trigram

This is a table of type trigram and their frequencies. Use it to search & browse the list to learn more about your study carrel.

trigram frequency
of the tunnel239
of the work154
troy and greenfield133
the troy and131
and greenfield railroad120
part of the103
the new york102
of the shield97
the construction of82
the pennsylvania railroad75
of the tunnels74
end of the70
in order to69
the long island68
side of the66
greenfield railroad company66
the amount of65
the hoosac tunnel64
top of the63
the east river60
of the state60
of the pennsylvania60
the cost of58
the top of57
construction of the57
on account of56
governor and council55
of the troy55
the governor and55
new york city55
the shield was53
of the road53
the treasurer of53
of the commonwealth52
the iron lining51
the north river51
as soon as49
the completion of49
account of the48
long island railroad48
of the river48
had to be47
shown in fig46
the work was45
portion of the45
the use of45
east of the44
was to be44
in the tunnel44
of said scrip43
completion of the43
line of the42
hundred thousand dollars41
a distance of40
in addition to39
of the hoosac39
of new york39
of the concrete38
the same time38
shall be delivered38
long island city38
in one or38
the bottom of37
on the new37
of the iron37
bottom of the37
of the same37
to the treasurer36
of the shaft36
the end of36
the cutting edge36
face of the35
at the same35
cost of the35
of the railroad35
one of the35
shown on plate34
the concrete lining34
of the company34
of the arch33
the provisions of33
of the line33
portion of said33
the time of33
the line of33
treasurer of the33
and in the33
the western road32
the rate of32
the face of32
board of trustees32
were to be32
at the time32
section of the32
the concrete was31
pennsylvania railroad company31
the west end31
of the western31
of the corporation30
one or more30
attached to the30
level of the30
of this act29
for the purpose29
the east end29
control of the29
so that the29
progress of the29
of the long29
the board of29
the weehawken shaft28
the rock was28
hundred and fifty28
by the state28
the air pressure28
the rock surface28
as shown in28
the boston and28
addition to the28
the metal lining27
the terminal station27
at the west27
to the west27
at the top26
in the tunnels26
it was necessary26
surface of the26
it will be26
the remainder of26
as may be26
the sum of26
the fitchburg railroad26
would have been25
of their said25
said company shall25
to the state25
per linear foot25
the progress of25
another portion of25
said board of25
the east side25
east river tunnels25
as well as25
the work of25
the weight of25
connection with the25
the excavation was25
to the tunnel25
was necessary to25
and it was24
new york side24
earth and rock24
to the amount24
the river tunnels24
the center line24
shall have been24
west of the24
the tunnel was24
on each side24
use of the24
the tunnel line24
weight of the24
vermont and massachusetts24
the level of24
of all the24
in d street24
railroad company shall24
of the governor23
from time to23
the acts of23
of the new23
of about ft23
of the commissioners23
delivered to the23
the soft ground23
the surface of23
the hoosac mountain23
remainder of the23
the tunnel and23
the purpose of23
from the west23
used in the23
of said company23
of the north23
length of the23
in the bottom23
to be made23
road and tunnel22
there was a22
of the acts22
the west side22
time to time22
at the east22
the railroad company22
of the whole22
could not be22
president of the22
found to be22
location of the22
east side of22
soon as the22
rock bottom heading22
first day of22
the western railroad22
thousand lineal feet22
the tunnels were21
of the rock21
shown by fig21
provisions of this21
in front of21
or more sections21
treasurer of said21
the quantity of21
lineal feet of21
front of the21
on the th21
of the committee20
as to the20
the number of20
the state of20
york tunnel extension20
by means of20
the capital stock20
extension of the20
into the tunnel20
new york tunnel20
of free air20
north river tunnels20
at the rate20
parts of the20
the manhattan shaft20
the hudson river20
the shields were20
one or two20
was found to20
out of the20
was put in20
the first day20
for a distance20
in the same20
owing to the20
stock of the20
at the bottom20
on the manhattan19
property of the19
it may be19
a number of19
as far as19
the length of19
the manhattan side19
and the other19
the middle of19
of the city19
troy and boston19
the work done19
eighteen hundred and18
company shall have18
made to the18
the act of18
and of the18
five per cent18
a and b18
the road and18
the new jersey18
to the commonwealth18
capital stock of18
and for the18
the excavation of18
delivered as aforesaid18
the city of18
to the shaft18
and on the18
of the excavation18
scrip shall be18
in the construction18
that of the18
on the work18
be delivered as18
up to the18
one hundred and18
it was found17
portions of the17
the tunnel to17
quantity of water17
is hereby authorized17
the same as17
in each tunnel17
be delivered to17
engineer of the17
some of the17
so as to17
connected with the17
of the shields17
in the middle17
boston and maine17
it was not17
for the construction17
sand and gravel17
and at the17
from to ft17
to the governor17
will be described16
as it was16
by the railroad16
member of the16
west side of16
to the east16
under the river16
per cubic yard16
of the cutting16
will be seen16
in feet material16
outside of the16
sides of the16
of the lining16
in advance of16
the central shaft16
on the first16
eastward from the16
free air per16
rock surface was16
feet of their16
and the work16
the th of16
fitchburg railroad company16
the whole of16
feet per month16
the vermont and16
the space between16
upon the road16
work in the16
tunnels under the16
access to the16
and to the16
of the face16
southern vermont railroad16
excavation of the16
in new york16
the payment of16
in the rock16
is shown on16
at this point16
not less than16
space between the15
at the end15
road east of15
of the ground15
the face was15
tail of the15
position of the15
in the concrete15
of the contractors15
capacity of the15
each of the15
in connection with15
greenfield railroad and15
of the caisson15
two hundred and15
to be done15
the southern vermont15
in the top15
and it is15
a part of15
ends of the15
which it was15
center line of15
of the top15
advance of the15
new jersey side15
in such manner15
of the two15
the heading was15
are to be15
which had been15
on the east15
description of the15
of the engineer15
by the governor15
of the west15
or two sections15
the removal of15
features of the15
it was decided15
an average of15
of the bench15
in the river15
the tail of15
the control of15
miles of their15
in soft ground15
edge of the14
air pressure was14
of the act14
of the enterprise14
most of the14
feet above the14
early part of14
center of the14
of the working14
on the line14
feet of tunnel14
to be paid14
ahead of the14
the road east14
this was done14
their said tunnel14
of the construction14
where it was14
the loss of14
of the board14
that it was14
sand and stone14
the eastern railroad14
where there was14
the center of14
work on the14
mixed rock cut14
grade of the14
the operation of14
bergen hill tunnels14
the early part14
is to be14
in the early14
of the track14
distance of ft14
rest of the14
of the great14
on which the14
to the level14
on the west14
it was then14
on the surface14
is shown by14
the foot of14
lining of the14
the north and14
the caisson was14
the direction of14
the rest of14
the roof of14
that the work14
that the state14
hundred and twenty14
of the terminal14
one hundred thousand14
of the directors14
the shield chambers14
made in the14
are shown in14
and maine railroad14
to new york14
was filled with14
in tunnel a14
middle of the13
in case of13
the passage of13
eastern railroad company13
of the fitchburg13
the sand and13
of one of13
approval of the13
prior to the13
as shown by13
the people of13
in favor of13
american society of13
chapter of the13
under the north13
new york central13
the company to13
roof of the13
new york and13
nature of the13
crown of the13
and boston railroad13
on top of13
the location of13
and that the13
from the east13
east and west13
society of civil13
the water was13
in this way13
interest of the13
the interest of13
size of the13
of civil engineers13
concrete lining was13
hundred and sixty13
the crown of13
tunnel extension of13
was decided to13
the tunnel lining13
in diameter and13
was done by13
r r r13
the west shaft13
ten per cent13
the shield and13
of the water13
of the east13
is shown in13
to the river13
to the new13
to be taken13
by the contractors13
charge of the13
whole of the13
diameter of the13
according to the13
value of the13
lines of the13
was found that13
of d street12
and shall have12
subject to the12
it has been12
and hoosac tunnel12
the greater part12
the size of12
there was no12
in the latter12
cost of labor12
were put in12
regard to the12
placed in the12
muck loaded by12
in accordance with12
in which the12
was carried on12
each side of12
of which was12
together with the12
millions of dollars12
lines and grades12
of ninth avenue12
r r a12
a pressure of12
fifty thousand dollars12
in the north12
of said road12
at intervals of12
to the top12
the placing of12
the aid of12
under the provisions12
between greenfield and12
east end of12
o o t12
of the street12
the deerfield river12
e p e12
a member of12
railroad and tunnel12
in the following12
feet wide and12
as the shield12
h h h12
to be used12
organization of the12
the building of12
that may be12
shall be made12
the result of12
loss of air12
the benefit of12
g g g12
chief engineer of12
twenty thousand dollars12
by the contractor12
of the heading12
directors of the12
at one time12
boston railroad company12
the grade of12
to a point12
table part w12
r a m12
operation of the12
to support the12
in the first12
it is not12
to the rock12
of the hudson12
was made to12
in regard to12
in long island12
e e p12
the average progress12
was placed in12
as shown on12
a top heading12
thousand feet of12
removal of the11
the approval of11
the work is11
each pair of11
to make the11
be made to11
details of the11
the said company11
made by the11
under the act11
the necessity of11
from greenfield to11
greenfield to the11
by the commonwealth11
the capacity of11
half of the11
the latter part11
the course of11
drilling and blasting11
railroad company to11
of this commonwealth11
point on the11
to the work11
in the state11
the state in11
of the legislature11
the fact that11
through the tunnel11
in the case11
of the first11
rate of progress11
to prevent the11
c and d11
where the rock11
the case of11
miles of the11
of the country11
amount of the11
shall have excavated11
out of rock11
of the metal11
of the mountain11
of compressed air11
which has been11
by the commissioners11
a depth of11
railroad and hoosac11
the execution of11
in relation to11
their said railroad11
in the roof11
report of the11
the opening of11
view of the11
the most important11
the soft material11
shown in table11
boston and lowell11
at the present11
in the center11
for this purpose11
base of the11
down to the11
heading and bench11
of the people11
time per ring11
and a half11
placing of the11
the northern line11
the base of11
and superstructure of11
the street surface11
and through the11
of the eastern11
and all the10
into new york10
between the tunnels10
the intercepting arch10
feet of heading10
were taken out10
approved by the10
which will be10
city of new10
the right to10
in the east10
heading was driven10
the part of10
had been made10
the working chamber10
so far as10
the tunnel in10
and the whole10
a short distance10
commissioners of the10
at the face10
vermont railroad company10
the method of10
the sinking fund10
to said company10
north and south10
to the contractor10
equal to the10
the work at10
the upper part10
settlement of the10
used on the10
on may th10
of the contract10
the land tunnels10
greater part of10
interests of the10
the rock and10
of the present10
of seventh avenue10
the details of10
the work to10
latter part of10
and ninth avenues10
the tunnels under10
the bench was10
with the west10
of the year10
shall have completed10
it could be10
of the cost10
to and from10
company and the10
direction of the10
when it was10
be seen that10
the exception of10
in charge of10
height of the10
pressure of lb10
the d street10
the escape of10
and massachusetts railroad10
of which the10
at right angles10
b and d10
pressure in the10
the purposes of10
the ends of10
of the most10
of the ring10
amounting to one10
north river division10
the railroad and10
to the contractors10
at that time10
d street and10
the time the10
whenever said company10
to be removed10
from to lb10
iron lining of10
at any time10
upon the tunnel10
hereby authorized to10
to complete the10
under d street10
to the whole10
of the shafts10
the first avenue10
escape of air10
through which the10
from the state10
state of new10
in the manner10
members of the10
on the north10
and fifty thousand10
such manner as10
at this time10
the value of10
in open cut10
to one hundred10
to be the10
the same shall10
to the legislature10
have been made10
a portion of10
the depth of10
at that point10
it would have10
work of the10
with the exception10
to keep the10
the atlantic avenue10
of the council10
shield was shoved10
for the use10
in the shield10
tunnel under the10
when the shield10
in the crown9
there were two9
to have been9
and from the9
first and thirty9
of trustees is9
new york connecting9
under the direction9
the river shafts9
paid by the9
the north side9
the lower part9
of fifth avenue9
to be a9
h l u9
lower part of9
average rate of9
to which the9
felt and pitch9
braced from the9
tunnel and terminal9
for the whole9
i l t9
of state scrip9
was of the9
t r o9
the outside of9
was attached to9
will be found9
the work in9
board of engineers9
it was thought9
full face of9
could be made9
scrip to the9
g g s9
the cutting edges9
it would be9
provisions of the9
to determine the9
the state treasurer9
t i s9
to the face9
tracks of the9
and shelburne falls9
to permit the9
trustees of the9
at or near9
avenue to the9
time taken to9
the tunnel at9
the roof was9
the point where9
execution of the9
the thickness of9
distance of about9
d g g9
one thousand lineal9
l u t9
east river division9
to provide for9
the same manner9
eight hundred and9
to the provisions9
rock center heading9
the effect of9
amount of scrip9
the position of9
n n n9
at the beginning9
the terms of9
to the people9
water from the9
tunnels b and9
flanges of the9
and lowell railroad9
and the iron9
by the city9
the bergen hill9
the present time9
the nature of9
in cubic yards9
s i o9
of the bottom9
and whenever said9
the tunnel is9
mixed bottom heading9
i r r9
provide for the9
for the completion9
greenfield and shelburne9
far as possible9
between seventh and9
atlantic avenue improvement9
bonds of the9
in in in9
at about the9
the average time9
the state to9
to the line9
table showing the9
of which were9
the erection of9
the expense of9
of the said9
under the east9
two millions of9
from long island9
the work under9
the majority bill9
of the entire9
of boston and9
caused by the9
by steam shovel9
of new jersey9
work at the9
the arch was9
right of way9
the shield method9
from the top9
i a t9
york connecting railroad9
l t r9
l n n9
the work on9
to the troy9
and the rock9
which was the9
the tunnels and9
be it enacted9
to avoid the9
at the manhattan9
this act shall9
have been described9
u t t9
be used in9
average time taken9
the limits of9
of first avenue9
may be required9
were used for9
credit of the9
are shown on9
lumber in feet9
a capacity of9
the two tunnels9
for the sum9
and d streets9
the bore segments9
to be built9
was made with9
to the shield9
the sunnyside yard9
d g i9
as in the9
and by the9
bottom heading oct9
the shaft was9
it can be9
i i a9
the town of9
the organization of9
board of directors9
west end of9
on either side9
of the piston9
placed on the9
e i i9
in the invert9
when said company9
there can be9
the duct bench9
of this section9
soft ground was9
the property of9
a loan of9
thousand dollars for8
or for the8
done by the8
shown on fig8
brown on pennsylvania8
either side of8
the directors voted8
the portion of8
by far the8
at each plant8
case of the8
to meet the8
miles of road8
has been made8
opening of the8
at a time8
l table part8
right angles to8
to the boston8
by the stockholders8
the credit of8
it shall be8
by which the8
and when said8
in tunnel b8
the establishment of8
the concrete and8
as much as8
in the south8
on the center8
were built in8
due to the8
average cost per8
was less than8
in tunnel d8
to from to8
passenger and freight8
of the hood8
this part of8
the ducts were8
which may be8
in the face8
of the plant8
line to the8
tunnels from the8
railroad company for8
was used for8
through the soft8
the contractor for8
and d street8
by the pennsylvania8
and the amount8
and with the8
compliance with the8
foot of the8
of the gross8
on pennsylvania r8
thickness of the8
the weehawken side8
the ground was8
tunnel to the8
feet material e8
and terminal railroad8
of number progress8
company for the8
the hands of8
to reduce the8
of the project8
and brown on8
of said tunnel8
length r method8
that the tunnel8
up to a8
the point of8
of this great8
with all the8
iron tunnel lining8
shall not be8
of the proposed8
from the tunnel8
between length r8
company to construct8
rock on the8
hewett and brown8
pair of tunnels8
upper part of8
applied to the8
junction of the8
tunnel of the8
railroad company and8
and long island8
five thousand dollars8
on the weehawken8
was divided into8
for the first8
n n a8
in the heading8
should be completed8
accordance with the8
hoosac tunnel railroad8
between boston and8
description in gang8
of pounds of8
to construct the8
lock bulkhead wall8
by compressed air8
the twin tunnel8
to the tunnels8
when the shields8
for more than8
r method of8
in compliance with8
work was carried8
which have been8
a n rings8
the prosperity of8
the tracks of8
the intermediate shafts8
into the shield8
pennsylvania tunnel and8
of scrip shall8
hoosac tunnel and8
of the latter8
the transportation of8
linear in feet8
the same year8
to full size8
a system of8
in spite of8
width of the8
hundred and seventy8
the shield had8
the interests of8
of the boston8
of the south8
the contract was8
of such a8
in normal air8
quantity of muck8
for the same8
from the shaft8
of the lower8
division of the8
was taken out8
of the amount8
the whole length8
the latter was8
the portions of8
the concrete arch8
tunnel and railroad8
on the other8
with the troy8
concrete was placed8
progress of linear8
of the southern8
that it would8
for the purposes8
the hudson and8
on the south8
the great west8
at the foot8
of the loan8
be considered as8
and the east8
of the sand8
the pressure was8
a view of8
in the interest8
n rings in8
o between length8
one of them8
in queens borough8
the installation of8
i o o8
large quantity of8
by the shield8
the question of8
the right of8
in tunnel c8
which shall be8
seventh avenue and8
exclusive of the8
acts of the8
well as the8
that in the8
tunnel and the8
duct bench concrete8
on the side8
to the public8
below the surface8
and the shield8
floor of the8
tunnel at the8
to the weehawken8
that it is8
number progress of8
of the sump8
material e excavation8
and the tunnel8
made with the8
rings in feet8
for top charges8
possession of the8
as resident engineer8
g s l8
of the ducts8
in the street8
for use in8
opinion of the8
dollars for each8
had been driven8
the commonwealth shall8
the importance of8
of the other8
of linear in8
same manner as8
in the contract8
first avenue shafts8
amount of excavation8
line between the8
done in the8
from the tunnels8
far as the8
the pump chamber8
air per minute8
said troy and8
rate of number8
table summary part8
r section u8
the rapid transit8
was started on8
top and bottom8
the holes were8
the history of8
worked by a8
were set up8
at each end7
all rock bottom7
were replaced by7
consisted of a7
holes were drilled7
the erie railroad7
use in the7
history of the7
the same to7
in the original7
to form a7
state board of7
tunnels and the7
to have the7
of the former7
the beginning of7
to the other7
the tunnel itself7
occupied by the7
easterly line of7
two hundred thousand7
the top and7
of tenth avenue7
would not be7
the subject of7
aid of the7
of the various7
after the completion7
the bolt holes7
the average rate7
excavation was completed7
for the tunnels7
the way of7
in compressed air7
lining of shield7
there is a7
by the writer7
favor of the7
the chief engineer7
all the work7
the river was7
the progress made7
the side of7
from the face7
the lines of7
on d street7
of the machine7
time of the7
in a manner7
much of the7
of the old7
rock cover was7
to be issued7
upon the work7
the west line7
of these tunnels7
be the most7
condition of the7
of the business7
the masonry lining7
was made by7
with the new7
have been completed7
to the time7
railroad and the7
from the station7
described under the7
superstructure of the7
air pressure in7
from the first7
not more than7
the hydrostatic head7
in this work7
on flat cars7
railroad and property7
b c d7
a bottom heading7
y r n7
change in the7
to allow the7
the river tunnel7
directly from the7
the concrete in7
that portion of7
found that the7
soft ground in7
a b c7
extending from the7
the south tunnel7
the east heading7
provided for the7
depth of ft7
building of the7
that the commissioners7
work in tunnel7
at the north7
the report of7
a r section7
resting on the7
two or three7
the specifications required7
of one hundred7
chairman of the7
placing the concrete7
of said corporation7
estimate of the7
of the pile7
the surface and7
from the river7
to the capital7
plan and profile7
be described in7
in driving the7
in the open7
loaded by steam7
shall be in7
a e e7
until after the7
the iron and7
shoving the shield7
of the american7
of the railroads7
had been built7
a length of7
known as the7
that the whole7
tunnel through the7
the new england7
be required to7
should have been7
on the shield7
for the long7
lining was placed7
r e a7
of the last7
line on the7
that the concrete7
contractor for the7
below mean high7
be found in7
for a short7
the contract for7
the american society7
of the three7
the name of7
whole length of7
the shields in7
of the time7
proved to be7
but it is7
the presence of7
burleigh and gates7
the adoption of7
the various operations7
have been a7
twenty per cent7
which could be7
from the weehawken7
to stop the7
portions of thirty7
years from the7
by the board7
in the form7
covered by a7
tunnels of the7
by the tunnel7
the time taken7
for that purpose7
and the long7
similar to the7
island railroad company7
loaded by hand7
during the period7
the junction of7
the directors of7
by reason of7
furnished to the7
the south shaft7
been actually paid7
erection of the7
in the summer7
similar to that7
to carry on7
from the heading7
were used in7
at fifth avenue7
the springing line7
of two hundred7
d b b7
the axis of7
between the two7
n r r7
axis of the7
and the treasurer7
the tunnels are7
conditions of the7
was at first7
in order that7
brought up to7
the committee are7
the sinking of7
mean high water7
the performance of7
rock at the7
seen that the7
given in table7
and stone were7
that they would7
kinds of ground7
three or four7
air cylinders were7
the joints were7
on the road7
carrying out the7
under the hudson7
there were three7
the resident engineers7
in the year7
the water from7
of the cross7
floors of the7
west line of7
at long island7
of tunnel was7
of the streets7
railroad company was7
from the foregoing7
for labor and7
in a few7
by the use7
seven miles of7
that they were7
the opinion of7
work to be7
of the flanges7
above the tunnel7
any of the7
said commissioners shall7
that at the7
large part of7
to be placed7
was authorized to7
to be delivered7
made up of7
with the advice7
support of the7
the rear end7
the commencement of7
as the same7
the tunnels to7
to the board7
of its cost7
provided in the7
hereby authorized and7
and troy and7
fourteen feet wide7
from to from7
six hundred thousand7
the same in7
in view of7
pressure on the7
will be given7
of this work7
the state board7
and new york7
the diameter of7
of trustees of7
from the shield7
the advice of7
was as follows7
same to the7
the construction and7
of the total7
the tunnels in7
of sand and7
to the surface6
the sliding platform6
six per cent6
and the railroad6
to the mountain6
along the tunnel6
had not been6
east river and6
intervals of about6
the consideration of6
air per min6
was supported by6
tunnels c and6
lineal foot of6
from to in6
at manhattan was6
back of the6
about of the6
of the manhattan6
for the state6
and the west6
it to the6
was a small6
flatbush avenue terminal6
the north tunnel6
the commissioners of6
water in the6
six of the6
and prior to6
the great northern6
and the time6
bridge over the6
the distance piece6
river to the6
can be done6
were of the6
time of its6
delivery of scrip6
to the delivery6
three hundred and6
the location and6
the flanges of6
more than a6
rods in the6
for the new6
and manhattan railroad6
lining and the6
on the part6
of the unfinished6
and th street6
at the other6
the shield advanced6
on december th6
the receipt of6
the shutters were6
in the upper6
the work could6
be described later6
directly to the6
the excavation for6
streets and avenues6
was desired to6
filled with concrete6
bench concrete was6
a few feet6
not be used6
chapter two hundred6
in aid of6
a typical cross6
the charge of6
to a depth6
the driving of6
east new york6
the legislation of6
total average cost6
the state has6
to the track6
the estimated cost6
little more than6
reference to the6
the leading end6
more than two6
of the minority6
the whole line6
the bottom heading6
of the rail6
of the caissons6
management of the6
on the completion6
was completed in6
the road between6
of the center6
communication with the6
thousand eight hundred6
the other hand6
of the opening6
the rock at6
at all times6
work will be6
this method was6
deliveries of scrip6
the possibility of6
feet high in6
the interest on6
engineers instituted transactions6
those of the6
the width of6
paid upon the6
the bonds of6
street to the6
cost per cubic6
excavation for the6
it is a6
driven tunnel work6
transactions paper no6
feet per mile6
thousand dollars to6
the tunnel on6
of ground encountered6
new york station6
action of the6
to some extent6
at north adams6
and also the6
people of the6
those on the6
the lowell railroad6
of the sinking6
resulted in a6
or any part6
instituted transactions paper6
the whole work6
cement and sand6
for the various6
greater than the6
between it and6
all parts of6
of eighteen hundred6
the change in6
sized twin tunnel6
total field charges6
given by the6
pearson and son6
the commonwealth for6
method of construction6
eastern end of6
the front of6
across the river6
had been removed6
edges of the6
the sump segment6
authorized and directed6
had been excavated6
caulking and grummeting6
elevation of the6
sections of the6
more than ft6
of the engineering6
up on the6
tunnel to be6
hudson and manhattan6
of bore segments6
filled with grout6
mortgage bonds of6
angles to the6
near the east6
dollars for the6
was in progress6
to enable the6
of the station6
of a large6
for the work6
was made in6
the form of6
first section of6
there are two6
before the committee6
contract for the6
jersey city station6
and new jersey6
tops of the6
the disposal of6
as the work6
and the same6
on the same6
the export trade6
by james h6
viaducts or bridges6
the state credit6
the attention of6
was done with6
adjacent to the6
it was possible6
five miles of6
d and d6
of the structure6
york central railroad6
the corporation was6
terminal railroad company6
was carried out6
of the main6
ducts were laid6
the pennsylvania tunnel6
acts of eighteen6
and directed to6
for each lineal6
of said railroad6
to the construction6
was taken up6
the companies are6
providing for the6
from station to6
the unavoidable delays6
western railroad corporation6
map and profile6
the shields had6
act of april6
the surrender of6
large number of6
shape of the6
eighty thousand dollars6
the commonwealth in6
taken from the6
lease of the6
left in the6
be paid by6
and eighth avenues6
the lining was6
power of the6
each end of6
required for the6
of completing the6
interest on the6
in pursuance of6
in the air6
avenue and d6
cutting edge of6
driven from the6
of the pump6
seventh and eighth6
previous to the6
heading of the6
at the rear6
six hundred and6
each lineal foot6
the friends of6
delivered on the6
of the upper6
it is the6
consolidation of the6
ground in the6
engineering construction company6
where they were6
at one end6
may be said6
from the date6
at d street6
in the line6
and about ft6
it secures to6
boston and albany6
long island shafts6
the compressed air6
of the several6
full page image6
used for the6
of from to6
the tops of6
fact that the6
day of january6
rock in the6
and council shall6
friends of the6
which they were6
by virtue of6
on plate xiii6
but it was6
meeting of the6
the extent of6
gross earnings of6
table shows the6
the sale of6
the working face6
erection of shield6
construction of this6
at west end6
surrender of the6
carried on by6
of tunnel as6
greenfield railroad corporation6
the rear of6
was built in6
westward from the6
rock middle heading6
that there was6
to construct a6
records of the6
the rock cover6
any portion of6
the gross earnings6
streets or avenues6
at the point6
of this tunnel6
before the concrete6
shafts were sunk6
a large quantity6
lines a and6
to be very6
e a n6
civil engineers instituted6
a and c6
with a view6
work under the6
the eastern terminus6
a very large6
a little more6
name of the6
to which it6
the summer of6
as long as6
be added to6
point where the6
to place the6
could have been6
the meeting of6
in any way6
thousand dollars in6
with the pennsylvania6
lowell railroad company6
which is the6
way of the6
in the course6
high in the6
through the hoosac6
under the contract6
estimated cost of6
tunnels a and6
of cement and6
the unfinished portion6
north river bridge6
cut in the6
the tunnel of6
of the intercepting6
from the manhattan6
of the wall6
from the bottom6
the first section6
to examine the6
it appears that6
in contact with6
when the work6
in tunnels b6
foot of tunnel6
of the material6
of the way6
manner as the6
for a time6
to maintain the6
tunnels at the6
work was finished6
the extent and6
railroad company is6
the floors of6
the conditions of6
of which are6
after the concrete6
the period of6
to be sold6
thirty per cent6
was done in6
than the standard6
and will be6
all of the6
company shall be6
the north shaft6
railroad company in6
the tunnel extension6
western railroad company6
was fitted with6
loan of the6
by the construction6
was about ft6
the land tunnel6
the rock in6
it and the6
not included in6
done at the6
to carry the6
shall take effect6
by the company6
similar to those6
plan of the6
without caulking pockets6
just before the6
made for the6
total cost of6
of the reef6
to be constructed6
or near the6
telephone and telegraph6
to secure the6
to pay the6
the duties of6
long island shaft6
where the tunnels6
any part thereof6
the shield could5
construction of a5
act in addition5
carry on the5
with the work5
concrete lining of5
the cable conduits5
the material was5
to the crown5
was impossible to5
east of first5
of the section5
i s l5
necessary for the5
spent by the5
to whom the5
resident engineer of5
to the one5
advice of the5
shall have the5
lining had been5
a half feet5
the year eighteen5
to show the5
h e a5
tunnel extension project5
the records of5
as a result5
town of florida5
the joints between5
parallel to the5
have been paid5
the close of5
river tunnels was5
were located in5
manhattan railroad company5
the feasibility of5
commonwealth of massachusetts5
same shall be5
erecting the iron5
rock and the5
of the companies5
the basis of5
installation of the5
of said railroads5
a diameter of5
a state engineer5
the air was5
the last ring5
and profile of5
to more than5
of labor in5
the excavation had5
the state for5
year one thousand5
the top was5
part rock and5
the horizontal diameter5
shield was about5
to operate the5
purposes of the5
had been used5
side of tenth5
in conjunction with5
in their judgment5
in the proportion5
amount of state5
for the last5
included in this5
by the resident5
a large amount5
shall be furnished5
treasury of the5
time for jacks5
and as the5
was reduced to5
distance from the5
boston and troy5
were as follows5
the sand was5
soon as possible5
and when the5
new england states5
field engineering staff5
in the sand5
the solid rock5
of the d5
methods of excavation5
not inconsistent with5
in such a5
and if the5
increased cost of5
the concrete for5
they were used5
in segment no5
sinking of the5
of the form5
work is shown5
shall be paid5
work has been5
the actual cost5
of their own5
several kinds of5
considerable portion of5
of the full5
lined with concrete5
but in the5
by a single5
as the concrete5
of men e5
as they were5
the stone was5
it was impossible5
the whole amount5
iron lining was5
the tunnel company5
which it is5
the support of5
the broken plates5
from the eastern5
underground portions of5
nearly all the5
shown in the5
the concrete had5
this great enterprise5
the tunnels as5
to issue scrip5
brought into the5
the shield chamber5
on october th5
opposition to the5
with power to5
are hereby authorized5
muck from the5
of the skin5
of clay was5
of the above5
bears to the5
a few years5
site of the5
the heading of5
because of the5
to change the5
station to the5
in gang i5
of the shove5
an account of5
were placed in5
to remove the5
total length of5
order to avoid5
the working force5
east of shaft5
added to said5
of the duct5
the plans for5
one of these5
dumped into the5
to be at5
and allowed the5
including time for5
in proportion to5
were made of5
lagging was placed5
the open cut5
to the engineer5
it is impossible5
as it is5
the county of5
involved in building5
to twenty thousand5
that the rock5
has already been5
shown by the5
it was desired5
of the twin5
point of the5
the streets and5
excavated to full5
for the benefit5
were also used5
of the pipes5
tons of freight5
contact with the5
was engaged in5
and the air5
the same general5
the members of5
the tunnel lines5
the state and5
the character of5
the delivery of5
may be necessary5
to make such5
of this amount5
as chief engineer5
the satisfaction of5
and twenty feet5
this work was5
e i l5
committee of the5
might have been5
made it possible5
of the electric5
to increase the5
bond and mortgage5
shield could be5
extent and nature5
unfinished portion of5
time of his5
at first avenue5
five hundred and5
the river lines5
in the two5
many of the5
so that it5
the tunnels at5
the tunnels was5
also the extent5
tunnel a and5
the several kinds5
of a great5
removed and the5
satisfactory to the5
center line between5
those in the5
tunnels could be5
on the tunnel5
the eastern end5
the village of5
made from the5
york shield chambers5
typical working force5
labor and material5
the whole gang5
is given in5
of the traffic5
r h l5
done upon the5
the south side5
order to prevent5
the state should5
paid to the5
that he did5
the office of5
thousand dollars of5
and nature of5
design of the5
should not be5
authorizing a loan5
eastern terminus of5
was thought that5
the tunnel invert5
during the construction5
construct a tunnel5
has not been5
order to provide5
before the shields5
the settlement of5
up in the5
of the cast5
the time for5
and the heavy5
the year one5
required to be5
in the work5
the west shore5
of the vertical5
proportion of the5
were filled with5
excavation had been5
be issued in5
south of the5
used by the5
full width and5
extensions to the5
could be built5
it was very5
sufficient for one5
disposal of the5
the section of5
on plate xii5
per lineal foot5
the river bed5
into and through5
more than one5
where there were5
amount paid upon5
sums as may5
into the bins5
for the remainder5
to be deposited5
on one side5
increase of business5
the movement of5
was held in5
described in detail5
at the leading5
in the streets5
the air cylinders5
u d g5
the survey lines5
on june th5
cover over the5
out to the5
and part earth5
plans for the5
the first of5
east end heading5
terms of the5
of the sliding5
the transportation tax5
taken for the5
to the outside5
it does not5
to the railroad5
foot for the5
rock and earth5
character of the5
is made to5
passage of this5
development of the5
the stockholders of5
hereafter to be5
state control of5
of concrete lining5
of opinion that5
during the progress5
a short time5
of the land5
made upon the5
will be made5
the river line5
and twenty thousand5
be made for5
concrete for the5
on the hoosac5
and dumped into5
the date of5
and feet wide5
used as a5
the tunnel by5
long as the5
be necessary to5
and the remainder5
of the silt5
requirements of the5
just east of5
all the unavoidable5
material at the5
in some cases5
amounting to twenty5
less than ft5
through the shield5
at the central5
the original design5
with the tunnel5
the tunnel through5
eighth and ninth5
various operations involved5
and under the5
a section of5
also of the5
directly into the5
a single track5
be able to5
in the working5
the owners of5
a through line5
paid to said5
air from the5
under the charge5
the head of5
avenue and th5
i have no5
improvement of the5
close of the5
made of the5
tunnel for a5
western road was5
tunnel and troy5
such a consolidation5
and the total5
the whole state5
the development of5
about the same5
but they were5
terminus of the5
appointed by the5
be obtained by5
york and new5
to be about5
was placed under5
was also a5
of the scrip5
be applied to5
in the arch5
to put in5
facilities of the5
the minority bill5
the center heading5
cutting edge was5
the firm of5
were fitted with5
and shall be5
the balance of5
hydrostatic head at5
were authorized to5
only in the5
the edge of5
a committee of5
two of the5
a n r5
river bulkhead wall5
the loan act5
lining was put5
of his own5
until said company5
of more than5
hundred and eighty5
at least ft5
ninth and tenth5
of six hundred5
work was done5
g e e5
were left in5
it was desirable5
reason of the5
operated by a5
set in the5
movements of the5
near the shaft5
will not be5
on the amount5
the piston is5
and the operation5
at the new5
the lowest point5
such sums as5
a tendency to5
it should be5
consent of the5
the commissioners to5
from the shafts5
of a new5
a point on5
by the legislature5
of the majority5
new jersey and5
the pressure of5
had been placed5
temperature of the5
be at the5
was intended to5
amounting to eighty5
the rails shall5
act shall take5
to the satisfaction5
electrification of the5
the brick arch5
to the iron5
respect to the5
outline of the5
station of the5
rear of the5
in the town5
westerly side of5
and the average5
the other end5
in tunnels a5
had charge of5
is in the5
of labor and5
seemed to be5
to that of5
report to the5
had been done5
take possession of5
furnished by the5
of the cut5
new york shield5
majority of the5
of cast iron5
the work by5
can be made5
the state from5
pressure of the5
the commonwealth is5
and east rivers5
by the first5
were made to5
and the face5
to take the5
been paid by5
direct from the5
head at the5
the railroad commissioners5
from boston to5
of carrying out5
it consisted of5
tunnels east of5
to build a5
the contractors for5
pipes were built5
and jersey city5
east river to5
between ninth and5
and one of5
a large number5
platform of the5
to the center5
the lagging was5
between the first5
the application of5
bottom heading nov5
as the tunnel5
the burleigh machine5
during this period5
and the arch5
the average force5
a t i5
of each tunnel5
of water used5
determined by the5
the electrification of5
concrete was deposited5
the suspension of5
to the commissioners5
are given in5
from which the5
three per cent5
tunnel had been5
out from the5
the total length5
except in the5
which the concrete5
on april th5
on the top5
with compressed air5
enough to be5
the standard section5
from a point5
independent of the5
in the weehawken5
into the concrete5
described for the5
a large part5
it possible to5
end to the5
each and every5
one thousand eight5
the road from5
north side of5
in building tunnel5
the tunnels could5
the treasury of5
satisfaction of the5
the legislature of5
grout pipes were5
there were no5
of the permanent5
the blackwall tunnel5
payment of the5
been made to5
in the shaft5
the design of5
it might be5
in the meantime5
shall be added5
and tenth avenues5
means of the5
property to the5
a o o5
on november th5
table gives the5
that part of5
the hydraulic fittings5
of the masonry5
tunnel shall be5
avenue and the5
stock and bonds5
the center lines5
shall be appointed5
r b b5
limits of the5
on the long5
to the hoosac5
at a point5
road between greenfield5
the blacksmith shop5
side of seventh5
in this case5
thousand dollars shall5
large proportion of5
by the whole5
and property of5
feet of the5
be made by5
holes in the5
idea of the5
as they are5
year eighteen hundred5
carried down to5
prosecution of the5
relating to the5
that the tunnels5
inconsistent with the5
and the tunnels5
be made in5
wall of the5
the requirements of5
in river tunnels5
found in the5
extensions of the5
the temperature of5
running at rev5
diameter and ft5
can be no5
rock and part5