trigram

This is a table of type trigram and their frequencies. Use it to search & browse the list to learn more about your study carrel.

trigram frequency
the new york136
of the work131
of the tunnel120
part of the105
the top of103
in order to100
top of the99
of the shield99
side of the93
the pennsylvania railroad92
the bottom of91
end of the88
new york city86
bottom of the80
of the tunnels78
of the pennsylvania77
the construction of68
the long island68
the east river66
shown in fig65
face of the63
had to be63
the north river61
the face of59
as soon as55
the end of53
the weight of53
the shield was53
of the concrete53
weight of the53
the iron lining52
surface of the51
long island railroad49
the use of49
the cost of48
of the river48
the surface of48
portion of the47
construction of the47
as shown in45
due to the45
of the rock44
the concrete was43
on the new43
from to ft43
the work was43
on account of43
pennsylvania railroad company42
at the top42
long island city42
line of the42
of the wall42
of ninth avenue41
a distance of41
the rock was40
at the bottom40
so that the39
sides of the39
of the water39
east side of39
of the arch39
it was necessary38
the east side38
shown on plate38
the cutting edge38
a depth of38
of new york37
of the iron37
angle of repose37
at the same37
was necessary to36
east of the36
level of the36
as shown by35
the same time35
would have been35
section of the35
the terminal station35
account of the35
of d street35
of about ft35
of the new34
of civil engineers34
as to the34
and in the34
of the line34
and it was34
the concrete lining34
the excavation was33
society of civil33
shown by fig33
in the bottom33
the center line33
the rate of33
american society of33
connection with the32
the fact that32
of the excavation32
of the material32
of the sand32
west of the32
was to be32
on each side31
it will be31
of the same31
in d street31
the west side31
the rock surface31
of the long31
the railroad company31
attached to the31
in connection with31
the level of30
the air pressure30
in the tunnel30
there was a30
up to the30
soon as the29
the line of29
of the shaft29
on the north29
cost of the28
per linear foot28
found to be28
one of the28
as well as28
length of the28
owing to the28
so as to28
the weehawken shaft28
the center of28
the sides of27
the south side27
of the north27
in the tunnels27
some of the27
the length of27
back of the27
the metal lining27
outside of the27
engineer of the27
the number of26
on the south26
extension of the26
the time of26
a number of26
out of the26
chief engineer of26
the remainder of26
was put in26
earth and rock25
used in the25
it was not25
in front of25
remainder of the25
york tunnel extension25
the writer believes25
east river tunnels25
new york tunnel25
as far as25
as shown on25
it may be25
the river tunnels25
center of the25
the foot of25
could not be25
was found to25
front of the24
for a distance24
west side of24
it was found24
new york side24
shown on fig24
the work of24
in the rock24
of the terminal24
the case of24
pressure on the24
to a depth24
at the end24
of the ground24
in the case24
of the top24
of free air24
the north side24
of the american24
and d streets23
in which the23
in new york23
north river tunnels23
the amount of23
terminal station west23
on the surface23
the quantity of23
elevation of the22
rock bottom heading22
per cubic yard22
of the pier22
of the avenue22
of the face22
the board of22
to the top22
for the purpose22
on the east22
the soft ground22
the tunnels were22
below the surface22
b c d22
is shown on22
were to be21
by the writer21
the same as21
on the west21
on the sides21
cubic yards of21
the middle of21
of the city21
a b c21
center line of21
of seventh avenue21
completion of the21
on the other21
it was decided21
edge of the21
the removal of21
the excavation of21
use of the21
of the structure21
as it was21
bergen hill tunnels20
free air per20
on which the20
depth of ft20
the tunnel was20
the angle of20
in reinforced concrete20
there is a20
parts of the20
south side of20
the writer has20
sand and gravel20
investigations of mine20
on the manhattan20
the manhattan shaft20
and the other20
the shields were20
ends of the20
the elevation of20
the purpose of20
of the bottom19
the new jersey19
of the street19
position of the19
at elastic limit19
in advance of19
a capacity of19
tunnels under the19
a part of19
the manhattan side19
reinforced concrete design19
federal investigations of19
of mine accidents19
to a point19
to support the19
at the time19
to make the19
of the east19
questions in reinforced19
charge of the19
used on the19
writer believes that19
the base of19
is shown by19
that of the19
placed in the19
the question of19
was done by18
of the pipe18
was found that18
in the concrete18
the roof of18
the ends of18
the exception of18
at the rate18
shown by the18
of the rail18
portions of the18
special committee on18
the completion of18
of which was18
are shown on18
will be seen18
each of the18
was filled with18
van der hoek18
in soft ground18
height of the18
the placing of18
and it is18
with the exception18
this was done18
of from to18
on top of18
tunnel extension of18
which had been17
a pressure of17
pressure of lb17
civil engineers instituted17
of special committee17
transactions paper no17
from the bottom17
from to in17
at that point17
where it was17
features of the17
the hudson river17
instituted transactions paper17
distance of ft17
of the shields17
the sand and17
the retaining wall17
the method of17
on rail sections17
report of special17
to the new17
final report of17
base of the17
a and b17
in diameter and17
the pressure of17
in each tunnel17
the building of17
advance of the17
center to center17
were put in17
removal of the17
from center to17
the face was17
the point of17
quantity of water17
parallel to the17
in charge of17
committee on rail17
east and west17
an average of17
eastward from the17
most of the17
full page image17
tunnel and terminal17
engineers instituted transactions17
and on the17
resting on the17
in the top16
between seventh and16
president of the16
to the shaft16
it was thought16
new york division16
to the rock16
the results of16
connected with the16
was as follows16
of the caisson16
from to lb16
the american society16
location of the16
of sand and16
which it was16
member of the16
width of the16
of the cutting16
excavation of the16
rock surface was16
on the bottom16
of tenth avenue16
and terminal railroad16
as in the16
the pressure on16
in feet material16
of the first16
of the lining16
contact with the16
was decided to16
pennsylvania tunnel and16
sand and stone16
under the river16
work in the16
the space between16
of the south16
to the level16
each side of16
seventh avenue and16
new york central16
will be described16
at the point15
pressure of the15
it would have15
be seen that15
at the foot15
was placed in15
are shown in15
the form was15
shown in table15
a length of15
the city of15
the other hand15
to the river15
the width of15
placing of the15
put in place15
the tail of15
of the retaining15
the direction of15
to permit the15
roof of the15
on may th15
from the top15
new jersey side15
that it was15
and that the15
the street surface15
the position of15
of the west15
the depth of15
space between the15
by the contractor15
new york contracting15
the top and15
of the bench15
the north and15
and d street15
nature of the15
the erection of15
of the track15
north side of15
tail of the15
capacity of the15
access to the15
the caisson was15
that it is15
of the permanent15
description of the15
more or less15
to be taken15
the design of15
of the two15
there was no15
it should be15
the girders c15
a member of15
down to the15
lining of the14
in tunnel a14
the capacity of14
in long island14
and the rock14
in the river14
by the city14
the tunnels under14
to the west14
the lines of14
in the first14
crown of the14
of the latter14
was made to14
on the work14
the greater part14
the elevated railway14
caused by the14
by the railroad14
c b c14
air pressure was14
of the construction14
the crown of14
where there was14
the shield chambers14
division of the14
the bergen hill14
and tenth avenues14
in addition to14
is shown in14
the writer is14
ahead of the14
in the sand14
and of the14
to the bottom14
in this way14
diameter of the14
b c b14
mixed rock cut14
of the pile14
the outside of14
middle of the14
found that the14
made in the14
under the north14
ninth and tenth14
under ninth avenue14
of the total14
for the construction14
where the rock14
barrels of cement14
of the working13
between ninth and13
the heading was13
d street and13
together with the13
the weight on13
the sand was13
greater part of13
the back of13
of all the13
the tunnel lining13
a top heading13
was about ft13
from the face13
and ninth avenues13
side of ninth13
the head of13
and stability of13
of cement used13
lines of the13
similar to that13
it would be13
early part of13
the latter part13
to the east13
in this case13
on the side13
concrete lining was13
of the weight13
north river division13
r r r13
to the face13
not more than13
on either side13
the early part13
erection of the13
st and d13
to allow the13
with the new13
in contact with13
was carried on13
operation of the13
was used for13
in the early13
york contracting company13
in the center13
case of the13
it was then13
into the tunnel13
to be a13
to prevent the13
in the roof13
fact that the13
size of the13
new york and13
pressure in the13
were used for13
the beginning of13
the rest of13
from the east13
south of the13
the rock and12
as the shield12
on girders c12
similar to those12
tracks of the12
of the hudson12
so that it12
rest of the12
the holes were12
under the direction12
r a m12
the meadows division12
to that of12
filled with concrete12
the contractor for12
work on the12
r r a12
the hudson and12
in open cut12
the upper part12
the progress of12
view of the12
the escape of12
latter part of12
the american railway12
of the caissons12
in the form12
assumed to be12
details of the12
the shield and12
of new jersey12
at intervals of12
settlement of the12
in this paper12
lines and grades12
to ninth avenue12
material in the12
loss of air12
by the pennsylvania12
to the center12
temporary shoring girders12
directly from the12
east river division12
it would seem12
g g g12
the bridge seat12
e p e12
each pair of12
muck loaded by12
h h h12
of the metal12
rock on the12
in some cases12
of the form12
in the latter12
o o t12
in cubic yards12
to be made12
to keep the12
grade of the12
more than ft12
e e p12
and about ft12
the lower part12
there is no12
were used in12
table part w12
the thickness of12
and the work11
water in the11
well as the11
for the first11
at a depth11
of this section11
any of the11
had been removed11
and the excavation11
that the pressure11
the soft material11
for this purpose11
the rear of11
the size of11
of the wood11
of the bridge11
in the paper11
to be used11
board of engineers11
at the face11
depth of about11
to have been11
the limits of11
the bench was11
in the field11
at right angles11
the water supply11
the west line11
at a time11
the pennsylvania tunnel11
d and d11
seventh and eighth11
at one time11
were built in11
north and south11
pressure due to11
taken from the11
a section of11
of st street11
the time the11
of one of11
elevated railway structure11
in case of11
order to prevent11
a point ft11
the retaining walls11
west line of11
contractor for the11
the west end11
on the top11
there were no11
to be the11
it could be11
out of rock11
the excavation for11
at the meeting11
heading was driven11
on the line11
under the east11
made by the11
in the contract11
braced from the11
thickness of key11
sections of the11
when it was11
half of the11
in the same11
time per ring11
in the north11
equal to the11
the point where11
lower part of11
placed on the11
the work in11
of the lower11
an angle of11
of the piston11
the rapid transit11
were filled with11
either side of11
and construction of11
the pressure was11
c and d11
weight on the11
and at the11
excavation had been11
stability of earth11
heading and bench11
is to be11
the average time11
hudson and manhattan11
as long as11
proved to be11
at about the11
from seventh avenue11
the meeting of11
wall of the11
to the writer11
to the fact11
on the drivers11
the result of11
similar to the11
the presence of11
in excess of11
concrete water tower10
of the most10
of the board10
the disposal of10
the intercepting arch10
to the contractor10
on june th10
at the beginning10
memoir prepared by10
of the ring10
was elected a10
holes were drilled10
the grade of10
mean high water10
was thought that10
an elevation of10
removed and the10
iron lining of10
and to the10
that it would10
it is not10
of the tower10
far as possible10
felt and pitch10
of the railroad10
two or three10
of the tank10
the author has10
the loss of10
on the ground10
the permanent viaduct10
drilling and blasting10
to carry the10
of the entire10
in order that10
in view of10
under d street10
the pipe line10
b and d10
direction of the10
the operation of10
be noted that10
temperature of the10
into new york10
the material in10
progress of the10
shield was shoved10
top and bottom10
but it was10
foot of the10
to the tunnel10
less than the10
ninth avenue and10
in the east10
given in table10
should not be10
avenue and d10
a short distance10
paso and southwestern10
the nature of10
of the heading10
and the iron10
el paso and10
done by the10
maintenance of way10
and eighth avenues10
in normal air10
as chief engineer10
first and thirty10
on the outside10
concrete was placed10
there were three10
per square foot10
character of the10
escape of air10
having a capacity10
the el paso10
presented at the10
the work to10
the solid material10
the d street10
the excavation had10
seen that the10
up on the10
the land tunnels10
used for the10
building of the10
the company to10
a system of10
of the old10
on july th10
head of the10
cubic yard of10
locomotive performance on10
were set up10
the temperature of10
a few feet10
the atlantic avenue10
the application of10
in the face10
was divided into10
much of the10
the roof was10
by the author10
that there is10
of the time10
and western railroad10
seventh avenue to10
between the tunnels10
up to a10
the working chamber10
columns in table10
the tunnels and10
the first avenue10
work of the10
all the work10
the side of10
when the shield10
of the cost10
in such a10
believed to be10
of which were10
in the south9
bottom heading oct9
floor of the9
the specifications required9
diameter and ft9
to from to9
by the use9
t r o9
large quantity of9
to be done9
regard to the9
execution of the9
were taken out9
u t t9
and for the9
the ninth avenue9
exception of the9
floors of the9
the cutting edges9
rear of the9
two on the9
e i i9
of the company9
of the section9
end of each9
many of the9
in the invert9
line of ninth9
flanges of the9
had been driven9
as it is9
t i s9
to avoid the9
i r r9
the bore segments9
the section of9
from which the9
l n n9
of the upper9
amount of excavation9
north of the9
at a point9
i i a9
city of new9
i l t9
of the plant9
seemed to be9
was of the9
in accordance with9
it had been9
s i o9
the central track9
at the rear9
in pounds per9
in in in9
of the center9
number of cubic9
the installation of9
weight on drivers9
of the manhattan9
the east line9
n n n9
by steam shovel9
be used in9
there were two9
loaded by hand9
of various lengths9
at the north9
one or two9
of fifth avenue9
appear to be9
and this was9
of cubic yards9
at one end9
york connecting railroad9
at the manhattan9
to the tunnels9
per square inch9
air per minute9
of first avenue9
for some time9
the sunnyside yard9
line between the9
the united states9
at least ft9
from the west9
and also to9
and they were9
it is impossible9
a concrete water9
will be found9
and the east9
which was the9
at d street9
to be removed9
in the open9
rock center heading9
g g s9
h l u9
the river shafts9
l t r9
right angles to9
would not be9
the excavation on9
d g i9
of the earth9
point where the9
d g g9
the springing line9
terminal railroad company9
in the streets9
was started on9
to be built9
from long island9
on the upper9
of the surface9
was used in9
to the shield9
are to be9
the two tunnels9
lumber in feet9
made up of9
west end of9
atlantic avenue improvement9
the present time9
have been described9
was taken out9
was attached to9
distance of about9
soft ground was9
the water was9
the location of9
a matter of9
and from the9
the rock at9
and southwestern railway9
not less than9
new york connecting9
elevated railway columns9
on december th9
on the center9
transferred to the9
were replaced by9
the duct bench9
work was done9
which may be9
on october th9
east line of9
time taken to9
avenue to the9
as resident engineer9
full face of9
and long island9
directly to the9
the details of9
in the crown9
to be laid9
for use in9
bridge over the9
attempt was made9
the work under9
average time taken9
air per min9
to the surface9
mixed bottom heading9
i a t9
cost of labor9
during the period9
the concrete in9
the right to9
in the upper9
performance on grades9
to and from9
of the paper9
in a manner9
tunnels b and9
the shield method9
l u t9
l table part8
when the shields8
the members of8
and brown on8
through the soft8
were left in8
the possibility of8
the transverse girders8
the weehawken side8
the inside bucket8
the plane of8
the water in8
the central rock8
west of ninth8
placing the concrete8
by the board8
g s l8
and the north8
in tunnel b8
for the full8
the shield had8
concrete was deposited8
by the shield8
of the ingot8
length of time8
which could be8
by far the8
above the tunnel8
and the shield8
rate of progress8
of the cast8
the tunnel and8
the concrete and8
furnished by the8
o between length8
and the average8
of the pressure8
duct bench concrete8
lock bulkhead wall8
by the tunnel8
it is also8
to be about8
hewett and brown8
to the depth8
of compressed air8
made for the8
could have been8
to form a8
the hydrostatic head8
on d street8
beginning of the8
was made by8
sand and water8
grades of various8
the pipe was8
street to the8
and had to8
a tendency to8
of linear in8
central rock core8
table summary part8
on grades of8
and the face8
the commencement of8
elected a member8
and maintenance of8
upper part of8
n rings in8
first avenue shafts8
by the fact8
to determine the8
of the main8
the tendency of8
the total weight8
in this work8
linear in feet8
passenger and freight8
less than ft8
operated by a8
into the shield8
to be placed8
in queens borough8
the thrust of8
were made in8
the twin tunnel8
island railroad company8
not to be8
civil engineers on8
pearson and son8
method of construction8
of the roof8
removed from the8
the stability of8
feet material e8
the arch was8
which will be8
that the concrete8
shown in the8
large part of8
rings in feet8
in the lower8
was in progress8
angles to the8
on april th8
junction of the8
at that time8
on both sides8
was placed on8
about of the8
between the two8
the ducts were8
total cost of8
number progress of8
the sinking of8
pair of tunnels8
of the various8
to lift the8
the wall was8
a period of8
jersey city station8
in the middle8
plan and profile8
known as the8
shown by figs8
the form of8
two of the8
the most important8
average rate of8
the necessity of8
wide and ft8
the intermediate shafts8
addition to the8
rock at the8
to the north8
as much as8
described under the8
the ground was8
harrison transfer station8
of each other8
the state of8
should be made8
tunnels from the8
of the piles8
th street and8
r method of8
and manhattan railroad8
line of seventh8
the shaft was8
length r method8
progress of linear8
the various operations8
in st street8
excavation for the8
far as the8
in the original8
a n rings8
in spite of8
of the trestle8
of number progress8
of repose of8
i o o8
to the water8
of the hood8
from this point8
organization of the8
work was carried8
consisted of a8
in tunnel d8
in the shield8
constructed under the8
of the grade8
brown on pennsylvania8
can be found8
of the pump8
of the viaduct8
was supported by8
were placed on8
the pump chamber8
between length r8
were as follows8
tendency of the8
r section u8
the hackensack river8
on pennsylvania r8
in the construction8
the material was8
quantity of muck8
walls of the8
of the project8
the skin friction8
one of these8
except that the8
is that the8
iron tunnel lining8
against the face8
after the concrete8
in the street8
and stone were8
placed under the8
for top charges8
of the former8
as the concrete8
rate of number8
from the tunnels8
the joints were8
tunnels and the8
rods in the8
by means of8
the execution of8
average cost per8
the concrete arch8
water from the8
could be done8
the surface and8
on the weehawken8
it necessary to8
this work was8
the junction of8
to bring the8
n n a8
in other words8
the tops of8
rate of grade8
material e excavation8
description in gang8
to the weight8
excavation was completed8
area of the8
because of the8
the latter was8
to the weehawken8
at each end8
of the sump8
below mean high8
supply of the8
had been built8
in tunnel c8
at each plant8
at tenth avenue8
of wood pipe8
this method was8
of the trench8
of the ducts8
according to the8
the excavated material8
from the first7
harrison transfer yard7
the stone was7
was done with7
to receive the7
to be much7
had been completed7
lining was placed7
of the actual7
was desired to7
and through the7
form for the7
to santa rosa7
the walls of7
side of st7
which they were7
made with the7
the new england7
line of d7
york central railroad7
load and deflection7
air cylinders were7
the water pressure7
company and the7
was done in7
filled with water7
for this reason7
held in place7
to the pressure7
had been excavated7
the face and7
a e e7
it is the7
and as the7
was carried out7
occupied by the7
and from to7
in compressed air7
it was the7
square foot of7
of the streets7
has taken place7
the masonry lining7
will be given7
which is the7
believes that the7
for a short7
forms for the7
the bolt holes7
of excavation was7
the laying of7
it does not7
the chief engineer7
of the building7
of the cut7
in the summer7
appears to be7
of the four7
the portion of7
made to the7
at a pressure7
to reduce the7
be taken out7
the following is7
of the station7
as compared with7
divided into two7
to full size7
certain amount of7
from the station7
this part of7
to be excavated7
level with the7
water supply of7
the tunnels to7
all rock bottom7
the pumping main7
given by the7
deck of the7
change in the7
the total cost7
and thence to7
limits of the7
house line of7
in the air7
railroad of new7
on march th7
filled with grout7
loaded by steam7
left in place7
to which the7
no attempt was7
the floors of7
from carrizozo to7
of the steel7
be found in7
was less than7
the character of7
the water to7
the sand is7
they were used7
had been made7
during the progress7
the period of7
r e a7
carrizozo to santa7
work in tunnel7
the th street7
prior to the7
the earth was7
a variation of7
under the hudson7
of the shafts7
wall was built7
surface railway structure7
of the other7
the roof and7
and the tunnels7
american railway engineering7
reference to the7
be able to7
of the standard7
of damage done7
the contract for7
at fifth avenue7
it can be7
was fitted with7
on the rock7
a layer of7
a r section7
long as the7
it was desirable7
and the long7
shown on the7
mean total deflection7
the design and7
and deflection log7
thickness of the7
at the other7
the driving of7
the height of7
of the flanges7
to place the7
soft ground in7
obtained from the7
buried in the7
except in the7
of his death7
large number of7
he was a7
engineering and maintenance7
had been done7
determined by the7
for the upper7
in the following7
a series of7
company for the7
of a large7
for the new7
the time taken7
kinds of ground7
a certain amount7
tunnels of the7
portions of thirty7
by reason of7
inside of the7
the south shaft7
on flat cars7
design of the7
the harrison transfer7
of the engineering7
out to the7
from to from7
through the tunnel7
was taken up7
and therefore the7
it was possible7
the shields in7
to give a7
state of new7
three or four7
the south tunnel7
from the river7
shoving the shield7
of which the7
of this work7
and face walls7
d a b7
the face wall7
the erie railroad7
the tunnel company7
soon after the7
day and night7
earth pressure and7
work was finished7
was at first7
girders c were7
was built in7
had not been7
engineer in charge7
at long island7
streets and avenues7
a height of7
for the long7
after which the7
in driving the7
the material above7
a and c7
long and ft7
as a result7
in regard to7
the contractor was7
site of the7
for the various7
could be made7
the handling of7
been made in7
in the water7
clear of the7
before the concrete7
to remove the7
both sides of7
fastened to the7
time of his7
deflecton curves beam7
for the tunnels7
expansion of pipes7
the underside of7
axis of the7
those in the7
the flow of7
all parts of7
y r n7
pounds per square7
in all cases7
the axis of7
by compressed air7
structure of the7
be made for7
cut in the7
air pressure in7
the tunnel extension7
in the design7
angles of repose7
rock cover was7
miles of the7
of the hill7
control of the7
work under the7
the resident engineers7
the arrangement of7
section can be7
he was graduated7
close to the7
the rock to7
on the elevated7
at this point7
are given in7
d street to7
of the el7
of the length7
a short time7
was intended to7
of eighth avenue7
required to lift7
the concrete had7
increase in the7
filled with sand7
be described in7
east river and7
it was desired7
the tracks of7
the river tunnel7
railway engineering and7
lackawanna and western7
application of the7
sand in the7
lining of shield7
were of the7
the adoption of7
part of this7
the rear end7
at an elevation7
a bottom heading7
where there were7
the portions of7
the tunnel line7
above the top7
as may be7
the tunnel in7
d b b7
was supported on7
the distance between7
the filtered water7
tunnel under the7
practically all the7
the lehigh valley7
water at the7
permanent viaduct girders7
property of the7
construction of a7
the same general7
the effect of7
a total of7
of this paper7
support of the7
the tunnels are7
at the west7
of way association7
to the full7
tests of creosoted7
the rock in7
extending from the7
and jersey city7
southwestern railway from7
independently of the7
from the shield7
n r r7
the paper by7
railway from carrizozo7
c d a7
is impossible to7
at the south7
that portion of7
when the excavation7
to be very7
of the cross7
seventh and ninth7
location and construction7
with regard to7
top of rail7
edges of the7
on one side7
from the weehawken7
as they were6
on plate xiii6
of the rings6
a typical cross6
east of seventh6
the diameter of6
tunnels at the6
to the time6
to an average6
to th street6
engineering and contracting6
noted in the6
sent to the6
as for the6
iv iv iv6
was allowed to6
within the limits6
and the time6
new york station6
the cars were6
borings were made6
accordance with the6
for a time6
were placed under6
e a n6
in eighth avenue6
with the pennsylvania6
lehigh valley railroad6
in tunnels b6
the electrification of6
encountered in the6
they were set6
to complete the6
below the top6
driven from the6
the pennsylvania station6
concrete pier construction6
lining and the6
from the manhattan6
the streets and6
of that company6
be found by6
the vicinity of6
and new jersey6
will show that6
action of the6
the necessity for6
the movement of6
i i i6
intervals of about6
for that section6
indicate that the6
work to be6
and the weight6
flow of water6
the distance of6
the shutters were6
retaining and face6
of the ordinary6
directly into the6
united engineering and6
approved by the6
the working face6
worked by a6
it is believed6
of the bulkhead6
the upper deck6
have to be6
the course of6
in experiment no6
map and profile6
for more than6
to the work6
of the above6
east new york6
of the pipes6
was covered with6
and the material6
the river bed6
of the present6
of the full6
and th street6
were then placed6
the front of6
bearing on the6
cement and sand6
per cubic foot6
in from the6
which the writer6
that at the6
by the construction6
long island shafts6
across the river6
engineer for the6
the united engineering6
that the sand6
is thus seen6
of the holes6
american railway association6
is believed to6
would seem as6
the basis of6
the sum of6
th street pier6
on the lower6
variation of ft6
of work in6
it was finally6
as determined by6
by james h6
iii iii iii6
on november th6
the permanent steel6
movement of the6
foot of d6
cost per cubic6
the wood pipe6
the materials were6
the top was6
had been taken6
viaducts or bridges6
out from the6
set in the6
was a small6
new jersey and6
that the results6
at the pier6
or to the6
as great as6
line to the6
the north tunnel6
the iron and6
of the intercepting6
had been used6
there will be6
on a timber6
out by the6
the bents were6
left in the6
have been made6
he does not6
of the bents6
on february th6
between it and6
the benefit of6
until after the6
the land tunnel6
long island shaft6
avenue to ninth6
used in any6
the unavoidable delays6
as a matter6
under contract dated6
the first and6
that the arching6
to provide for6
to the track6
just east of6
of the division6
flatbush avenue terminal6
the south abutment6
may be of6
the tunnel to6
a portion of6
through which the6
side of tenth6
result of the6
order to allow6
there would be6
there are two6
the plans for6
for the whole6
all of the6
to the grade6
sunk to a6
at manhattan was6
to have a6
all structures were6
condition of the6
line of tenth6
placed at the6
for the entire6
westward from the6
to new york6
over the new6
of the intermediate6
the support of6
ends of these6
holes in the6
is capable of6
skin friction on6
covered by the6
a large part6
of retaining wall6
to the lower6
cutting edge of6
the rock cover6
and the bottom6
avenue and the6
of the period6
a large quantity6
during this period6
adjacent to the6
they were of6
just west of6
braced to the6
that could be6
the flanges of6
der hoek was6
record of retaining6
he was elected6
was also a6
for the disposal6
built into the6
the sump segment6
the location and6
where they were6
provided for the6
order to provide6
and contracting company6
of the way6
compared with the6
and then the6
of ground encountered6
described in the6
set up on6
side of d6
the north shaft6
into the rock6
that section in6
then put in6
streets or avenues6
it is a6
to be of6
to which it6
and also the6
were made of6
at the east6
caulking and grummeting6
in the walls6
of the pit6
order that the6
the full width6
total average cost6
soon as possible6
large amount of6
a description of6
and west of6
reinforced concrete pier6
be placed in6
of the test6
at all times6
resulted in a6
and all the6
hole in the6
between stations and6
the sections of6
of a heavy6
load on pile6
just before the6
on september th6
the average force6
ii ii ii6
could be obtained6
the action of6
whole of the6
as high as6
the sliding platform6
use of a6
greater than the6
the hydraulic grade6
not be used6
the shield advanced6
to be at6
table gives the6
the shield could6
above the bottom6
and the air6
retaining wall was6
when the angle6
was due to6
of the last6
to the other6
were made by6
the distance piece6
total length of6
for labor and6
was held in6
it to be6
the same manner6
through the sand6
from station to6
electrification of the6
the shields had6
the average rate6
east of ninth6
the false bottom6
was required to6
sized twin tunnel6
to have the6
of the meadows6
the southern pacific6
is due to6
but it is6
retaining walls in6
those on the6
lines a and6
tunnels a and6
section of concrete6
the bearing value6
of this kind6
bench concrete was6
the part of6
no arch action6
north river bridge6
driven tunnel work6
used as a6
for the tunnel6
as fast as6
the river was6
that the rock6
as the work6
was then taken6
pressure against the6
as the rock6
of the opening6
in the larger6
than the standard6
the leading end6
at this time6
were erected on6
excavated material was6
the percentage of6
was excavated to6
the east and6
engineering construction company6
for the lower6
the forms and6
and the railroad6
of more than6
of these tunnels6
permanent steel viaduct6
it might be6
v e j6
the pressure is6
of the reef6
should have been6
the bottom heading6
the arch were6
of th ave6
by a single6
ducts were laid6
with sand and6
stone and sand6
full width and6
in any section6
possible to the6
brought up to6
of the beam6
be described later6
where the tunnels6
the companies are6
tunnels c and6
the hydraulic method6
and subjected to6
without caulking pockets6
given to the6
total field charges6
the horizontal diameter6
the development of6
which he was6
in position and6
the load on6
the edge of6
a timber trestle6
was replaced by6
not include the6
has been made6
that in the6
it and the6
were made with6
of the sides6
of bore segments6
shield could be6
of the whole6
was being done6
on the same6
depending on the6
the forms were6
as possible to6
of cement and6
and profile of6
two sets of6
be required to6
enough to permit6
was transferred to6
ultimate load on6
members of the6
the tunnels in6
the site of6
posts were placed6
to the present6
and by the6
found by multiplying6
erection of shield6
river to the6
the nogal reservoir6
thrust of the6
at th street6
ground in the6
as a rule6
shape of the6
back to the6
any section can6
and the whole6
to the point6
the extent of6
the pier was6
in the two6
to form the6
same manner as6
the pier head6
matter of fact6
does not seem6
by which the6
as the tunnel6
of each section6
for the excavation6
of the completed6
as to bring6
described for the6
to the terminal6
the contract was6
concrete for the6
subjected to a6
by the new6
length of about6
the lining was6
rock middle heading6
for the work6
the performance of6
side of th6
telephone and telegraph6
cement used for6
with compressed air6
rock and earth6
pressure and stability6
the whole of6
tops of the6
the forms for6
the total length6
of tunnel was6
described in this6
excavation on the6
from that time5
of this class5
general electric motor5
use in the5
center line between5
be stated that5
were in place5
the solid rock5
this is shown5
to be set5
all excavated material5
treatment of the5
lined with concrete5
the average progress5
h e a5
the average number5
pressure per square5
of deceased members5
in the floor5
the bottom and5
form of a5
number of the5
committee of the5
to eighth avenue5
in the vicinity5
were used on5
joints of the5
station to the5
of weight on5
in the side5
from the shafts5
were built on5
bottom heading nov5
the tractive power5
had been placed5
was more than5
through the form5
from tenth avenue5
a very large5
by the resident5
the bottom was5
by the tangent5
the practicability of5
three sets of5
and supported on5
the ordinary type5
the test pieces5
described in a5
of the late5
was one of5
was finally decided5
to reach the5
contract was let5
the friction of5
multiplied by the5
the late a5
before the shields5
as will be5
was loaded by5
as the sand5
from the shaft5
was desirable to5
which the concrete5
in conjunction with5
street and north5
nailed to the5
made of the5
could be built5
a n r5
the typical working5
on the completion5
was made up5
on plate xii5
in segment no5
tunnel a and5
for the east5
vicinity of the5
of the outside5
the influence of5
he was engaged5
work was in5
to the sides5
the east house5
twice as great5
s e i5
weight per cubic5
forms were removed5
and dumped into5
into the concrete5
was excavated in5
at eleventh avenue5
pipes were built5
the station and5
a piece of5
memoirs of deceased5
seems to be5
through the shield5
the total quantity5
bottoms of the5
the tunnel lines5
the dome and5
a structure of5
to extend the5
the rock excavation5
r b b5
are of the5
the center lines5
in the filtered5
d annual convention5
the cable conduits5
done in the5
the street level5
linear foot of5
the pressure to5
referred to above5
in clear water5
the whole gang5
were made to5
excavated to full5
have been a5
the difficulty of5
and chief engineer5
on the basis5
previously referred to5
in the trench5
driving of the5
about the same5
excavation of rock5
the tunnel excavation5
time he was5
the lack of5
and under the5
from the tunnel5
of the land5
east house line5
the whole length5
the tunnels was5
in the state5
that of a5
by the weight5
of brooklyn and5
that the work5
in a few5
along the tunnel5
referring to the5
that the tunnels5
york and new5
the box drains5
the surface was5
had been carried5
muck from the5
directly over the5
to cover the5
a large number5
of earth and5
see that the5
east end of5
the other two5
on the tunnels5
interfere with the5
the last ring5
to within ft5
slope of the5
partly filled with5
the shield chamber5
pressure would be5
be well to5
one end of5
in river tunnels5
dumped into the5
as the water5
river tunnels was5
was constructed under5
chief assistant engineer5
the disposal trestle5
would seem that5
of the church5
york central and5
of interest to5
direct from the5
the tunnels would5
work is shown5
by the two5
excess of the5
of the angle5
being put in5
there can be5
of the surrounding5
the work the5
tests were made5
the tangent of5
tunnel had been5
and bracing for5
and a large5
tunnel to be5
a t i5
constructed in the5
tunnel at the5
a static theory5
the under side5
with which the5
the settlement of5
about the middle5
for this work5
address at the5
only in the5
in many cases5
along the lines5
terminal of the5
covered by a5
extensions to the5
of electric traction5
of the d5
made it possible5
through the concrete5
of the sliding5
four or five5
that the piston5
of concrete in5
under the same5
the writer that5
and the operation5
which were placed5
several kinds of5
the floor of5
would have to5
back into the5
be made in5
nearly all the5
rock in the5
the tank is5
the summer of5
should be noted5
that there would5
in the last5
and hudson river5
iron lining was5
was done at5
into the sand5
in which case5
carried on by5
the grade line5
which does not5
full width of5
tunnel through the5
those at the5
the piston was5
he was employed5
inside diameter of5
of clay was5
a grade of5
running at rev5
brought into the5
taken to the5
evident that the5
head at the5
up in the5
were carried on5
the path of5
typical working force5
york and long5
to allow for5
voids in the5
respect to the5
on the long5
same as the5
that the water5
the joints between5
was impossible to5
railroad company for5
placed in position5
reason of the5
to the iron5
the extent and5
plans for the5
and the general5
the bottoms of5
between the first5
air from the5
the hackensack meadows5
be considered as5
to be put5
and the heavy5
with the bottom5
described in detail5
was made for5
from under the5
on august th5
various operations involved5
west d street5
at the leading5
will be noted5
the entire length5
entire length of5
the difference in5
hydrostatic head at5
the concrete on5
friction on piles5
the concrete walls5
order to make5
by the company5
to make a5
concrete lining of5
east of shaft5
the deck of5
was taken from5
at track level5
installation of the5
the form for5
to be in5
of the vertical5
eighth and ninth5
by the united5
point of the5
be made to5
of concrete lining5
at first avenue5
he was also5
and the water5
in d and5
it was to5
points where the5
was made in5
all the unavoidable5
thus seen that5
sand used in5
and the writer5
the outside tracks5
over the tunnels5
the work is5
the muck was5
carried down to5
each of these5
at the center5
spent by the5
the east end5
grout pipes were5
time for jacks5
to more than5
d streets were5
at frequent intervals5
to erect the5
the line was5
was caused by5
independent of the5
of which are5
the bay ridge5
a large amount5
from the heading5
on the permanent5
of the high5
of the original5
tests of the5
that the arch5
by a system5
of the results5
at the d5
the hydraulic fittings5
concrete had set5
in gang i5
supplied by the5
were plastered with5
tunnel extension project5
concrete was mixed5
with the design5
the tunnels at5
the lowest point5
may be said5
the tunnels could5
of creosoted timber5
carried by the5
friction of the5
in solid rock5
idea of the5
separated by a5
distance of the5
placed on it5
more than lb5
appears to have5
the charge of5
yard of the5
of the silt5
the sand in5
line and grade5
in any way5
of the air5
central and hudson5
a o o5
rock and part5
by multiplying the5
to be considered5
the addition of5
in this manner5
manhattan railroad company5
york shield chambers5
and so on5
suspended from the5
the points where5
of the shove5
including time for5
avenue and th5
between coyote and5
the latter being5
from jersey city5
line on the5
the organization of5
in tunnels a5
extent and nature5
for the same5
to the construction5
of repose is5
hours and min5
also the extent5
of the bergen5
was graduated in5
of labor in5
were supported on5
the stone and5
and two on5
the blackwall tunnel5
shown on general5
provide for the5
provided with a5
from new york5
while in the5
in all the5
the water from5
the web of5
of the twin5
from the center5
the latter is5
the river lines5