colder, unsettled, some snow or sleet. Easterly and NE’ly winds, increasing in force.’ ” Sent S.G. : “ Crawford to Gott.” “ About to make final. Weather promising. Will see Mr. Wilmot to-morrow for tests and your instructions. Compliments of the Season from all.” Sent S.G. : “ ‘ Silvergray, London’, and Gray, Lessness Park, Abbey Wood, Kent.” “ Thursday, 10 p.m. About to make final splice. Will see Waterville re tests and instructions. All well. Compli- ments of Season from all. — Crawford, ‘ Buccaneer.’ ” “ Crawford to Wilmot.” “ Now about to make final splice. Please advise Weston to call you at 3 a.m. We will see you to-morrow. Compli- ments of the Season from all.” “ Wilmot to Crawford.” “ Thanks, I cordially wish you all the same.” Gave out both ends for splice. No indicated length taken as cable paid out through stoppers. Light variable airs. Fine and overcast. Bar. 30*18. Ther. 56° F. FRIDAY, DECEMBER 25th (14th DAY OUT). Commenced joints. Finished ,, Commenced splice. Sounded No 2 T — 10 fms. Air Temp., 51° F. Bot., 49|° F. S.S., 52° F. Finished splice. Light NE airs and fine. Bar. 30Y7. Ther. 52° F. Commenced paying out final splice by hanging ropes. 42 On Cableground. S.S. “BUCCANEER.” HOUR. A.M. 4.17 4.20 8.0 8.30 8.40 10.7 NOON. P.M. 0.3 0.35 1.55 FRIDAY, DEC. 25th (14th DAY OUT). — Gontd. Cut hanging ropes and slipped final splice, thus completing the Repair to the Commercial Cable Co.’s Weston — Waterville No. 1 Cable. ( Lohar R.C. Church l gno ogr Old Watch Tower { Western Pig Rock j ^9 By horizontal angles. Sounding = 12-| fms. Total Cable Expended. Type 8567 = 0-1150 n.m. „ 8556 = 0-1245 „ Total = 0-2395 ,, Cut out of Section. Shore End type = 0-1 50 n.m. Cut off Weston ) _ >nn . End for Splice J ” •154 „ Laid in Section. Type 8567 = 0-1080 n.m. (5 fms. splice.) „ 8556=0-1185 „ Total = 0-2265 „ Laid in = 0-2265 n.m. Cut out =0-1540 ,, 0-0725 ,, Increase Set on to dodge till daylight. Light NNE breeze. Fine. Bar. 30-17. Ther. 52° F. Picked up balloon buoys put down for marks on Sunday last. Picked up Mark Buoy “B.” Messrs. Crawford and Cann left for shore to get result of final tests, and instructions. Calm and fine weather. Bar. 30-17. Ther. 53° F. Messrs. Crawford and Cann returned to ship. Set on for London. Pilot O’Neill left ship off Horse Island. Bull Island abeam. 43 Steaming to London. S.S. “BUCCANEER.” HOUR. P.M. 3.46 4.0 4.38 8.0 MID. A.M. 4.0 8.0 8.22 10.34 NOON. P.M. 4.0 4.55 8.0 MID. A.M. 2.38 4.0 FRIDAY, DEC. 25th (14th DAY OUT) — Contd. Mizen Head abeam Light ESE airs and calm sea. Fine and clear. Bar. 30-19. Ther. 52° F. Fastnet abeam. Mod. variable breeze and fine. WSW swell. Bar. 30-14. Ther. 48° F. Light ENE wind and fine. Bar. 30*08. Ther. 44° F. STEAMING TO LONDON. SATURDAY, DECEMBER 26th (15th DAY OUT). Light N’ly airs and fine. Bar. 30-03. Ther. 46° F. Mod. NE wind and cloudy. Passing hail and sleet. Bar. 30-00. Ther. 50° F. Longships Lighthouse abeam. Lizard Lighthouse abeam. Signalled Lizard Ship’s Number. Mod. ENE wind. Fine and cloudy. Bar. 29-94. Ther. 48° F. Fresh ENE breeze and fine. Cloudy- Bar. 29-97. Ther. 50° F. Start Point Light abeam. Fresh E wind and squally, with head sea. Hail and rain. Bar. 30-03. Ther. 49° F. Fresh E wind and squally, with rain and hail. Bar. 30-33. Ther. 54° F. SUNDAY, DECEMBER 27th (16th DAY OUT). St. Catherine’s Light abeam. Fresh E x N breeze. Passing clouds, but clear. Bar. 30-02. Ther. 54° F. 44 Steaming up River. S.S. “BUCCANEER.” HOUR. A.M. 8.0 9.15 10.2 NOON. P.M. 0.25 2.33 3.58 4.0 8.0 8.20 MID. A.M. 4.0 4.50 5.20 5.40 8.0 8.45 SUNDAY, DEC. 27th (16th DAY OUT). — Contd. Strong E wind and overcast. Bar. 30-08. Ther. 52° F. Beachy Head abeam. Royal Sovereign Light Vessel abeam. Strong E wind and overcast. Bar. 30-08. Ther. 45° F. Picked up Pilot, Mr. E. Bussey, off Dungeness and pro- ceeded. Signalled at Dover. Gull Buoy abeam. Fresh E breeze. Cloudy and fine. Bar. 30-17. Ther. 50° F. Mod. breeze (NNE). Overcast and showery. Bar. 30-07. Ther. 50° F. Brought up off Mucking Light with starboard anchor. Light NNE breeze. Passing rain and hail showers. Bar. 30-08. Ther. 53° F. STEAMING UP RIVER. MONDAY, DECEMBER 28th (17th DAY OUT). Light N wind and overcast. Passing hail and rain squalls. Bar. 30-10. Ther. 50° F. Hove up anchor and proceeded up river. Off Gravesend. Pilot Twist having not boarded, decided to anchor. Let go starboard anchor. Light N wind and overcast. Bar. 30-12. Ther. 49° F. Pilot Twist boarded. Pilot Bussey left. Ship too late for a.m. tide. 45 Arrived in Victoria Dock. S.S. “BUCCANEER.” HOUR. A.M. 9.20 NOON. P.M. 1.20 2.54 3.51 4.0 4.7 5.0 6.35 8.0 2.0 MONDAY, DEC. 28th (17th DAY OUT). — Contd. Messrs. Crawford, Cann, and Walker left ship. Light N wind, with sleet at times. Hove up anchor and proceeded up river towards the Royal Albert Docks. Anchored of Dock gates. Hove up anchor. Light N wind. Fine and overcast. Bar. 30-15. Ther. 49° F. Entered Lock. Entered Victoria Dock. Entered berth to await for Dry Dock. Light N wind. Fine and cloudy. Draught of Ship j 3 J Mean = 11' 7". TUESDAY, DECEMBER 29th. All hands paid off and discharged. 46 COMMERCIAL CABLE COMPANY’S REPAIRS. S.S. “BUCCANEER,” DECEMBER, 1903. 1-a a> :=3 a> ph 2 o oS H P3 ryH Ol do -rfi k3 <1 H O Eh 47 • COMMERCIAL CABLE COMPANY’S WESTON— WATERYILLE No. 1 CABLE REPAIR. S.S. “ BUCCANEER,” DECEMBER, 1903. DISTRIBUTION OF WEIGHT IN SHIP ON ARRIVAL IN LONDON. Cable in fore tank ,, after ,, Coal in bunkers Fresh water in after fresh water tank ,, ,, fore cone ,, ,, side tanks Water in ballast tank — forward n aft Boatswain’s stores Cable stores and buoys Engine room stores Water in main boilers Steward’s stores Extra chain cable Spare anchors, ropes, etc. ,, propeller ... Deck machinery Tons. 12-71 38-27 75-00 6-00 4-50 70-00 •50 11-50 2- 25 30-00 2-00 1-00 2-00 3- 00 10-00 Total ... 268-73 tons Draught of ship on arrival j | Mean = 1 1 f 7" 48 WESTON— WATERVILLE No. 1 CABLE REPAIR. S.S. “BUCCANEER.” ELECTRICAL REPORT. 49 INDEX TO ELECTRICAL REPORT. Weston — Waterville No. 1 Repair Report Cover Sheet Section Sheet, Plain Core, A 99 99 5 ? 99 99 99 Section Sheet, Rib Core, A i 99 99 99 99 9 ? 99 *9 99 99 99 B C D Distribution of Cable in Tanks on Leaving the Thames, 12.12.03 Factory Electrical Values at 75 ° F. of Cable on board on Leaving the Thames, 12.12.03, Fore Tank Ditto After Tank Distribution of Cable in Tanks on Return to Thames, 28.12.03 Factory Electrical Values at 75° F. of Cable on board on Return to the Thames, 28.12.03, Fore Tank Ditto After Tank Expenditure Table ... Diagram showing Operations during Repair PAGE 53 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 51 ELECTRICAL REPORT. F. C. Crawford, Esq., Engineer in Charge. S.S. “ Buccaneer .” December 31st , 1905. Dear Sir, On December 9th the S.S. “Buccaneer” was chartered by the Commercial Cable Company for the purpose of removing a fault in the Weston No. 1 Cable (twin core), both cores being faulty at the same place. The fault had been localised by Loop test from Weston, U) and its position placed at 20 from Waterville Office. This resistance — at the sea temperature — represented a cable distance of 1*57 n.m from Waterville Offiee, or 1*25 n.m. from H. — W. mark, Waterville Beach. On the 11th inst. Weston reported no continuity on both cores. After shipping cable from Silvertown Works, and two lengths of cable ex barge “Wilts,” from Siemens’ Bros., viz., 0T15 n.m. of Type 8567, and 1*660 n.m. of Type 8556 — see Loading Table — the S.S. “Buccaneer” left her moorings off Silvertown, on December 12th, 7.45 a.m., and after adjusting compasses at Greenhithe, cast off from buoys at 1.36 p.m. same afternoon, and proceeded for Waterville. After a very rough passage, having to shelter en route at the Nore, Isle of Wight, and Falmouth, the ship arrived off Horse Island, Ballinskelligs Bay, at 9 am., December 18th, where Pilot O’Neill boarded, and owing to the heavy weather prevailing, proceeded to Valencia Harbour for shelter, anchoring there at 11 a.m. same morning. Note. — While in Falmouth Harbour the opportunity was taken to cover the cable in both tanks with water, and all sections of cable 53 Electrical Beport. were tested. The results were quite satisfactory, with the exception of spliced section, Type 8512, length = 4*95 n.m. This cable showed a weakness, the electrification readings being irregular with both currents, and after the application of 450 volts the D.R. per n.m. o decreased from over 700 per n.m. to 200 approx. Shortly after anchoring at Valencia, Messrs. Crawford, Cann, and Captain Combe proceeded by car to Waterville to interview Mr. Wilmot re work in hand, and to receive any further instructions. Mr. Cann also arranged with Mr. Wilmot — having regard to the long length in circuit on the Weston side — to work Mirror with Weston, using two to three cells only. The following morning (19th inst.), the wind having abated, weighed anchor and proceeded for Waterville. Placed Mark Buoy, and angles were taken to determine position of cable. Anchored for the "night at 4.15 p.m. in Ballinskelligs Bay. The next day — Dec. 20th, 8.40 a.m. — lowered grapnel for Drag No. 1, and hooked cable, which on being brought to the surface was taken to be the Harve — Waterville Section. This cable was slipped without damage — its position being marked by a balloon buoy — and grappling resumed. Hooked same cable, which was again slipped and position marked. Drags 3 and 4 were unsuccessful, but Drag 5 hooked a cable (1.17 p.m.) which was taken to be the “ Southern.” Slipped cable and resumed dragging. Note. — Mr. Wilmot, Superintendent at Waterville Station, joined ship at noon, having come off to ship in coastguard’s boat. At 2.45 p.m. hooked the Weston No. 1 Cable, and at 3.51 p.m. the Waterville end was handed to Testing Boom. Waterville was called without success, and tests were then taken by Cann’s method, and the fault found to be a short distance from the ship. Waterville end was then buoyed (4.30), and Weston end hove in for testing. On calling Weston very strong signals were received which were (!) quite unreadable, being off scale with 1* shunt and brash inserted. Weston was requested to decrease battery, and as darkness was 54 Electrical Report. approaching, and wind and sea increasing, it became imperative to buoy end immediately. Weston end was accordingly buoyed at 4.56 p.m., and the ship anchored off Rinneen Point at 5.10 p.m. During the night the wind increased, and next morning a strong SE gale was blowing. At daylight weighed anchor, and ran for Valencia, anchoring there at 11.35 a.m. The “Buccaneer” remained in Valencia Dec. 22nd and 23rd, a SSW gale prevailing. The weather having moderated on Dec. 24th, hove up anchor (8.3 a.m.) and proceeded to cableground, arriving alongside buoy on Weston end at 10.20 a.m. Weston end was raised, and on calling up at 10.35 a.m., ship received an immediate answer to call, Weston signals being good with an unshunted galvanometer. Ship now took a series of tests on Weston end. Conductor Resistance. (Cores looped at Weston.) Length in circuit = 328*796 n.m. C.R. of loop (corrected) = 8353*4 Plain core = 4174*3. Rib „ =4179*1. Calculated temperature by C. F. & T.’s co-efficient = 52°* 2 F. Dielectric Resistance. (30 volts.) ft o Plain core, P, Z., abs. = 20*09 = 6606* per n.m. at sea temp. ft ft Rib „ ,. =18*834 = 6195* „ Inductive Capacity. Kelvins Null Method. (30 volts.) Plain core = 100*77 mfds. Total. Rib „ = 99*69 „ At 11.23 a.m. sent S.G. — “ Cann to S. W. N. One hour after we buoy your end, please take insulation and capacity of buoyed cable, and send results to Waterville,” and at 11.50 a.m. buoyed Weston end. At 11.55 a.m. ship was up to buoy on Waterville end, and at 0.20 p.m. commenced picking up to fault. At 0.45 p.m., a bad place 55 GG Electrical Report. came inboard with many broken wires. On examination found both cores parted, with conductor exposed. Cut cable forward of bad place, called Waterville on Morse and received immediate reply. Instructed Waterville to “free” both cores, and ship tested for D.R. Both cores found to be “ O.K.” Deflection nil. S.R. 10000. Testing battery = 30 volts. Length of cable picked up to fault = 0T50 n.m. Type 8567. Coiled in fore tank and labelled Piece “A.” Mechanically bad and electrically weak. Nature of Fault. Damaged portion about three feet. Sheathing holding by seven inner wires and two complete strands of outer and one single wire. The rest of the wires chafed through by rock. Core exposures . — Waterville end both cores scarfed, about J" of conductor exposed. On Weston end the scarf was about J" with similar exposure. 1.25 p.m. Ship took C.R. on Waterville end. Cores looped on shore. (V ( u C.R. of loop (corrected) = 45 091. 75° values plain core = 23-94. Lib „ =23-87. CO CO Plain core = 22*580. Rib core = 22*511. Calculated temperature by C. F. & T.’s co-efficient = 48*8° F. At 1.32 p.m., after testing spliced section in after tank 8567-1-8556 for C.R., I.C., and D.R., the tank cable and Waterville end were given out to prepare for splicing, and at 3.15 p.m. the following S.G.’s were despatched : OJ “ To Gott. Cut out fault in Weston No. 1, 22*5 from Waterville. Fault was bad, chafe close to a splice. Have removed 150 fathoms. Cable on both sides in good condition. Hope to put through by to-morrow daylight. Please instruct. Crawford, ‘Buccaneer.’ ” “ ‘ Silvergray ’ and ‘ Graysilver, London.’ “ Cut out fault off Waterville, and hope to put through to-morrow morning. All well. Crawford, * Buccaneer.’” 56 Electrical Report. 3.30 p.m. Joints between tank cable and Waterville end com- menced. 5.30 p.m. Joints between tank cable and Waterville end finished. Joints brass taped. Jointer, Molt. Received Weston’s tests on buoyed end from Waterville. Weston’s Tests on Buoyed End. Length in circuit = 328*796 n.m. (each core.) Plain core. Zinc mean of 5 minutes = 22*04 abs. ,, ,, Carbon ,, „ =26*34 „ Rib ,, Zinc ,, ,, =20*37 „ ,, „ Carbon ',, „ =22*04 „ Non-Earth. Zinc to Rib ,, „ =20*21 „ „ „ „ Plain „ =21*39 „ Capacity. Rib core = 101*78 mfds. Plain „ =102*90 ,, 7.10 p.m. (Dec. 24th.) Splice between tank cable and Waterville end completed. Splice compounded. 5 fms. = 0*005 n.m. cut off tank cable 8567 for splice. At 7.20 p.m. the following S.G. was received from Waterville : “ To Crawford, ‘ Buccanner.’ Better put in ship’s new shore end. Gott.” Commenced paying out cable towards Weston buoy, at 7.25 p.m., reaching same at 7.40 p.m. Control test applied during paying out. The following S.G.’s were now sent : 7.30 p.m. “ Crawford to Gott. Just received yours. Now coming up to Weston end, paying out Nos. 8567 and 8556. I take this is what you wish.” 8.10 p.m. “ Crawford to Wilmot. After slipping final splice will proceed to sea for night, returning to pick up buoys at daylight, and 57 gg 2 Electrical Report. if weather favourable will land, otherwise proceed to Valencia and drive over for tests. Weston end now on board. Please send to-day’s weather report.” At 8.30 p.m., Weston was called, and ship tested for D.R., the results being “ O.K.” — practically the same as on picking up the end this morning. Weston was now instructed to take C.R., the cores being looped on board. Weston’s C.R. = 8378- (loop). Ship took C.R. on Weston side. (Cores looped at Weston.) (t) Total C.R. of loop (corrected) = 8350- At 9.36 p.m. advised Weston : “ About to cut and make final splice. Call Waterville at 1 a.m. to-morrow morning. Anything further for you will advise from Waterville. Compliments of the Season. G.B.” 9.40 p.m. Closed with Weston, and gave out end for opening out for splice. At 10 p.m., the following S.G.’s were sent from ship to Water- ville : “ Crawford to Gott. 10 p.m. About to make final splice. Weather promising. Will see Mr. Wilmot to-morrow for tests and your instructious.” “ To ‘ Silvergray, London,’ and Mr. M. H. Gray, Lessness Park, Abbey Wood, Kent. Thursday, 10 p.m. About to make final splice. Will see Waterville to-morrow re tests and instructions. All well. Compliments of Season from all. Crawford, ‘ Buccaneer.’ ” At 10.15 p.m. the cable was cut in tank. Length Paid Out by C.R. and I. C. = 0 2265 n.m. Types 8567 and 8556. T • -i • , , , (Type 8567 = 0-1080 n.m. | a oock Laid m between buoys I 8556 — 0-1185 j =0-2265 n.m. Waterville was now instructed to take C.R. of cable between ship and shore, the cores being looped on board. 58 Electrical Report. co C.R. of Loop (corrected) = 51 * *07 * At 10.50 p.m. (Dec. 24th), ship having “freed” both cores on board, Waterville took D.R. tests on Plain and Rib Cores with following result : Waterville D.R. Test on Cable between Ship and Shore. n Plain Core, mean Z. and C. = 466* abs. Rib ,, ,, ,, =325* ,, T (1*7935 n.m. Cable. Length in circuit = 1 0 . 2210 „ LL 2-0145 N.B. — This result being too low, Waterville was instructed to test again, the result obtained being practically the same. Water- ville then “freed” cores, and ship took a D.R. test. With 30 volts and S.R. 10000 x power = 1, the deflection on cable was inappre- ciable. The current was kept on for six minutes and no change noticed. It was therefore decided under the circumstances to splice up. The following morning, in conversation re this subject, Mr. Wilmot informed Mr. Cann that he thought a weakness existed in the cable buried ashore. At 11.31 p.m., sent following S.G. to Waterville : “ Crawford to Wilmot. Now about to make final splice. Please advise Weston to call you at 3 a.m. We will see you to-morrow. Compliments of the Season from all.” Closed with Waterville at 11.38 p.m., and gave out both ends for splicing. co * Deducting 5-7, the C.R. of length (looped core) laid in ex after tank. This co co resistance becomes 51-07 — 5-7=45-37=C.R. of looped cores up to “Buccaneer’s” co co first splice. Ship obtained a C.R. of 45-09, a difference thus existing of 0 - 28, which, co at 25-251 — the resistance per n.m. of looped cores at 49° F. — represents a length= 0*011 N.M. — say, 11 fms. only. 59 Electrical Report. Christmas Day, Dec. 25th. 0.30 a.m. Commenced joints between Weston and Waterville ends. 2.30 a.m. Finished joints between Weston and Waterville ends. Brass taped. N.B. — Both cores of 8556 spliced on to Weston end are Plain. They had previously been marked on board Nos. 1 and 2, and when jointing cores for final splice, No. 1 was joined to Plain, and No. 2 to Bib core of Weston end. This order of joining up has always been followed on previous repairs. 4 a.m. Finished splice. Compounded over all, and at 4.17 ama. slipped same, thus completing repairs to the Commercial Cable Company’s Weston No. 1 Section, and set on to cruise until daylight. 8.30 to 8.40 a.m. Picked up balloon buoys and mark buoy. Shortly after 10 a.m. Messrs. Crawford and Cann left ship for shore for instructions, and to receive results of tests taken on Weston No. 1 Cable after repair. On arriving at the Station (Waterville) Mr. Wilmot handed to Mr. Cann the following results of tests : Weston No. 1. Plain Core >> >> • • • Bib „ Non-Earth Tests after Bepair. n ... Z = 12690- per n.m. ... C= 7720- „ ... Z = 12270- „ ... C = 7430- „ Z to P = 8660- „ C to P = 8870- „ Messrs. Crawford and Cann returned to ship at noon, and having discharged Pilot O’Neill off Horse Island, the “Buccaneer” set on for London, arriving off Gravesend at 6 a.m., Dec. 28th. In the Appendix will be found the following tables, etc. : Bevised Length and 75° F. Values of Plain and Bib Cores after Bepair. 60 Electrical Beport. Distribution of Cable in Tanks, and 75° F. Values on Leaving the Thames. Distribution of Cable in Tanks, and 75° F. Values on Return to the Thames. Expenditure Table. Diagram Sheet of Repairs, containing Tests, etc., etc. I am, dear Sir, Yours faithfully, HERBERT E. CANN. ■ Electrician. Electrical Report. Cover Sheet. WESTON No. 1 CABLE, After repairs by S.S. “ Buccaneer.” December, 1903. ELECTBICAL VALUES AT 75° E. PLAIN CORE. Sheet. Length n.m. Total C.R. Total I.C. w Mfds. A 27-360 365-896 8-444 B 67-850 915-32 20-733 C 210-364 2800-53 63-471 D 25-011 33413 7-661 Totals 330-585 4415-876 100 300 RIB CORE. Sheet. Length n.m. Total C.R. Total I.C. U) Mfds. A 27-360 367-770 8-308 B 67-850 916-76 20-518 C 210-364 2802*43 62-678 D 25-011 333-65 7-466 Totals 330-585 4420-61 98-970 02 SECTION SHEET. Plain Core. Sheet 63 C.R. IS HERE GIVEN OF THE CABLE LENGTH— NOT CORE LENGTH. SECTION SHEET. Plain Core. Sheet SECTION SHEET. Plain Core. Shi et 65 SECTION SHEET. Plain Coee. 66 SECTION SHEET. Bib Core. Sheet •siaqum^ oougaajsy; van^'eaadraax tno^og a^Bmixojddv 3 Si ^55 3 S S * g 8 CO CO 00 CO S cp 4-1 M 05 rH § US o js R (N eo •gs ea.2 wp3 g «P S ° 1 s' Tft 00 tH Plain 1-480 13-10 0-0376 0-333 “ Buccaneer,” ’ 11.12.03. 8566 1 1-654^ 22-162 13-40 0-5805 0-351 2 22-032 13-32 0-5673 0-343 Total 1-767 Main Piece 2 8512 Main Pt. 5 0150 2-553 17-02 0-0498 0-3320 f “ Buccaneer,” f 24.11.03. ) 8512 0-616 10-480 99 02045 ,, ' Main ' 1 f “ Buccaneer,” Piece 4 1 f 24.11.03. 8512 0-986 16-780 0-3273 >» 588 580 J 1 Total ,1-752 29-813 17-02 0-5816 0-3320 | Main Piece C 1 ^Factory, Dec. 03. 1 8512 Main Pt. 3 1 0-868 15-146 17-45 0-2651 0-3054 J ■> Factory, 0-422 7-364 „ 0-1289 „ j 1 | 18 & 19.11.03. | Main Piece 6 1-722 30-050 5» 0-5 9 n < | 99 99 99 1 Main Pt. B 0081 1-414 0-0247 » 1 99 99 99 Main Pt. B 0-106 1-850 »> 0-0324 M I “ 99 99 99 Total 3-199 55-824 17-45 0-9770 0-3054 As spliced together. 3-199 55-824 0-9770 1-752 29-813 0-5816 H.I. Total 4-951 85-637 17-30 1-5586 08150 8514 H.I. 8514 0-5511 9-385 1703 0T962 0*356 693 382 “ Buccaneer,” 0-3724 6-342 99 01325 jj 1026 99 j V h 25.11.03. L.I. ' I r >» » »> 8513 H.I. 8514 0-2200 3-747 99 0-0783 99 1736 99 { Tapering Splice 0-5000 8-515 99 0-1780 99 ( 764 99 ) Siemens. Total 1-6435 27-989 1703 0-5850 0-356 232-4 382 73 COMMERCIAL CABLE COMPANY’S REPAIRS. S.S. “BUCCANEER,” DECEMBER, 1903. GQ m a < w EH P H Eh O Eh P P5 P Eh P « O P p < Eh P P P < O K Eh 00 cq P P PP P o P A P O O HH EH P S s Eh GQ g* _1 o O CO -+< LO 10 n ic cc k ,-H o o «p cq © O © » 0-0247 55 _ — i \ ■ Pc. “ B ” 8512 0-106 1-850 - 0-0324 - - 1 i- - ■ Total 3-199 66-824 17-45 0-9770 0-3054 - - X As spliced together 3-199 55-824 0-9770 - - 1-752 29-813 0-5816 - - otal 4-951 85-637 17-30 1-5586 •3150 - - H.I. 8514 0-5511 9-385 17-03 0-1962 •356 693 382 \ “ Buccaneer,” H.I. 8514 0-3724 6-342 >9 01325 „ 1026 - J 1 f 25.11.03. 1 L.I. 8513 0-2200 3-747 0-0783 )) 1736 __ r » H.I. 1 i Tapering splice, 1 (Siemens’) 8514 0-5000 8-515 0-1780 99 764 — J Total 1-6435 27-979 17-03 0-5850 •356 232-4 382 76 Electrical Report. Weston— Waterville No. 1 Repairs. S.S. “Buccaneer,” December 20th and 25th, 1903. EXPENDITURE TABLE. TYPE 8567. N.M. Received from Siemens’ Bros, ex-barge “Wilts,” December 9th, 1903 = 0*1150 Cut off December 11th, when splicing =0*0020 Laid in Weston — Waterville, No. 1 = 0*1080 Cut off for splice with Weston — Waterville end, Dec. 24th = 0*0050 Total = 0*1150 TYPE 8556. N.M. Received from Siemens’ Bros, ex-barge “Wilts,” December 9th, 1903 = 1*6600 Cut off for splice to 8567, December 11th, 1903 = 0*0060 Laid in Weston — Waterville, No. 1 =0*1185 Remaining in After Tank, “ Buccaneer ” ... = 1*5355 Total = 1*6600 Total expended Type 8567 = 0*1150 „ „ „ 8556 = 0*1245 Total = 0*2395 77 g w O o 55 jo o P S a M £ o Ph « p H W £ § 55 O H 02 H O Lr £ a h « H P 55 ft 3 OQ g 55 P o PQ <1 P? P gq Ph O {H ffl « HH <1 pH P GQ O 55 HH £ o w 3 GQ a P? O <1 52 - S ' t- >A N N 2 £tf aSS «5 CO T* © .§•1 W 00* 1 1 g-rt g* a s 3 a a & 5 3; "3 3*s 1 ? 2 « o S © o So 5 3] 2 h S66 II II II II £ l u S fe a « « d d a "3 JQ Stf ICO 1C 'll* -d* II II V Q. fci .& o ••Q J3 PSCQM II II I* * •§i ogi H * g » £ 8 .& •r- 5 o 00 65 H $ I II n QQ Cl 00 I.. CD -d* -d* 225S 2 ^"*322 Gn ® " II II II 2? <» $>* a II § « '3 a i-t Q CLtf P-. P3 o o o o> »■« !§a *a ~ 5« 3 s^| « s' CO -S? c fO Jo ■ 8 i *3* sg; «, » »• ll ll n 1i I § H O Ktf dd s . a b* 50 9? o o II II a j2-° ££ a . J3 - O © o © © 2 Is o a o « ° Eh so d -5 £ * £ £ 3^-2 ■g 2 | p o ^ .o pjNNO & o d 2 2 pj . 5 0ifli0 -« tH go 3 3 p • Qj «0 »« O ^ -*f r ^ 50 NMiO HN00 gHNO o ift qooo o’ 6 M co co co eo ill |.a | -s |w | O^p PPPm OP o ^ PRINTED BY DALZIEL AND Cg^ LTD., CAMDEN PRESS, LONDON, N.W. H P « <3 o o oo g M »— i !> K EH O Ph cq H 1 EH W <1 £ I s cq £ P 5 H O EH GO S w o H H P grf W H « H P 53 CQ g 53 £ O ffl W - EH gj 02 S « P 4 O >H ffl P§ <1 S N ?? o o II II s ’ 3 £ Stf 1 . o §§ CO CO II II is l 1 ’3 £ Stf Tjt o _ CO 00 3 -H P.H E« S? o o II II a "cS X ! S 3 II II a '3 .a Eg dd ■Sg » be || II g£ • 64 JesS ig 50 SSggSiS I «1 lie i5g a lU gii-d |ggs2&§ 2 g 8 15 JS I J o H “ d -g E « « £ S ^ a j o £ .CD WO D> HDO Q T* - ^oo o o o o * !>• O *0 |» ^4 ^ ® o p o> p p p a* o* b b b b H *-h ©* o 2 ^ JhOiAO ■ft' CD C* CONifl gSSJo SoS •S 6 ®® &’ g CO CO II II II 1 II II f .5 | | ■jaStH |*fcj P ojfi PmQPj . © CD O < '©oo § ' © *999 p p pjwrtO ^ b g*o 3 3 ►q • Qj*0 W iO CD^ fONiO 5 ®i^ NN Hl^OO g rH